Language of document : ECLI:EU:T:2010:323





Order of the President of the General Court of 29 July 2010 – Cross Czech v Commission

(Case T-252/10 R)

Application for interim measures – Sixth Framework Programme for research, technological development and demonstration activities – Letter confirming the findings of a financial audit – Application for suspension of operation of a measure – Disregard of formal requirements – Inadmissibility

1.                     Application for interim measures – Suspension of operation of a measure – Interim measures – Conditions for granting – Prima facie case – Urgency – Serious and irreparable damage – Cumulative nature – Discretion of the judge dealing with the application for interim relief (Arts 278 TFEU and 279 TFEU; Rules of Procedure of the General Court, Art. 104(2)) (see paras 7-8)

2.                     Application for interim measures – Formal requirements – Submission of applications – Brief summary of the pleas in law on which the application is based – Pleas not set out in the application and pleadings – General reference to documents – Inadmissibility (Arts 278 TFEU and 279 TFEU; Rules of Procedure of the General Court, Arts 44(1)(c) and 104(3)) (see paras 9-16)

Re:

APPLICATION for suspension of operation of the Commission’s letter of 12 March 2010 confirming the findings of the audit of financial statements submitted by the applicant for the period from 1 February 2005 to 30 April 2008 in respect of the eMapps.com, CEEC IST NET and Transfer-East projects.

Operative part

1.

The application for interim measures is dismissed.

2.

Costs are reserved.