Language of document : ECLI:EU:T:2018:929

JUDGMENT OF THE GENERAL COURT (Ninth Chamber, Extended Composition)

13 December 2018 (*)(1)

(Competition — Abuse of dominant position — Slovakian market for broadband telecommunications services — Access by third-party undertakings to the ‘local loop’ of the incumbent operator on that market — Decision finding an infringement of Article 102 TFEU and Article 54 of the EEA Agreement — Single and continuous infringement — Definition of ‘abuse’ — Refusal to grant access — Margin squeeze — Calculation of margin squeeze — Equally efficient competitor test — Rights of defence — Imputation of an infringement committed by a subsidiary to its parent company — Decisive influence of the parent company over the subsidiary’s commercial policy — Actual exercise of such influence — Burden of proof — Calculation of the fine — 2006 Guidelines on the method of setting fines)

In Case T‑851/14,

Slovak Telekom, a.s., established in Bratislava (Slovakia), represented by D. Geradin, lawyer, and R. O’Donoghue QC,

applicant,

v

European Commission, represented initially by M. Farley, L. Malferrari and G. Koleva, and subsequently by M. Farley, M. Kellerbauer, L. Malferrari and C. Vollrath, acting as Agents,

defendant,

supported by

Slovanet, a.s., established in Bratislava, represented by P. Tisaj, lawyer,

intervener,

ACTION under Article 263 TFEU seeking, primarily, the annulment, insofar as it concerns the applicant, of Commission Decision C(2014) 7465 final of 15 October 2014 relating to proceedings under Article 102 TFEU and Article 54 of the EEA Agreement (Case AT.39523 — Slovak Telekom), as rectified by Commission Decision C(2014) 10119 final of 16 December 2014 and by Commission Decision C(20 15) 2484 final of 17 April 2015, and, in the alternative, the reduction of the fine imposed on the applicant,

THE GENERAL COURT (Ninth Chamber, Extended Composition),

composed M. van der Woude, acting as President, S. Gervasoni, L. Madise, R. da Silva Passos (Rapporteur) and K. Kowalik-Bańczyk, Judges,

Registrar: N. Schall, Administrator,

having regard to the written part of the procedure and further to the hearing on 26 April 2018,

gives the following

Judgment

I.      Background to the dispute

1        The applicant, Slovak Telekom, a.s., is the incumbent telecommunications operator in Slovakia. Deutsche Telekom AG, the incumbent telecommunications operator in Germany and the company at the helm of the Deutsche Telekom group, acquired a 51% stake in the applicant on 4 August 2000, a shareholding which it held throughout the relevant period in this case. The remaining shareholding in the applicant was held by the Ministry of Economy of the Slovak Republic (34%) and the National Property Fund of the Slovak Republic (15%).

2        On 15 October 2014, the European Commission adopted Decision C(2014) 7465 final relating to proceedings under Article 102 TFEU and Article 54 of the EEA Agreement (Case AT.39523 — Slovak Telekom), rectified by its Decision C(2014) 10119 final of 16 December 2014 and by its Decision C(2015) 2484 final of 17 April 2015, which was addressed to the applicant as well as to Deutsche Telekom (‘the contested decision’). On 24 December 2014, Deutsche Telekom brought an action also seeking annulment of the contested decision (Case T‑827/14).

A.      Technological, factual and regulatory context of the contested decision

3        The applicant, which is the indirect successor of the public post and telecommunications undertaking that ceased to exist in 1992, is the largest telecommunications operator and broadband provider in Slovakia. The legal monopoly it enjoyed on the Slovakian telecommunications market came to an end in 2000. The applicant offers a full range of data and voice services, and owns and operates fixed copper and fibre optic networks as well as a mobile telecommunications network. The copper and mobile networks cover almost the entire territory of Slovakia.

4        The contested decision concerns anticompetitive practices on the Slovakian market for broadband internet services. In essence, it relates to the conditions set by the applicant for unbundled access of other operators to the copper local loop in Slovakia between 2005 and 2010.

5        The local loop is the physical twisted metallic pair circuit (also known as ‘the line’) connecting the network termination point at the subscriber’s premises to the main distribution frame or equivalent facility in the fixed public telephone network.

6        Unbundled access to the local loop allows new entrants — usually called ‘alternative operators’, as opposed to the incumbent operators of the telecommunications networks — to use the pre-existing telecommunications infrastructure belonging to those incumbent operators in order to offer various services to end users, in competition with the incumbent operators. The different telecommunications services that can be provided to end users through the local loop include high bit-rate data transmission services for fixed internet access and for multimedia applications based on digital subscriber line (DSL) technology.

7        Local loop unbundling was organised at EU level by, inter alia, Regulation (EC) No 2887/2000 of the European Parliament and of the Council of 18 December 2000 on unbundled access to the local loop (OJ 2000 L 336, p. 4), and Directive 2002/21/EC of the European Parliament and of the Council of 7 March 2002 on a common regulatory framework for electronic communications networks and services (OJ 2002 L 108, p. 33). Regulation No 2887/2000 required operators holding ‘significant market power’ to give access to unbundled local loops (ULLs) and to publish a reference unbundling offer. Those provisions were implemented in Slovakia by the Zákon z 3. decembra 2003 č. 610/2003 Z.z. o elektronických komunikáciách, v znení neskorších predpisov (Law No 610/2003 of 3 December 2003 on electronic communications), as amended, which entered into force, with certain exceptions, on 1 January 2004.

8        In essence, that regulatory framework required the operator identified by the national regulatory authority as the operator with significant market power, which is generally the incumbent operator, to grant alternative operators unbundled access to its local loop and to related services under transparent, fair and non-discriminatory conditions, and to maintain an updated reference offer for such unbundled access. The national regulatory authority was required to ensure that charging for unbundled access to the local loop, set on the basis of cost-orientation, fostered fair and sustainable competition. To that end, the national regulatory authority was entitled inter alia to require changes to be made to the reference offer.

9        Following a market analysis, on 8 March 2005 the Slovakian national regulatory authority for telecommunications (‘TUSR’) adopted a first-instance decision — Decision No 205/14/2005 — designating the applicant as an operator with significant power on the wholesale market for unbundled access to the local loop within the meaning of Regulation No 2887/2000. Consequently, TUSR imposed a number of obligations on the applicant, including requiring it to submit a reference offer within 60 days. That decision, which the applicant challenged, was confirmed by the Chairman of TUSR on 14 June 2005. Pursuant to that confirmatory decision, the applicant was required to grant all reasonable and justified requests for unbundling of its local loop in order to enable alternative operators to use that loop with a view, on that basis, to offer their own services on the ‘retail mass market’ for broadband services at a fixed location in Slovakia. The decision of 14 June 2005 also ordered the applicant to publish all intended changes to the reference unbundling offer at least 45 days in advance and to submit them to TUSR.

10      The applicant published its reference unbundling offer on 12 August 2005 (‘the reference offer’). That offer, which was amended on nine occasions between that date and the end of 2010, sets out the contractual and technical conditions for access to the applicant’s local loop. On the wholesale market, the applicant offers access to unbundled local loops in or next to a main distribution frame on which the alternative operator seeking access has rolled out its own backbone network.

11      According to the contested decision, the applicant’s local loop network, which could be used to supply broadband services after the lines concerned have been unbundled from that operator, covered 75.7% of all Slovakian households between 2005 and 2010. That coverage extended to all local loops in the applicant’s metallic access network that could be used to transmit a broadband signal. However, during that same period, only very few of the applicant’s local loops were unbundled, as from 18 December 2009, and used only by a single alternative operator to provide retail broadband services to undertakings.

B.      Procedure before the Commission

12      The Commission opened an investigation on its own initiative, inter alia, the conditions for unbundled access to the applicant’s local loop. Following requests for information sent to alternative operators on 13 June 2008 and an unannounced inspection at the applicant’s premises which took place on 13 and 15 January 2009, the Commission decided, on 8 April 2009, to open a procedure against that operator, within the meaning of Article 2 of Commission Regulation (EC) No 773/2004 of 7 April 2004 relating to the conduct of proceedings by the Commission pursuant to Articles [101] and [102 TFEU] (OJ 2004 L 123, p. 18).

13      Further steps were taken in the investigation consisting of additional requests for information sent to alternative operators and TUSR, as well as an announced inspection at the applicant’s premises on 13 and 14 July 2009.

14      In several discussion documents sent to the Commission between 11 August 2009 and 31 August 2010, the applicant argued that there were no grounds for finding that it had infringed Article 102 TFEU in the present case.

15      In the course of the investigation, the applicant objected to the provision of information dating from the period prior to 1 May 2004, the date of accession of the Slovak Republic to the European Union. It brought an action for annulment, first, of Commission Decision C(2009) 6840 of 3 September 2009 relating to a proceeding pursuant to Articles 18(3) and 24(1) of Council Regulation (EC) No 1/2003 of 16 December 2002 on the implementation of the rules on competition laid down in Articles [101 and 102 TFEU] (OJ 2003 L 1, p. 1) and, second, of Commission Decision C(2010) 902 of 8 February 2010 relating to a proceeding pursuant to Articles 18(3) and 24(1) of Regulation No 1/2003. By judgment of 22 March 2012, Slovak Telekom v Commission (T‑458/09 and T‑171/10, EU:T:2012:145), the Court dismissed the actions brought against those decisions.

16      Following requests for information sent to Deutsche Telekom, the Commission decided on 13 December 2010 to open a procedure against that company pursuant to Article 2 of Regulation No 773/2004.

17      On 7 May 2012, the Commission sent a statement of objections to the applicant. That statement of objections was sent to Deutsche Telekom the day after. In that statement of objections the Commission concluded, on a preliminary basis, that the applicant might have infringed Article 102 TFEU on account of a practice resulting in the margin squeeze as regards unbundled access to local loops in its network as well as national and regional wholesale broadband access to its competitors, and may have refused alternative operators access to some wholesale products. It also set out the preliminary view that Deutsche Telekom might be liable for the infringement in its capacity as parent company of the applicant during the infringement period.

18      After accessing the investigation file, the applicant and Deutsche Telekom each replied to the statement of objections on 5 September 2012. A hearing was held on 6 and 7 November 2012.

19      On 21 June 2013, the applicant sent the Commission a description of possible commitments intended to address its objections from the standpoint of competition law and asked the Commission to adopt a commitments decision within the meaning of Article 9 of Regulation No 1/2003 instead of a prohibition decision. The Commission nonetheless considered those commitments to be insufficient and therefore decided to continue the procedure.

20      On 6 December 2013 and 10 January 2014 respectively, the Commission sent the applicant and Deutsche Telekom a letter of facts intended to afford them the opportunity to comment on the additional evidence collected after the statement of objections had been issued. The Commission stated that that evidence, to which the applicant and Deutsche Telekom were given access, could be used in a possible final decision.

21      The applicant and Deutsche Telekom replied to the letter of facts on 21 February and 6 March 2014 respectively.

22      At meetings held with the applicant on 16 September 2014 and with Deutsche Telekom on 29 September 2014, the Commission provided information on the decision it planned to adopt under Article 7 of Regulation No 1/2003.

C.      Contested decision

23      In the contested decision, the Commission finds that the undertaking comprising the applicant and Deutsche Telekom committed a single and continuous infringement of Article 102 TFEU and Article 54 of the EEA Agreement concerning broadband services in Slovakia between 12 August 2005 and 31 December 2010 (‘the period under consideration’).

1.      Definition of the relevant markets and dominant position of the applicant on those markets

24      In the contested decision the Commission identifies two relevant product markets, namely:

–        the retail mass market for broadband services at a fixed location;

–        the wholesale market for access to unbundled local loops.

25      According to the contested decision, the relevant geographical market is the entire territory of the Republic of Slovakia.

26      The Commission states that, during the period under consideration, the applicant held a monopoly position on the wholesale market for unbundled access to local loops and there were no direct constraints in the form of actual or potential competition or countervailing buying power limiting its market power. The applicant therefore held a dominant position on that market during the period under consideration. The Commission also finds that the applicant held a dominant position during that period on the retail mass market for broadband services at a fixed location.

2.      The applicant’s conduct

(a)    Refusal to provide unbundled access to the applicant’s local loops

27      In the first part of its analysis entitled ‘Refusal to supply’, the Commission observes that, although several alternative operators had expressed great interest in being granted access to the applicant’s local loops in order to compete with it on the retail market for broadband services, that operator set unfair terms and conditions in its reference offer rendering such access unacceptable. The applicant thereby delayed, complicated or prevented entry on the retail broadband market.

28      In that regard, the Commission states that, first, unbundled access to the local loop by an alternative operator is based on the premiss that that operator must first obtain sufficient and adequate information concerning the incumbent operator’s network. That information must enable the alternative operator concerned to assess its business opportunities and to prepare appropriate business plans for its future retail services based on unbundled access to the local loop. In the present case, the reference offer did not satisfy that information requirement with respect to alternative operators.

29      Accordingly, despite the requirements laid down in the relevant regulatory framework (see paragraphs 7 and 8 above), the reference offer does not provide any basic information regarding the locations of physical access sites and the availability of local loops in specific parts of the network. Alternative operators had access to such information only upon request, in exchange for payment of a fee, within five days of the entry into force of a confidentiality agreement with the applicant and solely after the provision of a bank guarantee. The Commission considers, in essence, that those requirements unreasonably delayed and complicated disclosure of the relevant information to alternative operators and thus discouraged those operators from accessing the applicant’s local loops.

30      Even in the case of access upon request, the Commission finds that the information provided by the applicant was insufficient. In particular, the applicant did not provide any information on the availability of its local loops, even though such information was crucial to enable alternative operators to prepare their business models in time and to identify the business potential of unbundling. The Commission takes the view that the applicant should have disclosed not only the list of main distribution frames and similar facilities, but also a description of their geographical coverage; information on the ranges of telephone numbers served by those exchanges; information on the actual use of cables (in %) for DSL technologies; information on the ratio of pulse code modulation (PCM) equipment deployment regarding the cables connected to the different main distribution frames; the names or functions of the distribution frames and information on how they are used in the applicant’s technical and methodological regulations; and the maximum lengths of homogeneous local loops. The applicant was moreover well aware of the problems faced by alternative operators as a result of those terms of access to information and the information’s limited scope. The Commission also points out that, although the applicant did not publish a template for the unbundling requests to be submitted by alternative operators until May 2009, its reference unbundling offer made provision at the very outset for the imposition of financial penalties if a request for access were deemed incomplete.

31      Secondly, according to the contested decision, the applicant unjustifiably reduced the scope of its obligation relating to unbundled access to its local loops.

32      Thus, in the first place, the applicant improperly excluded from that obligation ‘passive’ lines, namely lines which existed physically but were not in use. By doing so, the applicant reserved for itself a significant number of potential customers who were not yet purchasing its broadband services but to whom its network was available, even though the market was growing and the relevant regulatory framework did not restrict the unbundling obligation to active lines only. The restriction applied by the applicant was not, in the Commission’s view, justified by any objective technical reasons.

