Judgment of the General Court of 10 July 2012 - Interspeed v Commission

(Case T-587/10) 

(Non-contractual liability - External relations - Call for tenders issued by the EAR concerning work at the Preševo (Serbia) border crossing, the financing of the works and other connected measures - No causal link)

Language of the case: Slovenian

Parties

Applicant: Holding kompanija Interspeed a.d. (Belgrade, Serbia) (represented by: M. Bošnjak, lawyer)

Defendant: EuropeanCommission (represented by: F. Erlbacher and B. Rous, Agents)

Re:

Application for the compensation of damage allegedly resulting from works carried out at the Preševo (Serbia) border crossing under a contract financed by the EAR.

Operative part of the judgment

The Court:

Dismisses the action;

Order Holding kompanija Interspeed a.d to bear its own costs and to pay those incurred by the European Commission.