Order of the President of the General Court of 26 March 2010 - Sviluppo Globale v Commission

(Case T-6/10 R)

(Interim measures - Public contracts -Tendering procedure - Rejection of tender - Application for suspension of operation and interim measures - Loss of opportunity - Lack of serious and irreparable harm - Lack of urgency)

Language of the case: Italian

Parties

Applicant: Sviluppo Globale GEIE (Rome, Italy) (represented by: F. Sciaudone, R. Sciaudone and A. Neri, lawyers)

Defendant: European Commission (represented by: P. Costa de Oliveira, F. Erlbacher and P. Manzini, Agents)

Re:

Application for interim measures concerning call for tenders EUROPEAID/127843/D/SER/KOS for the provision of support services to the customs and tax authorities in Kosovo.

Operative part of the order

1.    The application for interim measures is dismissed.

2.    The costs are reserved.