33      In the second place, the applicant unjustifiably excluded from its unbundling obligation the services which it classed as ‘conflicting services’, namely services that it was likely to offer and which may have been in conflict with access to the local loop by an alternative operator. In addition to the fact that the actual concept of conflicting services is vague, the list of such services — drawn up unilaterally by the applicant — is open and, in consequence, creates uncertainty for alternative operators. That limitation deprived alternative operators of a large number of potential customers, customers which were reserved for the applicant and therefore withdrawn from the retail market.

34      In the third place, the Commission classifies as unjustified the rule imposed by the applicant in the reference offer, whereby only 25% of local loops contained in a multi-pair cable could be used for the provision of broadband services, in order to avoid cross-talk and interferences. That rule is not justified because it is of a general and abstract nature and does thus not take account of the characteristics of the cables and the specific combination of transmission techniques. The Commission points out, in that regard, that the practice followed in other Member States demonstrates that there are alternatives to such upstream abstract limitations on access, for instance the principle of 100% cable fill-in together with the a posteriori resolution of any specific problems stemming from spectrum interferences. Finally, the applicant applied to itself a maximum fill-in rule of 63%, which is less strict than the rule it applied to alternative operators.

35      Finally, thirdly, the applicant established a number of unfair terms and conditions in the reference offer concerning unbundled access to its local loops.

36      In that regard, in the first place, according to the contested decision, the applicant included unfair terms and conditions in the reference offer relating to collocation, defined in that offer as ‘the provision of the physical space and the technical equipment necessary for the appropriate placement of the telecommunication equipment of the Authorised Provider with the purpose of provision of services to the end users of the Authorised Provider via access to the local loop’. The barrier thus erected for alternative operators was the result of, in particular, the following factors: (i) the conditions required a preliminary inquiry into the possibilities of collocation which was not objectively necessary; (ii) alternative operators were only able to challenge the determination of the form of collocation decided by the applicant by paying an additional fee; (iii) the consequence of the expiry of the reservation period after delivery to the alternative operator of the notice regarding the outcome of the preliminary or detailed inquiry, without any collocation agreement being concluded, was that the preliminary or detailed inquiry had to be repeated in full; (iv) the applicant was not bound by any deadlines in the event of additional detailed inquiries triggered by negotiations and was entitled to withdraw — without stating reasons and without any legal consequences — a proposed collocation agreement during the term for acceptance of the proposal by the alternative operators within the established deadlines; (v) the applicant was not bound by any precise time limit for implementing collocation; (vi) the applicant unilaterally imposed unfair and non-transparent fees for collocation.

37      In the second place, the Commission finds that, under the reference offer, alternative operators were required to submit forecasts of the requests for qualification of the local loop 12 months in advance for each collocation space, on a month-by-month basis, before being able to submit a request for qualification for access to the relevant local loop. The Commission considers that such a requirement obliges alternative operators to submit forecasts at a time when they are not in a position to estimate their needs in terms of unbundled access. It also criticises the fact that failure to comply with the forecasting terms triggered the payment of penalties and complains about the mandatory nature of the forecasting obligation and the lack of any deadline for the applicant to respond to a request for qualification in the event that such a request did not comply with the forecasted volume.

38      In the third place, the Commission considers that the mandatory qualification procedure, which was designed to enable alternative operators to determine whether a specific local loop was suitable for xDSL technology or any other broadband technology they might intend to use before placing a firm unbundling order, was such that those operators were deterred from requesting unbundled access to the applicant’s local loops. Thus, while conceding that it is necessary to verify the suitability of local loops for unbundling or the basic preconditions for unbundling a specific line, the Commission states that the splitting of that qualification process from the very request for access to the local loop unnecessarily delayed unbundling and generated additional costs for alternative operators. Furthermore, a number of aspects examined in the context of the qualification process are superfluous. The Commission considers to be unjustified the validity period limited to 10 days applying to the positive qualification of a local loop, after which a request for access could no longer be made.

39      In the fourth place, according to the contested decision, the reference offer included disadvantageous terms as regards repairs, service and maintenance, due to (i) the lack of an appropriate definition of ‘planned works’ and ‘unplanned works’; (ii) the unclear distinction between ‘unplanned works’ and straightforward ‘defaults’, liable to give rise to unjustified conduct on the part of the applicant; (iii) the very short deadlines for informing alternative operators of such works and for transmitting that information to their customers; and, finally, (iv) the shifting of responsibility to the alternative operator for service interruptions caused by repairs where that operator has been deemed to be uncooperative.

40      In the fifth place, the Commission regards as unfair several terms and conditions applying to the bank guarantee that must be provided by all alternative operators wishing to conclude a collocation agreement with the applicant and ultimately secure access to its local loops. Therefore, first of all, the applicant enjoys an overly wide discretion in deciding whether to accept or refuse a bank guarantee and is not subject to any deadline in that regard. Next, the amount of the guarantee, set at EUR 66 387.84, is disproportionate in the light of the risks and costs borne by the applicant. That is all the more so since the reference offer allowed the applicant to multiply that amount by up to 12 where it called on the guarantee. Furthermore, the applicant was able to call on the bank guarantee to cover not only the failure to pay for actual services it provided, but also to cover any claims for damages that it could submit. Moreover, the applicant was entitled to trigger the bank guarantee without having to show that it had first asked the debtor to pay and without the debtor having the option of raising a counterclaim. Lastly, the Commission notes that alternative operators do not benefit from any similar security even though they may incur losses as a result of the applicant’s conduct in respect of unbundled access to local loops.

41      The Commission concludes that those aspects of the applicant’s conduct, taken together, amounted to a refusal by that operator to provide unbundled access to its local loops.

(b)    Margin squeeze of alternative operators in the provision of unbundled access to the applicant’s local loops

42      In the second part of its analysis of the applicant’s conduct, the Commission makes a finding of margin squeeze as a result of the behaviour of that operator in connection with unbundled access to its local loops, which constitutes an independent form of abuse of a dominant position. Accordingly, the spread between the prices charged by the applicant for the grant of such access to alternative operators and the prices charged to its own customers was either negative or insufficient for an operator as efficient as the applicant to cover the specific costs which it had to incur to supply its own products or service on the downstream market, namely the retail market.

43      Where the service portfolio under consideration includes only broadband products, the Commission notes that an equally efficient competitor would have been able, by means of unbundled access to the applicant’s local loops, to replicate the entirety of the retail DSL offering of the applicant as it evolved over time. The ‘period-by-period’ margin analysis (namely the calculation of the available margins for each year of the period between 2005 and 2010) demonstrates that a competitor as efficient as the applicant faced negative margins and would not therefore have been able to replicate profitably the retail broadband portfolio offered by the applicant.

44      Where the portfolio examined includes voice telephony services in addition to broadband services by means of full access to the local loop, the Commission also concludes that a competitor as efficient as the applicant would not have been able, due to the prices charged by the applicant on the upstream market for unbundled access, to operate profitably on the relevant retail market during the period between 2005 and 2010. An equally efficient competitor would not therefore have been able to replicate profitably, over that same period, the applicant’s portfolio. The addition to that portfolio of multi-play services, available as from 2007, would not alter that finding.

45      Since neither the applicant nor Deutsche Telekom put forward during the administrative procedure any objective justification for their exclusionary conduct, the Commission concludes that the applicant’s conduct during the period under consideration constitutes an abusive margin squeeze.

3.      Analysis of the anticompetitive effects of the applicant’s conduct

46      The Commission considers that those two types of conduct on the part of the applicant, namely the refusal to provide unbundled access to the local loop and the margin squeeze of the alternative operators were likely to prevent alternative operators from relying on unbundled access in order to enter the Slovakian retail mass market for broadband services at a fixed location. According to the contested decision, its conduct made competition less effective on that market because there was no genuine profitable alternative for competing operators to wholesale access to xDSL broadband based on the unbundling of local loops. The impact of the applicant’s conduct on competition was all the more significant because the retail market for broadband services showed strong potential for growth during the period under consideration.

47      The Commission also states, in essence, that according to the ‘investment ladder’ concept, that barrier to access to the unbundling of the local loop deprived alternative operators of a source of income which would have allowed them to make further investments in the network, particularly by developing their own access network to connect their customers directly.

48      The Commission concludes that the anticompetitive conduct of the applicant on the mass market for broadband services at a fixed location in Slovakia was likely to have negative effects on competition and, in the light of its geographical reach across the entire territory of the Slovak Republic, was able to affect trade between Member States.

4.      Addressees of the contested decision and fines

49      According to the contested decision, not only was Deutsche Telekom in a position to exercise decisive influence over the applicant’s commercial policy during the entire period under consideration, but it actually exercised such influence. Since the applicant and Deutsche Telekom form part of the same undertaking, both were held liable for the single and continuous infringement of Article 102 TFEU forming the subject matter of the contested decision.

50      As regards the penalty for that infringement, the Commission states that it set the amount of the fines by reference to the principles laid down in its Guidelines on the method of setting fines imposed pursuant to Article 23(2)(a) of Regulation No 1/2003 (OJ 2006 C 210, p. 2) (‘the 2006 Guidelines’).

51      First of all, the Commission calculates the basic amount of the fine by retaining 10% of the applicant’s turnover on the market for unbundled access to the local loop and for fixed retail broadband in the last full financial year of its participation in the infringement, in the case at hand 2010, and by multiplying the resulting figure by 5.33 to take account of the duration of the infringement (5 years and 4 months). The basic amount of the fine is thus EUR 38 838 000. Under the first paragraph of Article 2(a) of the contested decision, this is the first fine imposed for the infringement in question and for which the applicant and Deutsche Telekom are held jointly and severally liable.

52      Next, the Commission applies a twofold adjustment to the basic amount. In the first place, it finds that when the infringement in question occurred, Deutsche Telekom had already been held liable for an infringement of Article 102 TFEU, on account of a margin squeeze in the telecommunications sector, in Decision 2003/707/EC of 21 May 2003 relating to a proceeding under Article 82 [EC] (Cases COMP/37.451, 37.578, 37.579 — Deutsche Telekom AG) (OJ 2003 L 263, p. 9), and that, when the decision was adopted, Deutsche Telekom held 51% of the applicant’s shares and was in a position to exercise decisive influence over it. Consequently, the Commission finds that, for Deutsche Telekom, the basic amount of the fine should be increased by 50% on account of repeated infringement. In the second place, the Commission states that the worldwide turnover of Deutsche Telekom for 2013 was EUR 60 123 million and that, in order to give the fine sufficient deterrent effect, a coefficient multiplier of 1.2 should be applied to the basic amount. The product of that twofold adjustment, namely EUR 31 070 000, gives rise, under the first paragraph of Article 2(b) of the contested decision, to a separate fine imposed on Deutsche Telekom alone.

5.      Operative part of the contested decision

53      Articles 1 and 2 of the contested decision read as follows:

Article 1

(1)      The undertaking consisting of Deutsche Telekom AG and Slovak Telekom a.s. has committed a single and continuous infringement of Article 102 of the Treaty and Article 54 of the EEA Agreement.

(2)      The infringement lasted from 12 August 2005 until 31 December 2010 and consisted of the following practices:

(a)      withholding from alternative operators network information necessary for the unbundling of local loops;

(b)      reducing the scope of its obligations regarding unbundled local loops;

(c)      setting unfair terms and conditions in its Reference Unbundling Offer regarding collocation, qualification, forecasting, repairs and bank guarantees;

(d)      applying unfair tariffs which do not allow an equally efficient competitor relying on wholesale access to the unbundled local loops of Slovak Telekom a.s. to replicate the retail broadband services offered by Slovak Telekom a.s. without incurring a loss.

Article 2

For the infringement referred to in Article 1, the following fines are imposed:

(a)      a fine of EUR 38 838 000 on Deutsche Telekom AG and Slovak Telekom a.s., jointly and severally;

(b)      a fine of EUR 31 070 000 on Deutsche Telekom AG. 

…’

II.    Procedure and forms of order sought

54      By application lodged at the Court Registry on 26 December 2014, the applicant brought the present action.

55      By documents lodged at the Court Registry on 29 May and 1 June 2015 respectively, Slovanet, a.s. and Orange Slovensko, a.s. applied for leave to intervene in the present proceedings in support of the form of order sought by the Commission.

56      At the request of the Commission, the time limit for lodging an application for confidential treatment was extended and set at 30 October 2015.

57      By letter of 30 October 2015, the applicant applied for certain information contained in the application and the reply, as well as in some of the annexes thereto, to be treated as confidential with regard to Slovanet and Orange Slovensko. By letter of the same date, the Commission applied for certain information contained in the application and the defence, as well as in some of the annexes thereto, to be treated as confidential.

58      By letter of 10 December 2015, the Commission applied for certain information contained in the reply to be treated as confidential with regard to Slovanet and Orange Slovensko. Moreover, by letter of 28 January 2016, it applied for certain information contained in the rejoinder and in a document contained in an annex thereto to be treated as confidential with regard to those companies.

59      By order of the President of the Second Chamber of the General Court of 24 June 2016, Slovanet and Orange Slovensko were granted leave to intervene in support of the form of order sought by the Commission. The decision on the merits of the applications for confidential treatment was reserved.

60      Joint non-confidential versions of the various procedural documents, prepared by the main parties, were communicated to Orange Slovensko and Slovanet. At the request of the latter, the time limit for challenging the applications for confidential treatment was extended and set at 8 August 2016.

61      By letters of 5 August 2016, Orange Slovensko and Slovanet challenged the confidentiality of various redacted passages in the non-confidential versions of the procedural documents. In a joint letter of the same date, Orange Slovensko and Slovanet explained that their challenges were identical in scope, except the objections to confidential treatment of information relating to each of them specifically.

62      After those challenges were lodged, the time limit previously set for lodging statements in intervention was interrupted.

63      By decision of the President of the General Court of 7 October 2016, a new Judge-Rapporteur was designated and the case was reassigned to the Ninth Chamber.

64      By order of 29 March 2017, the President of the Ninth Chamber of the General Court granted in part the applicant’s and the Commission’s applications for confidential treatment.

65      After communication to Orange Slovensko and Slovanet of new joint non-confidential versions of the various procedural documents, prepared by the main parties pursuant to that order, Slovanet lodged an additional statement in intervention on 15 June 2017. In the meantime, by letter sent to the Court Registry on 8 June 2017, Orange Slovensko requested leave to withdraw its intervention.

66      By order of 20 July 2017, the President of the Ninth Chamber of the General Court granted that request and, in the absence of observations from the main parties in that respect, ordered the main parties and Orange Slovensko to bear their own costs in relation to the application to intervene.

67      On a proposal from the Ninth Chamber, the Court decided, pursuant to Article 28 of its Rules of Procedure, to assign the case to a Chamber sitting in extended composition.

68      Acting on a proposal from the Judge-Rapporteur, the Court (Ninth Chamber, Extended Composition) decided to open the oral part of the procedure and, by way of measures of organisation of procedure provided for under Article 89 of the Rules of Procedure, requested the parties to answer certain questions at the hearing.

69      The parties presented oral argument and answered written and oral questions put by the Court at the hearing on 26 April 2018.

70      At the hearing, the Commission was requested to produce, within two weeks, the full version of the document of which an extract is included in Annex B.4 of the defence. On 2 May 2018, the Commission produced the non-confidential version of that procedural document and stated that it did not request confidential treatment of it. By document lodged at the Court Registry on 14 May 2018, the applicant requested that that document be treated as confidential vis-à-vis the intervener, Slovanet. By letter of 28 May 2018, the intervener raised objections to that request for confidential treatment. By order of 4 July 2018, the Vice-President of the General Court, acting President of the Ninth Chamber, extended composition, rejected that request.

71      The applicant claims that the Court should:

–        annul Articles 1 and 2 of the contested decision in so far as that decision affects it;

–        in the alternative, reduce the fine imposed on it under Article 2 of the contested decision;

–        order the Commission to pay the costs;

–        if the Court dismisses the action as inadmissible or unfounded, order each party to bear its own costs.

72      The Commission and the intervener contend that the Court should:

–        dismiss the action in its entirety, and

–        order the applicant to pay the costs.

III. Law

A.      Admissibility

1.      The preliminary observations formulated in the introductory part of the application and relating to the effects of the practices at issue

73      The applicant criticises, in the introductory part of the application and during the hearing, the use, by the Commission, of two economic theories on which the approach adopted by that institution in the contested decision is based, namely the ‘ladder of investment’ theory and the ‘foreclosure’ theory.

74      In that regard, it should be noted that, under the first paragraph of Article 21 of the Statute of the Court of Justice of the European Union, which applies to proceedings before the General Court by virtue of the first paragraph of Article 53 of that statute and of Article 44(1)(c) of the Rules of Procedure of the General Court of 2 May 1991, applicable at the time the action was brought, all applications are required to state the subject matter of the proceedings and a summary of the pleas in law on which the application is based and that it is necessary, for an action to be admissible, that the essential matters of fact and law on which it is based be indicated, at least in summary form, coherently and intelligibly in the application itself.

75      That information given must be sufficiently clear and precise to enable the defendant to prepare its defence and the Court to decide the case. The same is true of all claims, which must be accompanied by pleas and arguments enabling both the defendant and the Court to assess their validity (judgment of 7 July 1994, Dunlop Slazenger v Commission, T‑43/92, EU:T:1994:79, paragraph 183).

76      It is apparent from the Court’s case-law that the ‘summary of the pleas in law’ which must be stated in any application, as provided for by the articles cited in paragraph 74 above, means that the application must specify the nature of the grounds on which it is based (see judgment of 11 September 2014, MasterCard and Others v Commission, C‑382/12 P, EU:C:2014:2201, paragraph 39 and the case-law cited).

77      It must be noted that the applicant merely criticises the application of the theories referred to in paragraph 73 above, without indicating the elements of fact and law making it possible to understand the extent to which the contested decision is incompatible with Article 102 TFEU.

78      Therefore, such a line of argument fails to satisfy the requirements referred to by Article 44(1)(c) of the Rules of Procedure of 2 May 1991 and by the first paragraph of Article 21 of the Statute of the Court of Justice of the European Union.

79      The preliminary observations formulated by the applicant must therefore be rejected as inadmissible.

2.      Admissibility of Annex A.9 to the application

80      The Commission submits that Annex A.9 to the application, consisting of legal advice on legal questions raised by the dispute, issued by a former member of the Court of Justice of the European Union, is inadmissible because it was used by the applicant to raise and develop points of EU law even though, according to the case-law, annexes have a purely evidential and instrumental function. In particular, the Commission objects to the applicant’s attempt to supplement the legal arguments set out in the application by reference to that annex.

81      The applicant contends that that annex is admissible because the Commission had sight of it during the administrative procedure and it complies with the requirements laid down in the case-law. Accordingly, the applicant submits that the application refers extensively to the paragraphs of that annex in order to support its claims. Furthermore, the EU Courts apply principles of unfettered evaluation of evidence that are unique to EU law, with the result that the Commission’s references to rules of evidence are misconceived.

82      In that regard, in so far as the Commission contends that Annex A.9 is inadmissible on the ground that annexes may not be used to argue or develop a question of EU law, it should be noted that, in a dispute between parties concerning the interpretation and application of a provision of EU law, the Court is required to apply to the facts put before it by the parties the relevant rules of law for the solution of the dispute. According to the principle iura novit curia, determining the meaning of the law does not fall within the scope of application of a principle which allows the parties a free hand to determine the scope of the case (see judgment of 5 October 2009, Commission v Roodhuijzen, T‑58/08 P, EU:T:2009:385, paragraph 36 and the case-law cited). However, that principle cannot mean that annexes to the application relating to the interpretation of EU law are inadmissible.

83      Moreover, in so far as the Commission contests the admissibility of that annex, on the ground that a legal opinion annexed to an application is admissible only to support and supplement the essential elements which must be included in the application, it should be noted that, as was pointed out in paragraph 74 above, under the first paragraph of Article 21 of the Statute of the Court of Justice of the European Union, which applies to proceedings before the General Court by virtue of the first paragraph of Article 53 of that statute and of Article 44(1)(c) of the Rules of Procedure of the General Court of 2 May 1991, applicable at the time the action was brought, all applications are required to state the subject matter of the proceedings and a summary of the pleas in law on which the application is based and that it is necessary, for an action to be admissible, that the essential matters of fact and law on which it is based be indicated, at least in summary form, coherently and intelligibly in the application itself.

84      It is apparent from the Court’s case-law that the ‘summary of the pleas in law’ which must be stated in any application, as provided for by the articles cited in paragraph 83 above, means that the application must specify the nature of the grounds on which it is based (see judgment of 11 September 2014, MasterCard and Others v Commission, C‑382/12 P, EU:C:2014:2201, paragraph 39 and the case-law cited).

85      Whilst the body of the application may certainly be supported and supplemented on specific points by references to extracts from documents annexed thereto, a general reference to other documents, even those annexed to the application, cannot make up for the absence of the essential arguments in law which, in accordance with the abovementioned provisions, must appear in the application (judgment of 11 September 2014, MasterCard and Others v Commission, C‑382/12 P, EU:C:2014:2201, paragraph 40).

86      Furthermore, it is not for the Court to seek and identify in the annexes the pleas on which it may consider the action to be based, since the annexes have a purely evidential and instrumental function (see judgment of 17 September 2007, Microsoft v Commission, T‑201/04, EU:T:2007:289, paragraph 94 and the case-law cited).

87      Consequently, in the present case, the Court may take Annex A.9 into consideration only in so far as it supports or supplements pleas or arguments expressly set out by the applicants in the body of the application and in so far as it is possible for the Court to determine precisely what are the matters contained in that annex that support or supplement those pleas or arguments.

88      In that regard, it should be noted that, in paragraph 41 of the application, the applicant incorporates the passage which it considered to be the most relevant in order to support its arguments contesting the application of the judgment of 26 November 1998, Bronner (C‑7/97, EU:C:1998:569). Therefore, it is not necessary for the Court to seek or identify in that annex the arguments in support of the first plea in law. Consequently, that passage of Annex A.9 is admissible.

89      As regards paragraph 48 of the application, since the applicant cites a paragraph of Annex A.9 in full, it is not necessary for the Court to seek or identify in that annex the arguments in support of the first plea in law. Consequently, that paragraph of Annex A.9 is admissible.

90      Concerning paragraph 66 of the application, since the applicant cites a paragraph of Annex A.9 in full, it is also not necessary for the Court to seek or identify in that annex the arguments in support of the first plea in law. That paragraph of Annex A.9 is therefore admissible. The other paragraphs of Annex A.9 must, by contrast, be declared inadmissible.

B.      Substance

91      The applicant puts forward five pleas in law in support of both its principal claims seeking annulment of the contested decision and its alternative claims seeking a reduction of the fine imposed on it, alleging (i) manifest errors of law and assessment in the application of Article 102 TFEU as regards the applicant’s abusive conduct; (ii) infringement of the applicant’s rights of defence as regards the practice resulting in the margin squeeze; (iii) errors in the finding of that practice; (iv) error committed by the Commission in finding that the applicant and Deutsche Telekom were part of a single undertaking and were both liable for the infringement in question; and (v) errors in determining the amount of the fine.

1.      First plea in law: manifest errors of law and assessment in the application of Article 102 TFEU as regards the applicant’s abusive conduct

92      In support of its first plea, the applicant essentially objects to the legal test applied by the Commission in the contested decision in order to find that its practice constituted abuse of a dominant position within the meaning of Article 102 TFEU.

93      The first plea in law is essentially made up of five complaints, alleging (i) that the Commission failed to apply the condition relating to the indispensable nature of access to the applicant’s copper DSL network to be able to operate on the retail market for broadband services in Slovakia, within the meaning of the judgment of 26 November 1998, Bronner (C‑7/97, EU:C:1998:569); (ii) misapplication of the judgment of 9 September 2009, Clearstream v Commission (T‑30l/04, EU:T:2009:317); (iii) that the contested decision is inconsistent in terms of competition policy in so far as it concerns proof of the outright refusal of access and the refusal of access; (iv) errors of fact and of law as well as a defective statement of reasons in the justification for derogating from the conditions established in the judgment of 26 November 1998, Bronner (C‑7/97, EU:C:1998:569); and (v) failure to demonstrate that access to the applicant’s local loop is indispensable to competitors located on the downstream market.

94      The Commission and the intervener contest those complaints and contend that the present plea in law should be rejected.

(a)    The first and fifth complaints

95      In the context of its first and fifth complaints, the applicant claims that the Commission, in essence, classified a range of its conduct during the period under consideration, referred to by the seventh part of the contested decision (recitals 355 to 821), as a ‘refusal to supply’ access to its local loop without having verified the indispensability of such access, for the purposes of paragraph 41 of the judgment of 26 November 1998, Bronner (C‑7/97, EU:C:1998:569).

96      By its first complaint, the applicant calls in question the Commission’s findings in recitals 361 to 371 of the contested decision, according to which the circumstances of the present case are different from those in the judgment of 26 November 1998, Bronner (C‑7/97, EU:C:1998:569). The applicant asserts that it is apparent from that judgment that a refusal to supply infringes Article 102 TFEU in particular where that refusal concerns a product the supply of which is indispensable for carrying on the relevant business (the ‘indispensability condition’). In this case, the Commission wrongly failed to examine whether access to the applicant’s network was indispensable to be able to operate on the retail market for broadband services in Slovakia. Accordingly, the applicant disputes the Commission’s finding that the judgment of 17 February 2011, TeliaSonera Sverige (C‑52/09, EU:C:2011:83), is authority for the proposition that, in the case of a constructive refusal of access, the Commission is not required to demonstrate that the conditions of the judgment of 26 November 1998, Bronner (C‑7/97, EU:C:1998:569), particularly the indispensability condition, apply (recital 359 et seq. of the contested decision).

97      It follows from paragraphs 55 to 58 of the judgment of 17 February 2011, TeliaSonera Sverige (C‑52/09, EU:C:2011:83), read together, that the practice resulting in the margin squeeze constitutes a standalone abuse under Article 102 TFEU which does not require prior proof of an obligation to deal meeting the conditions of the judgment of 26 November 1998, Bronner (C‑7/97, EU:C:1998:569). Since the Commission found that paragraph 55 of the judgment of 17 February 2011, TeliaSonera Sverige (C‑52/09, EU:C:2011:83), covers not only the practice resulting in the margin squeeze but also a constructive refusal of access, as in this case, it was wrong to seek to expand significantly the narrow reasoning of that judgment.

98      In particular, according to the applicant, although it is apparent from the judgment of 17 February 2011, TeliaSonera Sverige (C‑52/09, EU:C:2011:83), that the indispensability condition is not a requirement for all ‘terms of trade’ abuses under Article 102 TFEU, this does not, however, mean that the condition does not apply in the case of a refusal of access. Nowhere in the judgment of 17 February 2011, TeliaSonera Sverige (C‑52/09, EU:C:2011:83), or in any other judgment, did the Court state that the indispensability condition established in the judgment of 26 November 1998, Bronner (C‑7/97, EU:C:1998:569), is limited to cases of outright refusal of access. On the contrary, that approach would undermine the effectiveness of Article 102 TFEU. Even if the judgment of 26 November 1998, Bronner (C‑7/97, EU:C:1998:569), involves an outright refusal to supply, the Court established in that judgment the general principles of a duty to assist competitors.

99      As regards the judgments cited by the Commission in the defence, the applicant considers that those judgments constitute a new approach compared to the contested decision. In any event, firstly, the judgment of 26 November 1998, Bronner (C‑7/97, EU:C:1998:569), assimilated the judgment of 6 March 1974, Istituto Chemioterapico Italiano and Commercial Solvents v Commission (6/73 and 7/73, EU:C:1974:18), which is authority for the proposition that indispensability is a legal prerequisite. Therefore, those two judgments are compatible.

100    Secondly, the case-law cited by the Commission, namely the judgments of 14 February 1978, United Brands and United Brands Continentaal v Commission (27/76, EU:C:1978:22), and of 16 September 2008, Sot. Lélos kai Sia and Others (C‑468/06 to C‑478/06, EU:C:2008:504), does not apply to the present case, since, first of all, the complaints raised in the context of those cases did not concern a refusal to deal but rather the fact that such a refusal was used as a way to bring about a different restriction of competition. Next, those cases did not involve the sale of an input to competitors on a downstream market, but the supply of finished goods for distribution or resale. Finally, in those cases, the dominant undertaking had decided to terminate the supply of goods that it previously supplied to the customers in question, while in this case — as in the case giving rise to the judgment of 26 November 1998, Bronner (C‑7/97, EU:C:1998:569), — the access seekers had never previously been supplied by the dominant undertaking.

101    Thirdly, the applicant considers, as regards the case-law cited by the Commission relating to the refusal to license intellectual property rights, namely the judgments of 5 October 1988, Volvo (238/87, EU:C:1988:477, paragraph 8), of 6 April 1995, RTE and ITP v Commission (C‑241/91 P and C‑242/91 P, EU:C:1995:98, paragraph 50), and of 29 April 2004, IMS Health (C‑418/01, EU:C:2004:257, paragraph 35), that that case-law is compatible with the judgment of 26 November 1998, Bronner (C‑7/97, EU:C:1998:569), since that judgment refers to the judgment of 6 April 1995, RTE and ITP v Commission (C‑241/91 P and C‑242/91 P, EU:C:1995:98), which is itself cited in the later judgments. The fact that more stringent conditions, in particular that the input must be necessary to manufacture a ‘new product’, may be required in intellectual property cases does not mean that the Commission can do away with the conditions of the judgment of 26 November 1998, Bronner (C‑7/97, EU:C:1998:569), in cases which are not related to that field.

102    Fourthly, the applicant claims that, regarding the application of the judgment of 17 February 2011, TeliaSonera Sverige (C‑52/09, EU:C:2011:83), there is no reason to think that the Court wished to limit the conditions of the judgment of 26 November 1998, Bronner (C‑7/97, EU:C:1998:569), to the strict circumstances of that case. There is a difference between stating, as was done in the judgment of 17 February 2011, TeliaSonera Sverige (C‑52/09, EU:C:2011:83), that the conditions of the judgment of 26 November 1998, Bronner (C‑7/97, EU:C:1998:569), do not apply to all ‘terms of trade’ cases and stating, as the Commission does, that the conditions of the judgment of 26 November 1998, Bronner (C‑7/97, EU:C:1998:569), should not apply in any of those cases.

103    Fifthly, the decisions cited by the Commission do not support its proposition, since its analysis in Decision 2001/892/EC of 25 July 2001 relating to a proceeding under Article 82 [EC] (COMP/C‑1/36.915 — Deutsche Post AG — Interception of cross-border mail) (OJ 2001 L 331, p. 40) is based on the fact that Deutsche Post’s distribution network was indispensable to senders located in the United Kingdom. The Polaroid v SSI Europe case, cited as an example of an abusive constructive refusal of access, is not relevant to the case at hand.

104    By its fifth complaint, the applicant asserts that the contested decision does not demonstrate that access to its local loop is indispensable to downstream competitors. In that regard, it follows from the judgment of 29 April 2004, IMS Health (C‑418/01, EU:C:2004:257, paragraph 28), that it is not sufficient to demonstrate that alternative approaches are less advantageous for other operators, but it is necessary to demonstrate the indispensability of the network concerned within the meaning of the judgment of 26 November 1998, Bronner (C‑7/97, EU:C:1998:569). The obligation to grant access to a facility arises if the refusal to supply objectively has a sufficiently serious effect on competition.

105    Furthermore, no relevance is to be attached to the questions examined by the Commission in section 7.3 of the contested decision and, in particular, in recitals 382 and 384 thereof, concerning whether the applicant’s copper network was important and whether efficient wholesale access to xDSL based on the local loop was important for alternative operators in Slovakia. Accordingly, the Commission committed an error as regards the application of the criterion of indispensability. It is necessary for the Commission to consider whether access to the local loop is indispensable to enable the applicant’s competitors to compete on the downstream retail market so that, without such access, competition would be impossible or excessively difficult. Since the vast majority of broadband access is based on technologies other than the applicant’s copper network, such access is not indispensable in the sense of impossible or excessively difficult.

106    The Commission and the intervener dispute those arguments.

107    In that regard, according to established case-law, a dominant undertaking has a special responsibility not to allow its behaviour to impair genuine, undistorted competition on the internal market (see judgment of 6 September 2017, Intel v Commission, C‑413/14 P, EU:C:2017:632, paragraph 135 and the case-law cited), and the fact that such a position has its origins in a former legal monopoly must, in that regard, be taken into account (judgment of 27 March 2012, Post Danmark, C‑209/10, EU:C:2012:172, paragraph 23).

108    That is why Article 102 TFEU prohibits, in particular, a dominant undertaking from, among other things, adopting pricing practices that have an exclusionary effect on competitors considered to be as efficient as it is itself and strengthening its dominant position by using methods other than those that are part of competition on the merits. From that point of view, not all competition on price can be regarded as legitimate (see judgment of 6 September 2017, Intel v Commission, C‑413/14 P, EU:C:2017:632, paragraph 136 and the case-law cited).

109    It has been held, in that regard, that abuse of a dominant position prohibited by Article 102 TFEU is an objective concept relating to the conduct of a dominant undertaking which, on a market where the degree of competition is already weakened precisely because of the presence of the undertaking concerned, through recourse to methods different from those governing normal competition in products or services on the basis of the transactions of commercial operators, has the effect of hindering the maintenance of the degree of competition still existing on the market or the growth of that competition (see judgments of 19 April 2012, Tomra Systems and Others v Commission, C‑549/10 P, EU:C:2012:221, paragraph 17 and the case-law cited, and of 9 September 2009, Clearstream v Commission, T‑301/04, EU:T:2009:317, paragraph 140 and the case-law cited).

110    Article 102 TFEU covers not only those practices that directly cause harm to consumers but also practices that cause consumers harm by interfering with the free play of competition (see, to that effect, judgments of 27 March 2012, Post Danmark, C‑209/10, EU:C:2012:172, paragraph 20 and the case-law cited, and of 29 March 2012, Telefónica and Telefónica de España v Commission, T‑336/07, EU:T:2012:172, paragraph 171).

111    The effect on competition referred to in paragraph 109 above does not necessarily relate to the actual effect of the abusive conduct complained of. For the purposes of establishing an infringement of Article 102 TFEU, it is necessary to show that the abusive conduct of the undertaking in a dominant position tends to restrict competition or, in other words, that the conduct is capable of having that effect (judgment of 19 April 2012, Tomra Systems and Others v Commission, C‑549/10 P, EU:C:2012:221, paragraph 68; see, also, judgments of 9 September 2009, Clearstream v Commission, T‑301/04, EU:T:2009:317, paragraph 144 and the case-law cited, and of 29 March 2012, Telefónica and Telefónica de España v Commission, T‑336/07, EU:T:2012:172, paragraph 268 and the case-law cited).

112    Moreover, as regards the abusive nature of a practice resulting in a margin squeeze, it should be noted that the second paragraph of Article 102 TFEU expressly prohibits a dominant undertaking from directly or indirectly imposing unfair prices (judgments of 17 February 2011, TeliaSonera Sverige, C‑52/09, EU:C:2011:83, paragraph 25, and of 29 March 2012, Telefónica and Telefónica de España v Commission, T‑336/07, EU:T:2012:172, paragraph 173). Since the list of abusive practices contained in Article 102 TFEU is nevertheless not exhaustive, the list of abusive practices contained in that provision does not exhaust the methods of abusing a dominant position prohibited by EU law (judgments of 21 February 1973, Europemballage and Continental Can v Commission, 6/72, EU:C:1973:22, paragraph 26; of 17 February 2011, TeliaSonera Sverige, C‑52/09, EU:C:2011:83, paragraph 26; and of 29 March 2012, Telefónica and Telefónica de España v Commission, T‑336/07, EU:T:2012:172, paragraph 173).

113    In the present case, it should be pointed out that the argument presented by the applicant in the first plea in law refers only to the legal test applied by the Commission, in the seventh part of the contested decision (recitals 355 to 821), in order to classify a range of conduct of the applicant during the period under consideration as ‘refusal to supply’. By contrast, the applicant does not dispute the existence itself of the conduct noted by the Commission in that part of the contested decision. As is apparent from recitals 2 and 1507 of the contested decision, that conduct, which contributed to the identification by the Commission of a single and continuous infringement of Article 102 TFEU (recital 1511 of the contested decision), consisted, firstly, in concealing from alternative operators information relating to the applicant’s network, which is necessary for the unbundling of that operator’s local loop, secondly, in a reduction by the applicant of its obligations relating to unbundling under the applicable regulatory framework and, thirdly, in the establishment by that operator of a number of unfair terms and conditions in its reference offer relating to unbundling.

114    Moreover, as the applicant confirmed during the hearing, the first plea in law does not call into question the analysis of the conduct which consisted in a margin squeeze carried out by the Commission in the eighth part of the contested decision (recitals 822 to 1045 of the contested decision). In its action, the applicant does not dispute that that type of conduct constitutes an independent form of abuse distinct from that of refusal to provide access and the existence thereof is therefore not subject to the criteria laid down in the judgment of 26 November 1998, Bronner (C‑7/97, EU:C:1998:569) (see, to that effect, judgment of 10 July 2014, Telefónica and Telefónica de España v Commission, C‑295/12 P, EU:C:2014:2062, paragraph 75 and the case-law cited). Therefore, in essence, by its first and fifth complaints, the applicant alleges that the Commission classified the conduct referred to in paragraph 113 above as ‘refusal to supply’ access to its local loop without having verified the ‘indispensable’ nature of such access, for the purposes of the third condition set out in paragraph 41 of the judgment of 26 November 1998, Bronner (C‑7/97, EU:C:1998:569).

115    In that judgment, the Court indeed considered that, in order for the refusal by a dominant undertaking to grant access to a service to constitute an abuse within the meaning of Article 102 TFEU, that refusal must be likely to eliminate all competition on the market on the part of the person requesting the service, such refusal must not be capable of being objectively justified, and the service must in itself be indispensable to carrying on that person’s business (judgment of 26 November 1998, Bronner, C‑7/97, EU:C:1998:569, paragraph 41; see, also, judgment of 9 September 2009, Clearstream v Commission, T‑301/04, EU:T:2009:317, paragraph 147 and the case-law cited).

116    Moreover, it is clear from paragraphs 43 and 44 of the judgment of 26 November 1998, Bronner (C‑7/97, EU:C:1998:569), that, in order to determine whether a product or service is indispensable for enabling an undertaking to carry on business in a particular market, it must be determined whether there are products or services which constitute alternative solutions, even if they are less advantageous, and whether there are technical, legal or economic obstacles capable of making it impossible or at least unreasonably difficult for any undertaking seeking to operate in the market to create, possibly in cooperation with other operators, alternative products or services. According to paragraph 46 of the judgment of 26 November 1998, Bronner (C‑7/97, EU:C:1998:569), in order to accept the existence of economic obstacles, it must be established, at the very least, that the creation of those products or services is not economically viable for production on a scale comparable to that of the undertaking which controls the existing product or service (judgment of 29 April 2004, IMS Health, C‑418/01, EU:C:2004:257, paragraph 28).

117    However, in the present case, since the legislation relating to the telecommunications sector defines the legal framework applicable to it and, in so doing, contributes to the determination of the competitive conditions under which a telecommunication undertaking carries on its business in the relevant markets, that legislation constitutes a relevant factor in the application of Article 102 TFEU to the conduct of that undertaking, in particular for assessing the abusive nature of such conduct (judgment of 14 October 2010, Deutsche Telekom v Commission, C‑280/08 P, EU:C:2010:603, paragraph 224).

118    As the Commission correctly points out, the conditions referred to in paragraph 115 above were laid down and applied in the context of cases dealing with the question whether Article 102 TFEU could be such as to require the undertaking in a dominant position to supply to other undertakings access to a product or service, in the absence of any regulatory obligation to that end.

119    Such a context differs from that of the present case, in which TUSR, by a decision of 8 March 2005 confirmed by the director of that authority on 14 June 2005, required the applicant to grant all reasonable and justified requests for unbundling of its local loop, in order to enable alternative operators, on that basis, to offer their own services on the retail mass market for broadband services at a fixed location in Slovakia (paragraph 9 above). That requirement resulted from the public authorities’ intention to encourage the applicant and its competitors to invest and innovate, whilst ensuring that competition in the market is maintained (recitals 218, 373, 388, 1053 and 1129 of the contested decision).

120    As is stated in recitals 37 to 46 of the contested decision, TUSR’s decision, taken in accordance with Law No 610/2003, implemented in Slovakia the requirement of unbundled access to the local loop of operators with significant market power on the market for the provision of fixed public telephone networks, provided for in Article 3 of Regulation No 2887/2000. The EU legislature justified that requirement, in recital 6 of that regulation, by the fact that ‘it would not be economically viable for new entrants to duplicate the incumbent’s metallic local access infrastructure in its entirety within a reasonable time[, since a]lternative infrastructures … do not generally offer the same functionality or ubiquity’.

121    Therefore, given that the relevant regulatory framework clearly acknowledged the need for access to the applicant’s local loop, in order to allow the emergence and development of effective competition in the Slovak market for high-speed internet services, the demonstration, by the Commission, that such access was indeed indispensable for the purposes of the last condition set out in paragraph 41 of the judgment of 26 November 1998, Bronner (C‑7/97, EU:C:1998:569), was not required.

122    It follows from the above that the Commission cannot be criticised for failing to establish the indispensable nature of access to the network at issue.

123    It should be added that such a complaint can also not be made against the Commission if it had to be considered that the implied refusal of access at issue was covered by the considerations in the judgment of 17 February 2011, TeliaSonera Sverige (C‑52/09, EU:C:2011:83). In that judgment, the Court held that it cannot be inferred from paragraphs 48 and 49 of the judgment of 26 November 1998, Bronner (C‑7/97, EU:C:1998:569), that the conditions to be met in order to establish that a refusal to supply is abusive, which was the object of the first question referred for a preliminary ruling examined in that case, must necessarily also apply when assessing the abusive nature of conduct which consists in supplying services or selling goods on conditions which are disadvantageous or on which there might be no purchaser (judgment of 17 February 2011, TeliaSonera Sverige, C‑52/09, EU:C:2011:83, paragraph 55). In that regard, the Court held that such conduct may, in itself, constitute an independent form of abuse distinct from that of refusal to supply (judgment of 17 February 2011, TeliaSonera Sverige, C‑52/09, EU:C:2011:83, paragraph 56).

124    The Court, moreover, stated that a different interpretation of the judgment of 26 November 1998, Bronner (C‑7/97, EU:C:1998:569), would amount to a requirement that any conduct of a dominant undertaking in relation to its terms of trade could be regarded as abusive, the conditions to be met to establish that there was a refusal to supply would in every case have to be satisfied, and that would unduly reduce the effectiveness of Article 102 TFEU (judgment of 17 February 2011, TeliaSonera Sverige, C‑52/09, EU:C:2011:83, paragraph 58).

125    The applicant correctly notes, concerning that point, that the practice at issue in the main proceedings examined by the Court in the judgment of 17 February 2011, TeliaSonera Sverige (C‑52/09, EU:C:2011:83), merely consisted, as is apparent from paragraph 8 of that judgment, in a possible margin squeeze by the historical Swedish fixed telephone network operator in order to discourage requests by alternative operators for access to its local loop. It cannot be deduced therefrom that the interpretation given by the Court in that judgment of the scope of the conditions set out in paragraph 41 of the judgment of 26 November 1998, Bronner (C‑7/97, EU:C:1998:569), is limited to that sole form of abusive conduct and does not cover practices which are not strictly related to pricing such as those examined in the present case by the Commission in the seventh part of the contested decision (see paragraphs 27 to 41 above).

126    It should, first of all, be noted that, in paragraphs 55 to 58 of the judgment of 17 February 2011, TeliaSonera Sverige (C‑52/09, EU:C:2011:83), the Court did not refer to the particular form of abuse constituted by the margin squeeze of competitor operators in a downstream market, but rather to the supply of ‘services or selling goods on conditions which are disadvantageous or on which there might be no purchaser’ and to ‘terms of trade’ fixed by the dominant undertaking. Such wording suggests that the exclusionary practices to which reference was therefore made concerned not solely a margin squeeze, but also other business practices capable of producing unlawful exclusionary effects for current or potential competitors, like those classified by the Commission as an implicit refusal to supply access to the applicant’s local loop (see, to that effect, recital 366 of the contested decision).

127    That reading of the judgment of 17 February 2011, TeliaSonera Sverige (C‑52/09, EU:C:2011:83), is supported by the reference made by the Court, in that part of its analysis, to paragraphs 48 and 49 of the judgment of 26 November 1998, Bronner (C‑7/97, EU:C:1998:569). Those paragraphs dealt with the second question for a preliminary ruling referred to the Court in that case and did not concern the refusal by the dominant undertaking at issue in the dispute in the main proceedings to give access to its home-delivery scheme to the publisher of a rival newspaper, examined in the context of the first question, but the possible classification as abuse of a dominant position of a practice which consisted for that undertaking in making such access subject to the condition that the publisher at issue entrust to it the carrying out of other services, such as sales in kiosks or printing.

128    In the light of the foregoing, it is necessary to conclude that the classification of the applicant’s conduct examined in the seventh part of the contested decision as abusive practices for the purposes of Article 102 TFEU did not presuppose that the Commission establish that the access to the applicant’s local loop was indispensable to the exercise of the activity of competitor operators in the retail market for fixed broadband services in Slovakia, for the purposes of the case-law cited in paragraph 116 above.

129    Therefore, the first and fifth complaints of the plea in law must be rejected as unfounded.

(b)    The third complaint

130    By its third complaint, the applicant claims that the non-application of the conditions of the judgment of 26 November 1998, Bronner (C‑7/97, EU:C:1998:569), in the case of a constructive refusal to supply access leads to inconsistency in terms of competition policy. In those circumstances, it is easier to prove a constructive refusal to supply access than an outright refusal, with the result that the more serious type of abuse would be treated less severely than the less serious abuse. In the present case, at least one of the applicant’s competitors had access to its network, with the result that the refusal of access would not be outright (recital 408 of the contested decision). Outright refusal is more serious than constructive refusal of access, although the Commission’s approach would result in the conditions of the judgment of 26 November 1998, Bronner (C‑7/97, EU:C:1998:569), applying to the outright refusal and not to the constructive refusal of access.

131    However, the Commission offers no explanation as to why, in general terms, a constructive refusal of access must be treated more severely than an outright refusal of access or why, in particular, the conditions of the judgment of 26 November 1998, Bronner (C‑7/97, EU:C:1998:569), no longer need to be satisfied in the former case.

132    The Commission and the intervener dispute those arguments.

133    In that regard, it suffices to note that that argument is based on an erroneous premiss, namely that the seriousness of an infringement of Article 102 TFEU consisting in a refusal by a dominant undertaking to supply a product or service to other undertakings depends solely on its form. The gravity of such an infringement is likely to depend on numerous factors independent of the explicit or implicit nature of that refusal, such as the geographic scope of the infringement, whether it is intentional, or further to its effects on the market. The 2006 Guidelines confirm that analysis when they state, in paragraph 20 thereof, that the assessment of the gravity of an infringement of Article 101 or Article 102 TFEU is made on a case-by-case basis for all types of infringement, taking account of all the relevant circumstances of the case.

134    Finally, it must be noted that, in paragraph 69 of the judgment of 17 February 2011, TeliaSonera Sverige (C‑52/09, EU:C:2011:83), the Court observed that the indispensable nature of the wholesale product could be relevant in order to assess the effects of a margin squeeze. However, in the present case, it must be pointed out that the applicant invoked the Commission’s obligation to show the indispensable nature of the unbundled access to the applicant’s local loop only in support of its claim that the Commission failed to apply the legally appropriate criteria during its assessment of the practices examined in the seventh part of the contested decision (see, by analogy, judgment of 29 March 2012, Telefónica and Telefónica de España v Commission, T‑336/07, EU:T:2012:172, paragraph 182), and not so as to call into question the Commission’s assessment of the anticompetitive effects of those practices, carried out in the ninth part of that decision (recitals 1046 to 1109 of the contested decision).

135    Therefore the third complaint must be rejected as unfounded.

(c)    The second complaint

136    By its second complaint, the applicant submits that the failure to apply the conditions of the judgment of 26 November 1998, Bronner (C‑7/97, EU:C:1998:569), in the contested decision is at odds with the judgment of 9 September 2009, Clearstream v Commission (T‑301/04, EU:T:2009:317), particularly paragraph 146 thereof, which, despite relating to a constructive refusal of sale, as mentioned in recital 360 of the contested decision, applies those conditions. The Commission is wrong because, in the Clearstream case, the de facto monopoly of the company at issue had statutory protection, even though the conditions of the judgment of 26 November 1998, Bronner (C‑7/97, EU:C:1998:569), were satisfied. Unlike the case giving rise to the judgment of 9 September 2009, Clearstream v Commission (T‑301/04, EU:T:2009:317), the Commission is, in this case, unable to demonstrate the indispensability of the applicant’s DSL network. That is why it goes to such lengths to distinguish it from the Bronner and Clearstream cases.

137    The Commission and the intervener dispute those arguments.

138    In that regard, it must be noted, as the Commission correctly maintained, that there is no contradiction between the approach taken by the Commission in the case giving rise to the judgment of 9 September 2009, Clearstream v Commission (T‑301/04, EU:T:2009:317), and in the present case, since, in that first case, there was no obligation for the dominant undertaking to supply the service at issue and the dominant undertaking had not developed its market position in the context of a legal monopoly.

139    As is apparent from the case-law referred to in paragraph 117 above, since the legislation relating to the telecommunications sector defines the legal framework applicable to it and, in so doing, contributes to the determination of the competitive conditions under which a telecommunications undertaking carries on its business in the relevant markets, that legislation is a relevant factor in the application of Article 102 TFEU to the conduct of that undertaking, in particular in assessing the abusive nature of such conduct.

140    Consequently, the second complaint must be rejected as unfounded.

(d)    The fourth complaint

141    By its fourth complaint the applicant claims that the contested decision is vitiated by errors of fact and of law as well as an insufficient statement of reasons in recital 370. In that recital, the Commission defended the derogation from the conditions of the judgments of 26 November 1998, Bronner (C‑7/97, EU:C:1998:569), stating that those conditions did not apply to a refusal to supply access because, first, the applicant was subject to a regulatory obligation to grant access to the local loop under earlier rules and, secondly, because the applicant’s network was developed under a former State monopoly.

142    In the first place, as regards the errors of fact and law relating to those two justifications, firstly, the applicant claims that the Commission committed errors by asserting that it was necessary to derogate from the conditions of the judgment of 26 November 1998, Bronner (C‑7/97, EU:C:1998:569), due to the existence of the obligation to grant access to the local loop deriving from earlier rules.

143    In that regard, the applicant argues that such an obligation does not necessarily have implications as regards the conditions for the application of Article 102 TFEU, since they pursue different objectives. The Commission erred in law by failing to draw the distinction, flowing from paragraph 113 of the judgment of 10 April 2008, Deutsche Telekom v Commission (T‑271/03, EU:T:2008:101), between the role of an ex ante regulatory obligation, which seeks to reduce the market power of dominant undertakings, and the role of ex post competition law, under which the main focus of the authorities is the specific conduct of undertakings and whether their use of any market power was abusive.

144    More particularly, an obligation to sell may be imposed by ex ante legislation where the Commission’s power to impose such an obligation under Article 102 TFEU is exercisable only in exceptional circumstances. Although it is apparent from the case-law that the legislation relating to the telecommunications sector may be taken into account for the purpose of applying Article 102 TFEU to the conduct of a dominant undertaking (judgment of 14 October 2010, Deutsche Telekom v Commission, C‑280/08 P, EU:C:2010:603, paragraphs 224 and 227), the Commission did not, in the contested decision, merely take into account the obligations imposed under such legislation; instead, it relied entirely on the assessment carried out by TUSR and did not conduct any examination of its own.

145    According to the applicant, the considerations in the judgment of 10 April 2008, Deutsche Telekom v Commission (T‑271/03, EU:T:2008:101), from which it follows that secondary EU legislation ‘may’ be relevant under Article 102 TFEU, apply only in the context of that case, since the Court was required to examine whether the Commission had committed an error by noting the existence of a regulatory obligation under such legislation. It does not follow from that judgment or from the existence of a regulatory obligation that the Commission is able to sidestep the conditions of the judgment of 26 November 1998, Bronner (C‑7/97, EU:C:1998:569).

146    On the contrary, the applicant submits, and pointed out during the hearing, that Article 102 TFEU and the legislation at issue pursue different objectives, so that a national regulatory authority may decide to increase competition on the market while an obligation to deal can be imposed under Article 102 TFEU only to remedy an abusive refusal of access.

147    Moreover, the reference to Article 21(3) of Law No 610/2003, to which the Commission referred to argue that TUSR weighed up the interests involved, was not cited in that ’authority’s earlier decisions. In any event, the general duty to conduct a balancing exercise under domestic law does not mean that the Commission is entitled to disregard the conditions of the judgment of 26 November 1998, Bronner (C‑7/97, EU:C:1998:569). It is for the Commission to demonstrate that, where there is an earlier regulatory obligation, the conditions of the judgment of 26 November 1998, Bronner (C‑7/97, EU:C:1998:569), do not apply. The applicant acknowledges that, while it is true that there was no relevant regulatory obligation in the case which gave rise to that judgment, that does not lead to the conclusion which the Commission seeks to draw.

148    Secondly, as regards the justification according to which the applicant’s network was developed in the context of a monopoly, the applicant claims that the case-law relied upon by the Commission, in the contested decision, does not allow that second justification to be rejected. First of all, paragraph 109 of the judgment of 17 February 2011, TeliaSonera Sverige (C‑52/09, EU:C:2011:83), cited by the Commission, is not relevant. Next, it follows from paragraph 23 of the judgment of 27 March 2012, Post Danmark (C‑209/10, EU:C:2012:172), to which the Commission refers, that the existence of a former State monopoly may be relevant when considering the conduct of an undertaking. Therefore, that judgment is not authority for the proposition that the conditions of the judgment of 26 November 1998, Bronner (C‑7/97, EU:C:1998:569), do not apply.

149    The contention that the conditions of the judgment of 26 November 1998, Bronner (C‑7/97, EU:C:1998:569), do not apply where the network at issue has its historical origins in a State monopoly is wrong because Article 102 TFEU does not envisage any special treatment for former State monopolies. On the contrary, the Commission has stated in the past that the historical nature of a monopoly was not relevant to the present-day assessment of abuse under Article 102 TFEU.

150    The Commission and the intervener dispute those arguments.

151    In that regard, it suffices, in order to reject those arguments, to note that the observations in paragraphs 117 to 121 above are not based on the premiss that the obligation imposed on the applicant to grant unbundled access to its local loop results from Article 102 TFEU, but merely notes, in accordance with the case-law cited in paragraph 117 above, that the existence of such a regulatory obligation is a relevant aspect of the economic and legal context in which it is necessary to assess whether the applicant’s practices examined in the seventh part of the contested decision could be classified as abusive practices for the purposes of that provision.

152    Moreover, the reference made by the applicant to paragraph 113 of the judgment of 10 April 2008, Deutsche Telekom v Commission (T‑271/03, EU:T:2008:101), to support the argument set out in paragraph 143 above, is not relevant. The Court admittedly held, in paragraph 113 of that judgment, that the national regulatory authorities operate under national law which may have objectives which differ from those of EU competition policy. That reasoning sought to support the Court’s rejection of the applicant’s argument invoked in that case, according to which, in essence, the ex-ante control of its charges by the German regulatory authority for telecommunications and post precluded that Article 102 TFEU could be applied to a possible margin squeeze resulting from its charges for unbundled access to its local loop. That paragraph was therefore unconnected with the question whether the existence of a regulatory obligation of access to the local loop of the dominant operator is relevant in order to assess the compliance of its access policy with Article 102 TFEU.

153    Moreover, it follows from settled case-law that the existence of a dominant position resulting from a legal monopoly must be taken into consideration in the context of the application of Article 102 TFEU (see, to that effect, judgment of 27 March 2012, Post Danmark, C‑209/10, EU:C:2012:172, paragraph 23 and the case-law cited).

154    Therefore, in so far as it alleges errors of law and fact relating to the justifications put forward by the Commission in order to defend the derogation from the conditions of the judgment of 26 November 1998, Bronner (C‑7/97, EU:C:1998:569), and relating to the applicant’s obligation, deriving from the earlier rules, to grant access to the local loop and to the existence of a pre-existing State monopoly, the fourth complaint must be rejected as unfounded.

155    In the second place, the applicant alleges that the Commission failed to state adequate reasons relating to the justification that that institution put forward with a view to derogating from the conditions of the judgment of 26 November 1998, Bronner (C‑7/97, EU:C:1998:569), and consisting in the need to make first-time access mandatory. The Commission did not conduct any examination as to the existence of an earlier regulatory obligation, did not analyse the content of that obligation and did not explain why first-time access should be mandatory or why the lack of such access would eliminate all effective competition. The Commission did not provide any evidence to support its assessment that national legislation had weighed up the incentives of the applicant for keeping its facilities for its own use against those of undertakings potentially wishing access to the local loop. The contested decision fails to demonstrate why the regulatory obligations concerned provide a sufficient basis for disregarding the conditions of the judgment of 26 November 1998, Bronner (C‑7/97, EU:C:1998:569). The Commission was required to give particularly clear, compelling and detailed reasons as to why first-time access should be mandatory and, in consequence, why the failure to grant access would eliminate all effective competition.

156    In the reply, firstly, the applicant adds that recitals 36 to 49 of the contested decision contain only a general description of the regulatory framework and a brief description of the earlier access obligation. That statement of reasons does not address the question whether that obligation justifies disregarding the conditions of the judgment of 26 November 1998, Bronner (C‑7/97, EU:C:1998:569).

157    Secondly, TUSR did not refer to the Slovakian regulatory provisions relating to the balancing exercise when it imposed the earlier obligations. In any event, the balancing exercise under the earlier rules is different from that under Article 102 TFEU. Moreover, an argument based on the balancing exercise allegedly carried out by TUSR cannot, according to the applicant, justify the complete lack of reasons as regards the other conditions of the judgment of 26 November 1998, Bronner (C‑7/97, EU:C:1998:569).

158    Thirdly, when the Commission contends that the conditions of the judgment of 26 November 1998, Bronner (C‑7/97, EU:C:1998:569), do not apply anyway in the present case, it is confusing the question of the merits of the decision with the obligation to state reasons.

159    Fourthly, the applicant claims that, as regards the reference to Section 9.3 of the contested decision relating to anticompetitive effects, that section does not state the reasons for the decision. The applicant claims, first of all, that the elimination of all effective competition is just one of the conditions of the judgment of 26 November 1998, Bronner (C‑7/97, EU:C:1998:569), while the failure to state reasons exists as regards the other conditions of that judgment. Next, the examination of anticompetitive effects in the contested decision does not replace the need to provide specific reasons concerning the indispensability condition. Lastly, that section rebuts the Commission’s argument in so far as it contains evidence demonstrating a lack of anticompetitive effects.

160    Moreover, as regards the justification based on the fact that the applicant’s network was developed in the context of a monopoly, the applicant claims that the statement of reasons contained in recital 373 of the contested decision is not sufficient to explain why the Commission found the existence of a former State monopoly to be relevant to the consideration of abuse under Article 102 TFEU.

161    According to the applicant, since the Commission is subject to the principle of good administration, it is responsible for examining the specific circumstances of the former State monopoly that it seeks to rely on as the basis for disregarding the conditions of the judgment of 26 November 1998, Bronner (C‑7/97, EU:C:1998:569), circumstances which are highly relevant. The applicant also submits that it is not possible to describe as factual details of no particular relevance the information provided in recital 891 of the contested decision relating to the applicant’s investments in broadband assets between 2003 and 2010. The applicant claims that, on the contrary, the Commission should have considered the nature and impact of those investments when compared with its historical position. The applicant concludes that if the statement of reasons contained in the contested decision was adequate, that would mean, in practice, that no limitation is imposed on the Commission where a State monopoly has existed in the past.

162    The Commission and the intervener dispute those arguments.

163    In that regard, the statement of reasons required by Article 296 TFEU must be appropriate to the act at issue and must disclose in a clear and unequivocal fashion the reasoning followed by the institution which adopted the measure, in such a way as to enable the persons concerned to ascertain the reasons for the measure and to defend their rights and the Court to exercise its power of review. In the case of a decision adopted pursuant to Article 102 TFEU, that principle requires that the contested decision mention facts forming the basis of the legal grounds of the measure and the considerations which led to the adoption of the decision (judgment of 9 September 2010, Tomra Systems and Others v Commission, T‑155/06, EU:T:2010:370, paragraph 227).

164    Firstly, the applicant considers that the contested decision does not contain an examination concerning the existence of an earlier regulatory obligation, or an analysis of its contents, or evidence supporting the Commission’s assessment that the national legislation had weighed up the incentives of the applicant for keeping its facilities for its own use against those of undertakings potentially wishing access to the local loop. It also does not put forward why the regulatory obligations allow the conditions of supply access arising from the judgment of 26 November 1998, Bronner (C‑7/97, EU:C:1998:569), to be disregarded. However, it must be noted that, first, the Commission set out, in the contested decision, the regulatory framework relating to unbundled access to the local loop in Slovakia in recitals 36 to 46 of the contested decision. Secondly, it set out the legal framework concerning abusive refusals to grant access in recitals 355 to 371 of the contested decision, explaining, more particularly, that it considered the present case to differ from the circumstances of the case giving rise to the judgment of 26 November 1998, Bronner (C‑7/97, EU:C:1998:569), and that that judgment does not apply in the present case. Therefore, the argument put forward by the applicant must be rejected.

165    Secondly, as regards the applicant’s claim that the Commission was required to give particularly clear, compelling and detailed reasons as to why the failure to grant access would eliminate all effective competition, it should be noted that, in the present case, the applicant invoked the indispensable nature of the unbundled access to its local loop only in support of its claim that the Commission failed to apply the legally appropriate criteria during its assessment of the practices examined in the seventh part of the contested decision (see, by analogy, judgment of 29 March 2012, Telefónica and Telefónica de España v Commission, T‑336/07, EU:T:2012:172, paragraph 182), and not so as to call into question the Commission’s assessment of the anticompetitive effects of those practices, carried out in the ninth part of that decision (recitals 1046 to 1109 of the contested decision). In any event, the reasoning contained in that part of the contested decision is clear and unequivocal concerning the negative effects on competition of the applicant’s exclusionary conduct.

166    Thirdly, as regards the applicant’s claim that the statement of reasons included in recital 373 of the contested decision does not suffice in order to explain the reasons why the Commission considers that the existence of a former State monopoly is relevant for the purposes of examining an abuse in the light of Article 102 TFEU, it should be noted that the Commission, first of all, stated in that recital, referring to the specific provisions of Articles 8 and 12 of Directive 2002/21 and Article 21(3) of Law No 610/2003, that the applicant’s obligation to supply imposed by TUSR’s decision took account of the applicant’s incentives, as well as those of its competitors, to invest and innovate, while ensuring that competition in the market is maintained. The Commission added, in that recital 373, that it was possible that the imposition of an obligation to supply or grant access has no impact on incentives to invest or innovate, where the market position of the dominant undertaking had been developed under the protection of special or exclusive rights or had been financed by State resources, as happened in the present case. The Commission, next, referred to paragraph 23 of the judgment of 27 March 2012, Post Danmark (C‑209/10, EU:C:2012:172), from which it follows that where the existence of a dominant position has its origins in a former legal monopoly, that fact has to be taken into account, explaining that that was the situation of the applicant in the present case. The Commission, finally, took care to explain, in recital 373 of the contested decision, that it followed from recital 3 of Regulation No 2887/2000 that one of the reasons why the local access network remained one of the ‘least competitive segments of the liberalised telecommunications market’ was that new entrants did not have widespread alternative network infrastructures, given that operators, such as the applicant, for a long time, had rolled out their local access networks over significant periods of time protected by exclusive rights and had been able, for decades, to fund investment costs from monopoly rents from the provision of voice telephony services and public funds.

167    Furthermore, the Commission noted, in recital 370 of the contested decision, that it followed from paragraph 109 of the judgment of 17 February 2011, TeliaSonera Sverige (C‑52/09, EU:C:2011:83), that the structure of a market is also highly influenced by the former monopolistic structure.

168    In the light of all those reasons, it must be considered that the Commission gave sufficient reasons for its decision, where it concluded that the fact that the network at issue was developed under a monopoly constituted a relevant factor which it had to take into account in the context of the examination it conducted under Article 102 TFEU.

169    Therefore, it is necessary to reject the fourth complaint also in so far as it alleges a breach of the obligation to state reasons.

170    It follows from all of the foregoing that the first plea in law must be rejected as unfounded.

2.      Second plea in law: infringement of the applicant’s rights of defence as regards the assessment of the practice resulting in the margin squeeze

171    The second plea in law concerns the applicant’s rights of defence and is divided into two parts. The first part alleges that the Commission committed procedural errors regarding the calculation of the applicant’s long run average incremental costs (‘LRAIC’), that is to say the costs which that operator would not have had to bear if it had not offered the corresponding services. The second part alleges that it was not possible for the applicant to adopt a position during the administrative procedure about the multi-period approach to the calculation of the costs borne by the applicant in order to assess the existence of a practice resulting in the margin squeeze.

(a)    The first part, alleging procedural errors committed by the Commission concerning the calculation of the long run Average incremental costs (LRAIC)

172    The applicant complains that the Commission, first, changed the methods, the principles and the data for the purpose of conducting the analysis of the LRAIC and, secondly, failed, before the adoption of the contested decision, to communicate its objections to the information that the applicant had submitted to it in order to conduct that analysis. In the statement of objections, the Commission used solely the data from the applicant’s internal cost reporting system, namely ‘UCN’ data (účelové členenie nákladov) (classification of specific costs) and the summaries of profitability provided by the applicant, since the applicant did not have specific data relating to the LRAIC. According to the applicant, that ‘UCN’ data was based on top-down, fully allocated historical costs. That data relies on straight-line depreciation that does not allow for the recovery of costs over time. In the statement of objections (paragraph 1038), the Commission itself acknowledged the limitations of that data for the purposes of the assessment of the practice resulting in the margin squeeze and stated that those data were unsatisfactory. Accordingly, following the statement of objections, the applicant submitted new data, on the basis of the consultancy report prepared in February 2013 and sent to the Commission in the annex to the response to the statement of objections. That new data inter alia adjusted the historical costs. Therefore, the Commission accepted the re-evaluation and asset costs and depreciation put forward by the applicant (recital 894 of the contested decision).

173    The applicant notes that, by accepting a significant part of that data, the Commission considers the consultancy report to be credible. Likewise, the Commission did not raise objections, with respect to the principles, methodology and data provided by the applicant, before the adoption of the contested decision. However, in the contested decision, it rejected part of those principles, that methodology and that data (recital 899 of the contested decision). The applicant considers that the Commission should have sent notification, before the adoption of the contested decision, of the detailed objections relating to the principles, methodology and data which it had set out in that decision. The lack of such notification constitutes an infringement of the rights of the defence. According to the applicant, the Commission was required to set out in full the methodology, principles and cost-related data on which it intended to rely as part of its burden of proving the infringement and was also required to communicate its view to the applicant. In addition, the applicant unsuccessfully raised those procedural problems with the Hearing Officer.

174    Furthermore, the Commission itself acknowledges that, at the time of the statement of objections, it was not in possession of any data on the LRAIC, while the contested decision relies on those costs, meaning that the Commission changed its approach between those two documents. According to the applicant, since the Commission changed its approach after sending the statement of objections, the onus was on it to send a fresh statement of objections or a new statement of facts to the applicant.

175    Moreover, according to the applicant, the tables relating to the margin squeeze calculation provided by the Commission during the state of play meeting of 16 September 2014 did not support the relevant passages of the contested decision or observe its rights of defence. In that context, the applicant describes those tables as superficial, being only four pages long and lacking any explanation in support of the data contained therein. Similarly, the applicant claims that the Commission did not send it the tables until the meeting on the state of play of the file held on 16 September 2014, one month before publication of the contested decision, showing that the Commission’s position at that point in time was already fixed. The applicant noted, at the hearing, that, during that meeting, the Commission had indicated that it was in the process of drafting a negative decision regarding it. In any event, the disclosure of those tables demonstrates that the Commission felt compelled to send, after the statement of objections, a document setting out its margin squeeze calculation.

176    The Commission contests those arguments.

177    As is apparent from recital 862 of the contested decision, the Commission requested the applicant to supply the information necessary in order to calculate the costs relating to additional inputs which are necessary to transform its wholesale services into retail services. Before the statement of objections, the applicant sent the Commission calculations of the costs for 2003 to 2010 in ‘UCN’ spreadsheets and several spreadsheets containing additional calculations. In the context of the first part of its second plea in law, the applicant alleges, in essence, an infringement of its rights of defence in so far as the objections raised by the Commission concerning the methodology, the principles and the data which the applicant submitted were highlighted for the first time in recitals 860 to 921 of the contested decision.

178    In that regard, it should be recalled that observance of the rights of the defence in the conduct of administrative procedures relating to competition policy constitutes a general principle of EU law whose observance the European Courts ensure (see judgment of 18 June 2013, ICF v Commission, T‑406/08, EU:T:2013:322, paragraph 115 and the case-law cited).

179    That principle requires that the undertaking concerned must have been afforded the opportunity, during the administrative procedure, to make known its views on the truth and relevance of the facts and circumstances alleged and on the documents used by the Commission to support its claim that there has been an infringement of the rules on competition. To that end, Article 27(1) of Regulation No 1/2003 provides that the parties are to be sent a statement of objections. That statement must set out clearly all the essential elements on which the Commission is relying at that stage of the procedure (judgment of 5 December 2013, SNIA v Commission, C‑448/11 P, not published, EU:C:2013:801, paragraphs 41 and 42).

180    That requirement is satisfied where the final decision does not allege that the persons concerned have committed infringements other than those referred to in the statement of objections and only takes into consideration facts on which the persons concerned have had the opportunity of stating their views in the course of the procedure (see, to that effect, judgments of 24 May 2012, MasterCard and Others v Commission, T‑111/08, EU:T:2012:260, paragraph 266, and of 18 June 2013, ICF v Commission, T‑406/08, EU:T:2013:322, paragraph 117).

181    However, the essential facts on which the Commission is relying in the statement of objections may be set out summarily and the decision is not necessarily required to be a replica of the statement of objections, because that statement is a preparatory document containing assessments of fact and of law which are purely provisional in nature (see, to that effect, judgments of 17 November 1987, British American Tobacco and Reynolds Industries v Commission, 142/84 and 156/84, EU:C:1987:490, paragraph 70; of 5 December 2013, SNIA v Commission, C‑448/11 P, not published, EU:C:2013:801, paragraph 42 and the case-law cited; and of 24 May 2012, MasterCard and Others v Commission, T‑111/08, EU:T:2012:260, paragraph 267). Thus, it is permissible for the Commission to supplement the statement of objections in the light of the parties’ replies, whose arguments show that they have actually been able to exercise their rights of defence. The Commission may also, in the light of the administrative procedure, revise or supplement its arguments of fact or law in support of its objections (judgment of 9 September 2011, Alliance One International v Commission, T‑25/06, EU:T:2011:442, paragraph 181). Consequently, until a final decision has been adopted, the Commission may, in view, in particular, of the written or oral observations of the parties, abandon some or even all of the objections initially made against them and thus alter its position in their favour or decide to add new complaints, provided that it affords the undertakings concerned the opportunity of making known their views in that respect (see judgment of 30 September 2003, Atlantic Container Line and Others v Commission, T‑191/98 and T‑212/98 to T‑214/98, EU:T:2003:245, paragraph 115 and the case-law cited).

182    It results from the provisional nature of the legal classification of the facts made in the statement of objections that the Commission’s final decision cannot be annulled on the sole ground that the definitive conclusions drawn from those facts do not correspond precisely with that provisional classification (judgment of 5 December 2013, SNIA v Commission, C‑448/11 P, not published, EU:C:2013:801, paragraph 43). The taking into account of an argument put forward by a party during the administrative procedure, without it having been given the opportunity to express an opinion in that respect before the adoption of the final decision, cannot as such constitute an infringement of its rights of defence, where taking account of that argument does not alter the nature of the complaints against it (see, to that effect, order of 10 July 2001, Irish Sugar v Commission, C‑497/99 P, EU:C:2001:393, paragraph 24; judgments of 28 February 2002, Compagnie générale maritime and Others v Commission, T‑86/95, EU:T:2002:50, paragraph 447, and of 9 September 2011, Alliance One International v Commission, T‑25/06, EU:T:2011:442, paragraph 182).

183    The Commission is required to hear the addressees of a statement of objections and, where necessary, to take account of their observations made in response to the objections by amending its analysis specifically in order to respect their rights of defence. The Commission must therefore be permitted to clarify that classification in its final decision, taking into account the factors emerging from the administrative procedure, in order either to abandon such objections as have been shown to be unfounded or to amend and supplement its arguments, both in fact and in law, in support of the objections which it raises, provided however that it relies only on facts on which those concerned have had an opportunity to make known their views and provided that, in the course of the administrative procedure, it has made available the evidence necessary for their defence (see judgments of 3 September 2009, Prym and Prym Consumer v Commission, C‑534/07 P, EU:C:2009:505, paragraph 40 and the case-law cited, and of 5 December 2013, SNIA v Commission, C‑448/11 P, not published, EU:C:2013:801, paragraph 44 and the case-law cited).

184    Finally, it should be recalled that, according to established case-law, the rights of the defence are infringed where it is possible that, as a result of an error committed by the Commission, the outcome of the administrative procedure conducted by the latter might have been different. An applicant undertaking establishes that there has been such an infringement where it adequately demonstrates, not that the Commission’s decision would have been different in content, but rather that it would have been better able to ensure its defence had there been no error, for example because it would have been able to use for its defence documents to which it was denied access during the administrative procedure (see judgments of 2 October 2003, Thyssen Stahl v Commission, C‑194/99 P, EU:C:2003:527, paragraph 31 and the case-law cited, and of 24 May 2012, MasterCard and Others v Commission, T‑111/08, EU:T:2012:260, paragraph 269 and the case-law cited; judgment of 9 September 2015, Philips v Commission, T‑92/13, not published, EU:T:2015:605, paragraph 93).

185    In the present case, the Commission received, during the investigation, the data on costs in the ‘UCN’ spreadsheets, which constitute an accounting instrument of the applicant, representing, by commercial service and by service family, the total revenues, the total operating costs, the capital employed, the total cost of capital, the operating profit and the economic profit (recitals 863 and 864 of the contested decision). It follows from the contested decision that the costs included in the ‘UCN’ spreadsheets are based on fully allocated historical costs and differ from the LRAIC (recital 875 of the contested decision). The Commission also obtained presentations showing how the costs were grouped and tables and descriptions relating to the costs of each of the services (recitals 865 to 867 of the contested decision). The Commission requested the applicant to provide profitability data for broadband services, recalculated by using the LRAIC methodology (recitals 868 and 869 of the contested decision). Since the applicant confirmed that it did not calculate the profitability figures according to the LRAIC methodology for broadband services, the Commission used, at the statement of objections stage, the data at its disposal, namely the ‘UCN’ data and the explanations relating to costs, by adapting the individual costs (recitals 870 to 875 of the contested decision). According the Commission, at that stage, in the absence of data on the LRAIC, the figures contained in the ‘UCN’ spreadsheets were the best available source for the margin squeeze calculations (recital 875 of the contested decision). On that basis, in the statement of objections, the Commission established that an equally efficient competitor with access to the applicant’s local loop would have faced significant negative margins if it had tried to replicate the applicant’s retail broadband portfolio over the years 2005 to 2010 (paragraphs 1203 and 1222 of the statement of objections).

186    In the first place, as regards the complaint put forward by the applicant that it was not heard in relation to the principles, the methodology and the data relating to the calculation of the LRAIC, it should be noted that the applicant had the opportunity to respond to the arguments set out in the statement of objections and that it made full use of that possibility. Therefore, in its response to the statement of objections, on the basis of the consultancy report, the applicant submitted a methodology based on current cost accounting, by means of the estimation of the downstream costs for the period between 2005 and 2010 based on data from 2011 (recital 881 of the contested decision). In particular, the applicant claimed, in that response, that it was necessary, during the calculation of the LRAIC, first, to re-evaluate the assets and, secondly, to take into account the inefficiencies of its network for broadband provision. As regards, in particular, the taking into account of those inefficiencies, the applicant proposed to make optimisation adjustments, namely, firstly, the replacement of existing assets with their modern equivalents, which are more efficient and less costly (modern asset equivalent), secondly, to maintain as far as possible technical coherence and, thirdly, asset reduction on the basis of currently used capacity as opposed to the installed capacity (together, ‘the optimisation adjustments’).

187    In the contested decision, the Commission agreed to include in particular the applicant’s asset re-evaluation in its margin squeeze analysis and to remove, as concerns the specific fixed costs, the joint and common costs. By contrast, it rejects the optimisation adjustments (recitals 894, 903, 904 and 910 of the contested decision). Therefore, in the contested decision, the Commission identified margins which were different from those calculated in the statement of objections.

188    However, it should be noted that the changes made in the contested decision in relation to the statement of objections, concerning the calculation of the margin squeeze, resulted from taking into consideration data and calculations provided by the applicant itself in response to the statement of objections. That taking into consideration appears therefore, in particular, in recitals 910, 945, 963 and 984 of the contested decision. It is moreover apparent from recitals 946 (footnote No 1405) and 1000 of the contested decision that the Commission took account, during the adoption of that decision, of the update of the margin squeeze calculations provided by the applicant in its response to the letter of facts (paragraph 21 above).

189    In the second place, as regards the complaint put forward by the applicant that the Commission changed the principles, methodology and data relating to the calculation of the LRAIC, without having heard the applicant on that issue, first of all, it is apparent from the examination of the statement of objections and the contested decision that the Commission did not put forward any new objections in the contested decision with respect to its assessment of the margin squeeze. In those two documents, the Commission considered that an equally efficient competitor using access to the local loop on the applicant’s wholesale market would face significant negative margins if it offered the applicant’s portfolio of broadband services via the local loop (paragraph 1203 of the statement of objections and recital 1023 of the contested decision). In both documents, the Commission considered that that would remain the case even if additional services in a downstream portfolio, namely voice services, internet television services (IPTV) and multi-play services, were taken into consideration (paragraph 1222 of the statement of objections and recital 1023 of the contested decision). Next, it should be noted that the infringement period applied by the Commission is shorter in the contested decision than that applied by the Commission in the statement of objections. In both documents, the date of the beginning of the infringement was 12 August 2005. By contrast, the date of the end of the infringement was 8 May 2012 in the statement of objections (paragraph 1546 of the statement of objections) and is set at 31 December 2010 in the contested decision (recital 1516 of the contested decision). Finally, as regards the methodology for calculating the margins, the Commission relied, in both documents, on the LRAIC. Therefore, both in paragraphs 996 to 1002 of the statement of objections and in recitals 860 and 861 of the contested decision, the Commission set out the guidelines for the calculation of costs on the basis of the LRAIC.

190    More particularly, as regards the methodology for calculating the margins, it should be noted that the Commission applied the same method at the stage of the statement of objections and of the contested decision. Firstly, tables 48 and 78 to 80 of the statement of objections and tables 21 to 24 of the contested decision show the wholesale charges for access to the local loop. It must be noted that the Commission nevertheless was careful to explain in recitals 935 to 938 of the contested decision the reasons why it considered that there was a difference between the figures provided by the applicant and the figures presented in the calculations which it carried out. Secondly, it should be noted that table 81 of the statement of objections corresponds to table 25 of the contested decision, both tables showing the network costs. Table 25 is based on data provided in the applicant’s response to the statement of objections. Thirdly, it should be noted that table 82 of the statement of objections corresponds to table 26 of the contested decision, which shows the ISP (internet service provider costs) recurrent costs. The calculations of those costs are based on data provided by the applicant. Moreover, the Commission responds, in recitals 964 and 697 of the contested decision, to the applicant’s arguments in that regard presented in its response to the state of objections. Fourthly, it must be pointed out that table 83 of the statement of objections and table 27 of the contested decision relate to the local loop set-up fees and are identical. Fifthly, both table 86 of the statement of objections and tables 29 and 30 of the contested decision concern the depreciation of subscribers’ acquisition costs, table 29 taking into account a period of depreciation over three years and table 30 a period of depreciation over four years, in accordance with the applicant’s suggestion in its response to the statement of objections. Sixthly, it must be noted that table 87 of the statement of objections is identical to table 31 of the contested decision relating to revenues from the applicant’s bundled DSL Access and DSL internet services. Seventh, it should be pointed out that the results of the calculations of the margin squeeze are set out in table 88 of the statement of objections and in tables 32 and 33 of the contested decision, table 32 being based on the depreciation over three years and table 33 on the depreciation over four years.

191    It follows that the method and the principles that the Commission applied to examine the applicant’s margins were, in essence, identical in the statement of objections and in the contested decision. Consequently, the complaint put forward by the applicant, according to which the Commission changed those methods and those principles before adopting the contested decision, without having heard the applicant on that issue, must be rejected.

192    As regards the data on which the calculations of the margins are based, as was explained in recitals 875 to 877 of the contested decision, admittedly, at the stage of the statement of objections, those calculations were based on the ‘UCN’ tables which reflected the fully allocated costs. However, as follows from recitals 885 to 894 of the contested decision, the Commission accepted the adjustments made by the applicant concerning current cost accounting. The Commission thus took into account the adjustments proposed in that regard by the applicant and modified the costs of network assets, so that they constitute a more precise estimate of an equally efficient competitor’s costs. The taking those adjustments into account was specifically designed to satisfy the requirements noted in paragraph 183 above and the right of the parties to be heard during the administrative procedure therefore did not require that they be granted a new possibility to make known their point of view about the calculations of margins prior to the adoption of the contested decision.

193    In the light of the above, it is necessary to reject the first part relating to procedural errors concerning the calculation of the LRAIC.

(b)    The second part, alleging the inability to take a position, during the administrative procedure, about the multi-period approach to the calculation of the costs borne by the applicant in order to assess the existence of a practice resulting in the margin squeeze

194    The applicant notes that, in the statement of objections, the Commission applied a method consisting in analysing the costs, by not taking into account the positive margin found in 2005, although, in the contested decision, the approach taken involved a multi-period analysis. By failing to give the applicant the opportunity to submit observations on that approach, the Commission infringed its rights of defence. The applicant considers that, in contrast to the Commission’s assertions, it cannot be inferred from the response to the statement of objections that it itself proposed the multi-period approach. By contrast, the applicant proposed the discounted cash flow analysis, which was moreover applied by the Commission in its Decision C(2007) 3196 final, of 4 July 2007, relating to a proceeding under Article 82 [EC] (Case COMP/38.784 — Wanadoo España v Telefónica). The discounted cash flow analysis is justified by the duration of a customer’s subscription or a contract.

195    The applicant claims that, in addition, in the context of the discounted cash-flow analysis, the Commission should not have commenced the evaluation in 2005 and terminated it in 2010 simply because that period corresponded to that examined in the context of the ‘period-by-period’ approach.

196    Specifically, the multi-period approach used in the contested decision leads to a finding of a positive margin in 2005 and to the extension of the period of the alleged abuse compared with the period set out in the statement of objections. In that regard, the Commission, according to the applicant, ignored that positive margin when it stated, in recital 998 of the contested decision, that entry for four months in 2005 could not be considered entry ‘on a lasting basis’. The change of approach between the statement of objections and the contested decision transforms a positive margin in one year into a negative margin by selecting subsequent years of profitability and concluding that the net arithmetical difference was negative overall. Thus, the multi-period approach makes it impossible for a dominant undertaking to foresee the outcome of applying such an approach. Furthermore, the multi-period approach also leads to arbitrariness, since one or more periods could have both positive and negative margins at the same time depending on which years are used in that approach.

197    The Commission disputes the applicant’s arguments and contends that the present part should be rejected.

198    In that regard, the applicant complains, in essence, that the Commission used the multi-period approach in order to extend the period of infringement set out in the statement of objections, since such an approach was not envisaged in the statement of objections, and that it infringed its rights of defence, by failing to give it the possibility of presenting its observations relating to that approach.

199    It should be noted that, in paragraph 1012 of the statement of objections, the Commission initially stated its intention to use the period-by-period approach in relation to the examination of the applicant’s margins. The margin squeeze calculations included in paragraphs 1175 to 1222 of the statement of objections were made on a year-by-year basis during the period under consideration. In the contested decision, in order to assess the possible margin squeeze, the Commission adopted the ‘period-by-period’ approach consisting in determining the profits or losses realised over periods equivalent to one year (recital 851 of the contested decision). It should be noted that the summary of the results of the analysis is included in recitals 1007 to 1012 of the contested decision, from which it is apparent that the Commission bases its conclusions on the ‘period-by-period’ approach.

200    In paragraph 1281 of its response to the statement of objections, the applicant nevertheless opposed the sole use of the ‘period-by-period’ method, which had been used by the Commission in the statement of objections. The applicant claims in essence that, in the telecommunications sector, operators assessed their ability to obtain a reasonable return over a period exceeding one year. It thus proposed, inter alia, that the examination of a margin squeeze be supplemented by an analysis over several periods, in which the total margin would be evaluated over several years.

201    The Commission therefore decided to use, in addition, as is apparent from recital 859 of the contested decision, a multi-period approach so as to take account of that objection and in order to establish whether that approach altered its conclusion that the rates charged by the applicant for alternative operators to gain unbundled access to its local loop resulted in a margin squeeze between 2005 and 2010.

202    In the context of that additional examination, the result of which is included in recitals 1013 and 1014 of the contested decision, the Commission identified a total negative margin relating to each portfolio of services, first, for the period between 2005 and 2010 (table 39 in recital 1013 of the contested decision) and, secondly, for the period between 2005 and 2008 (table 40 in recital 1014 of the contested decision). The Commission inferred therefrom, in recital 1015 of the contested decision, that the multi-period analysis did not alter its finding of the existence of a margin squeeze resulting from a ‘period-by-period’ analysis.

203    It results from the above that, first, in order to establish the applicant’s margins in the contested decision, the multi-period analysis followed the objection, made by the applicant, in its response to the statement of objections, relating to the ‘period-by-period’ method of calculation. Secondly, the multi-period analysis of the margins for unbundled access to the applicant’s local loop, in the contested decision, aimed to complement the ‘period-by-period’ analysis. Moreover, the additional multi-period analysis led the Commission to consolidate its finding concerning the existence of a margin squeeze on the Slovak market for broadband internet services between 12 August 2005 and 31 December 2010.

204    Therefore, as the Commission, in essence, maintains, the multi-period analysis did not result in the applicant being held accountable for facts in respect of which the latter did not have the opportunity to express its views during the administrative procedure, by altering the nature of the objections made against it, but merely led to an additional analysis of the margins resulting from the applicant’s pricing practices for unbundled access to its local loop, in the light of an objection raised by the applicant in its response to the statement of objections.

205    As regards the argument that the Commission used the multi-period analysis in order to establish the infringement period and to substitute a negative margin for 2005 for a previously positive margin, it should be noted that, following the ‘period-by-period’ analysis, the Commission had already reached the conclusion that a competitor as efficient as the applicant could not have, between 12 August 2005 and 31 December 2010, replicated profitably the applicant’s retail portfolio comprising broadband services (recital 1012 of the contested decision). It is apparent in particular from recital 998 of the contested decision that, according to the Commission, the existence of a positive margin between August and December 2005 does not prevent that period from being included in the infringement period in the form of a margin squeeze, since operators consider their ability to obtain a return over a longer period. In other words, the Commission established the duration of the practice resulting in the margin squeeze on the basis of the ‘period-by-period’ approach and the multi-period approach was used solely by way of addition. In any event, it must be noted that that argument, in reality, seeks to contest the merits of that approach and cannot, therefore, be considered to be validly raised in support of an alleged infringement of the applicant’s rights of defence. In reality, that complaint relates to a disagreement with the methodology used by the Commission to find a margin squeeze for the period from 12 August to 31 December 2005.

206    Concerning the applicant’s argument that the method of calculating the margin squeeze applied by the Commission in the context of that additional examination does not correspond to the method suggested by the applicant in its response to the statement of objections and allegedly based on the Commission’s decision-making practice, it is apparent from paragraphs 1498 to 1500 of that response that the applicant proposes to examine the ‘cumulated profits’ over a period between 2005 and 2008. The Commission however noted that the multi-period analysis suggested by the applicant was distinct from the backward-looking analysis of the discounted expected cash flow, which was based on different input data and a different methodology (recital 858 of the contested decision). It nevertheless took note of the applicant’s suggestion concerning a multi-period analysis by undertaking, by way of addition, a multi-period examination, by analysing, in recital 1013 of the contested decision (table 39), the cumulated profits over a period between 2005 and 2010, and, in recital 1014 of that decision (table 40), the cumulated profits over a period between 2005 and 2008.

207    It is apparent from the case-law cited in paragraph 183 above that respect for the applicant’s right to be heard merely required the Commission to take account, for the purposes of adopting the contested decision, of the criticism concerning the calculation of margins presented by the applicant in response to the statement of objections. By contrast, that right in no way implied that the Commission must necessarily reach the conclusion desired by the applicant when it made that criticism, namely the finding that there was no margin squeeze between 12 August 2005 and 31 December 2010.

208    Finally, as regards the document including the calculation of the margins sent by the Commission during the state of play meeting of 16 September 2014, the applicant claims, in essence, first, that that document was presented to it late, since the Commission had announced that the contested decision was being drafted and, secondly, since the Commission felt obliged to disclose its final calculations of margins before sending the contested decision to it.

209    However, for the reasons set out in in paragraphs 183 and 199 to 204 above, the Commission was not obliged to disclose its final calculations of margins before sending the contested decision to the applicant. Moreover, the fact that it organised a ‘state-of-play meeting’ does not invalidate that assessment. As the Commission maintained in its pleadings and during the hearing, such meetings are organised between the Commission and the parties under investigation in the interests of sound administration and transparency and to inform them of the state of play of the procedure. Nevertheless, those ‘state-of-play meetings’ are distinct from the formal meetings required in accordance with Regulations Nos 1/2003 and 773/2004 and are complementary to them. Therefore, the fact that it organised a state of play meeting on 16 September 2014 does not allow it to be concluded that the Commission was obliged to permit the applicant to present, on that occasion, its observations relating to the examination of margins, and that all the more so since the applicant was informed about all of the material elements of the calculation of margins made by the Commission and was given the opportunity to present its observations prior to the adoption of the contested decision.

210    It follows that the second part of the second plea in law and that plea in law must be rejected.

3.      The third plea in law, alleging errors committed in the finding of the margin squeeze

211    By its third plea in law, the applicant essentially claims that the Commission’s finding of the practice resulting in the margin squeeze was incorrect. This plea is divided into two parts. The first part alleges that no account was taken of the optimisation adjustments proposed by the applicant in the calculation of its LRAIC. The second part alleges error on the part of the Commission in its margin squeeze calculation due to the consolidation of revenue and costs for the entire infringement period, as well as infringement of the principle of legal certainty.

(a)    First part alleging that no account was taken of the optimisation adjustments in the calculation of the applicant’s LRAIC

212    In support of the first part of its third plea in law, the applicant contests the Commission’s decision for not having accepted, in recitals 895 and 903 of the contested decision, the optimisation adjustments in order to calculate the margin squeeze. The inclusion of those optimisation adjustments would have reduced the upstream costs used in calculating the margin squeeze. Therefore, the reasons for that rejection set out by the Commission in recitals 894 and 900 to 902 of the contested decision are misconceived. Consequently, the Commission overestimated the applicant’s actual downstream costs which, as a result, had material consequences for the findings relating to the margin squeeze, given that there was no margin squeeze in 2005 and 2007.

213    According to the applicant, its proposals were not additional adjustments, but in issue was its calculation of the LRAIC. The Commission’s approach was inconsistent. On the one hand, it accepted the current cost accounting and, on the other hand, rejected the optimisation adjustments, which are compatible with the calculations of the LRAIC. As regards the adjustments of the network costs, the applicant considers that those adjustments, which are necessary in order to estimate the LRAIC, took into account a certain level of spare capacity included in the requirements for retail broadband services.

214    That approach is borne out by the case-law. Relying on the judgments of 17 February 2011, TeliaSonera Sverige (C‑52/09, EU:C:2011:83), and of 10 April 2008, Deutsche Telekom v Commission (T‑271/03, EU:T:2008:101), the applicant notes that, in some circumstances, it may be wise to take account of competitors’ costs rather than those of the dominant undertaking. That is so in the present case, since the applicant did not have easy access to data to establish the LRAIC.

215    The Commission disputes the applicant’s arguments.

216    The applicant complains, in essence, that the Commission committed an error during the calculation of the LRAIC, by refusing, in recitals 895 to 903 of the contested decision, to adjust the latter to the level of costs which would have been incurred by an efficient operator building an optimal network adapted to meet current and future demand on the basis of information available at the time of the assessment carried out by the Commission.

217    Therefore, as was stated in paragraph 186 above, in its response to the statement of objections, the applicant, relying on the consultancy report, proposed a methodology based on current cost accounting, by means of the estimation of the downstream costs for the period between 2005 and 2010 based on data from 2011 (recital 881 of the contested decision). In particular, the applicant submitted, in that response, that it was necessary, during the calculation of the LRAIC, first, to re-evaluate the assets and, secondly, to take account of the inefficiencies of its network for broadband provision. As regards, in particular, taking those inefficiencies into account, the applicant proposed the optimisation adjustments described in paragraph 186 above.

218    In its own calculations of the LRAIC, the applicant thus adjusted the capital cost of the assets and their depreciation values in the years 2005 to 2010, as well as the operating costs of those assets, by relying on the weighted average adjustment factor calculated by the author of the consultancy report for 2011 (recital 897 of the contested decision). The applicant claims that the suggested optimisation adjustments reflected the spare capacity identified in the elements of that network, namely assets removed from that network because they were not in productive use, but which had not yet been sold by that operator (recital 898 of the contested decision).

219    The Commission nevertheless refused to make those optimisation adjustments in the contested decision.

220    In the first place, as regards the replacement of existing assets with their more modern equivalents, the Commission stated, in recital 900 of the contested decision, that such a replacement could not be accepted since it amounts to adjusting the costs without properly adjusting the depreciations. The Commission referred to that paragraph in recitals 889 to 893 of the contested decision, in which it expressed doubts about the adjustment, as it was proposed by the applicant, of the costs of assets for the period between 2005 and 2010. Moreover, the Commission considered, in recital 901 of the contested decision, that such a replacement of existing assets was not compatible with the equally efficient competitor criterion. The case-law confirmed that the abusive nature of the pricing practices of a dominant operator is in principle determined in relation to its own position. In the present case, the adjustments of the LRAIC suggested by the applicant is based on a collection of hypothetical assets and not on the same assets as those held by that operator.

221    In the second place, as regards the taking into account of the excess capacity of the networks on the basis of ‘actually’ used capacity, the Commission concluded, in recital 902 of the contested decision, that, since investments are based on a forecast of demand, it was inevitable that, in the context of an ex post examination, a certain capacity remains sometimes unused.

222    None of the complaints put forward by the applicant against that part of the contested decision can be upheld.

223    Firstly, the applicant is wrong to claim that there is a contradiction between, on the one hand, the rejection of the optimisation adjustments of the LRAIC and, on the other hand, the acceptance, in recital 894 of the contested decision, of the asset re-evaluation which it proposed. The applicant also cannot claim that the Commission should have accepted the optimisation adjustments proposed by it on the ground that, as for the asset re-evaluation, the Commission did not have reliable historic costs concerning the optimisation adjustments.

224    The re-evaluation of the assets was based on the assets held by the applicant in 2011. With respect to that re-evaluation and as is apparent from recitals 885 to 894 of the contested decision, the Commission noted that it did not have at its disposal data better reflecting the applicant’s incremental broadband asset costs for the period between 2005 and 2010. As a result, in the analysis of the margin squeeze in the contested decision, the Commission included the applicant’s current assets proposed by the latter. However, the Commission pointed out that that re-evaluation was capable of leading to an underestimation of downstream asset costs.

225    By comparison, as is apparent from recital 895 of the contested decision, the optimisation adjustments proposed by the applicant consisted in adjusting the assets to the approximate level of an efficient operator that would build an optimal network adapted to satisfy future demand based on ‘today’s’ information and demand predictions. Those adjustments were based on a forecast and on an optimal network model, and not on an estimate reflecting the incremental costs of the applicant’s existing assets.

226    It follows that the optimisation adjustments, in general, and the replacement of existing assets by their more modern equivalents, in particular, had a different objective from the re-evaluation of assets proposed by the applicant. Furthermore, the taking into consideration, by the Commission, of the re-evaluation of current assets proposed by the applicant, due to the absence of other more reliable data on the LRAIC of that operator, did not suggest that the Commission necessarily accepted the optimisation adjustments of the LRAIC. The Commission was thus justified in treating differently, on the one hand, the replacement of existing assets by their more modern equivalents and, on the other hand, the re-evaluation of assets proposed by the applicant.

227    Secondly, the applicant cannot be followed when it disputes the conclusion, in recital 901 of the contested decision, that the optimisation adjustments would lead to a calculation of the LRAIC on the basis of the assets of a hypothetical competitor and not its own assets.

228    In that regard, it should be noted that, according to settled case-law, the assessment of the lawfulness of the pricing policy applied by a dominant undertaking, in the light of Article 102 TFEU, requires that reference be made, in principle, to pricing criteria based on the costs incurred by the dominant undertaking and on its strategy (see judgments of 17 February 2011, TeliaSonera Sverige, C‑52/09, EU:C:2011:83, paragraph 41 and the case-law cited, and of 29 March 2012, Telefónica and Telefónica de España v Commission, T‑336/07, EU:T:2012:172, paragraph 190; see also, to that effect, judgment of 10 April 2008, Deutsche Telekom v Commission, T‑271/03, EU:T:2008:101, paragraph 188 and the case-law cited).

229    In particular, as regards a pricing practice resulting in a margin squeeze, the use of such analytical criteria can establish whether, in accordance with the equally efficient competitor test referred to in paragraph 108 above, that undertaking would have been sufficiently efficient to offer its retail services to end-users otherwise than at a loss if it had first been obliged to pay its own wholesale prices for the intermediary services (judgments of 14 October 2010, Deutsche Telekom v Commission, C‑280/08 P, EU:C:2010:603, paragraph 201; of 17 February 2011, TeliaSonera Sverige, C‑52/09, EU:C:2011:83, paragraph 42; and of 29 March 2012, Telefónica and Telefónica de España v Commission, T‑336/07, EU:T:2012:172, paragraph 191).

230    The validity of such an approach is reinforced by the fact that it also conforms to the general principle of legal certainty, since taking into account the costs and prices of the dominant undertaking enables that undertaking, in the light of its special responsibility under Article 102 TFEU, to assess the lawfulness of its own conduct. While a dominant undertaking knows its own costs and prices, it does not as a general rule know those of its competitors (judgments of 14 October 2010, Deutsche Telekom v Commission, C‑280/08 P, EU:C:2010:603, paragraph 202; of 17 February 2011, TeliaSonera Sverige, C‑52/09, EU:C:2011:83, paragraph 44; and of 29 March 2012, Telefónica and Telefónica de España v Commission, T‑336/07, EU:T:2012:172, paragraph 192).

231    The Court admittedly stated, in paragraphs 45 and 46 of the judgment of 17 February 2011, TeliaSonera Sverige (C‑52/09, EU:C:2011:83), that it could not be ruled out that the costs and prices of competitors may be relevant to the examination of the practice resulting in the margin squeeze. It is apparent however from that judgment that it is only where it is not possible, in the light of the particular circumstances, to refer to the prices and costs of the dominant undertaking that the prices and costs of competitors on the same market should be examined, which the applicant has not claimed in the present case (see, by analogy, judgment of 29 March 2012, Telefónica and Telefónica de España v Commission, T‑336/07, EU:T:2012:172, paragraph 193).

232    In the present case, first, the replacement of existing assets by their more modern equivalents sought to adjust the costs of assets by retaining the value of ‘current’ assets, without however properly adjusting the depreciations (recital 900 of the contested decision). That replacement led to a calculation of the margin squeeze on the basis of hypothetical assets, namely assets which do not correspond with those held by the applicant. The costs relating to the applicant’s assets were thus underestimated (recitals 893 and 900 of the contested decision). Secondly, taking into consideration the excess capacity of the networks on the basis of the ‘currently’ used capacity would result in excluding the applicant’s assets which are not in productive use (see paragraph 218 above).

233    Therefore, in the light of the principles noted in paragraphs 228 to 231 above, the Commission was able to conclude without committing an error that the optimisation adjustments of the LRAIC proposed by the applicant would have resulted, during the calculation of the margin squeeze, in the costs incurred by that operator itself between 12 August 2005 and 31 December 2010 being disregarded.

234    Finally, the applicant cannot be followed when it claims that, in the contested decision, the Commission infringed the principle that the examination of a margin squeeze must be based on an effective competitor, when it concluded in essence that it was inevitable that there sometimes remains unused capacity (recital 902 of the contested decision). It follows from the principles referred to in paragraphs 230 and 231 above that the examination of a pricing practice resulting in a margin squeeze consists, in essence, in assessing whether a competitor as efficient as the dominant operator is capable of offering the services concerned to final customers otherwise than at a loss. Such an examination is therefore not carried out by reference to a perfectly efficient operator in the light of market conditions at the time of such a practice. If the Commission had accepted the optimisation adjustments linked to excess capacity, the calculations of the applicant’s LRAIC would have reflected the costs associated with an optimal network corresponding to demand and not affected by the inefficiencies of that operator’s network, namely the costs of a competitor more efficient than the applicant. Therefore, in the present case, although it is not disputed that part of the applicant’s relevant assets remained unused between 12 August 2005 and 31 December 2010, the Commission was able without committing an error to include that part of the assets, in other words the excess capacity, in the calculation of the LRAIC.

235    The Commission was thus correct to reject the optimisation adjustments and, therefore, to analyse the abusive nature of the applicant’s pricing practices, in particular, on the basis of the applicant’s costs.

236    Thirdly, contrary to what is claimed by the applicant, the rejection of the optimisation adjustments is not incompatible with the findings in the judgments of 17 February 2011, TeliaSonera Sverige (C‑52/09, EU:C:2011:83), and of 10 April 2008, Deutsche Telekom v Commission (T‑271/03, EU:T:2008:101), according to which it may be wise to take account of competitors’ costs rather than the costs of the dominant undertaking.

237    First, regarding the case giving rise to the judgment of 10 April 2008, Deutsche Telekom (T‑271/03, EU:T:2008:101, paragraph 210), the termination fees at issue constituted wholesale charges billed by the dominant undertaking to its competitor and making up part of the total cost borne by that competitor. Those fees had therefore to be included in the calculation of the costs of an equally efficient competitor. However, those fees were different from a forecast as well as from an optimal network model, which did not reflect the incremental costs of the applicant’s existing assets (see paragraph 225 above).

238    Secondly, as regards the judgment of 17 February 2011, TeliaSonera Sverige (C‑52/09, EU:C:2011:83), as referred to in paragraphs 230 and 231 above, it follows from that judgment that it is only when it is not possible, in the light of the circumstances, to refer to the prices and costs of the dominant undertaking that it is appropriate to examine those of the competitors on the same market. However, that is not the situation in the present case, since the costs of the applicant’s assets could be established on the basis of a later revaluation, and they constituted an indicator in order to evaluate the costs of an equally efficient competitor.

239    It follows from the above that the first part of the third plea in law must be rejected as unfounded.

(b)    The second part, alleging an error in the margin squeeze calculation due to the consolidation of revenue and costs for the entire period under consideration, as well as infringement of the principle of legal certainty

240    The applicant contests the Commission’s resorting to the multi-period approach (multi-annual approach set out in recital 1013 of the contested decision). The Commission adopted that approach, which does not exist in the statement of objections, in order to convert the positive margins into negative margins. It obtained positive margins, during the administrative procedure, by adopting the ‘period-by-period’ approach. However, by adopting the multi-period (multi-annual) approach, the Commission extended the period of the infringement. In particular, the ‘period-by-period’ (year-by-year) approach led to a finding of negative margins for each year during the period between 2005 and 2010. The negative margin of 2005, found in the statement of objections, was, however, transformed into a positive margin in the contested decision. Consequently, by applying the ‘period-by-period’ (year-by-year) approach, in actual fact, there was no practice resulting in the margin squeeze in 2005. Relying on a numerical example, the applicant concludes that, in accordance with the multi-period (multi-annual) approach used by the Commission, a margin squeeze could be found for the entire period, whereas that is not the case when each year is consolidated.

241    Therefore, the multi-period (multi-annual) approach is arbitrary and incompatible with the principle of legal certainty, since the infringement period depends entirely on the period over which the margins are aggregated and compared.

242    The applicant considers that, if those errors were corrected, there would be no basis for a finding of the practice resulting in the margin squeeze and the Commission would not have discharged its burden of proving the infringement. Annex A.21 to the application demonstrates the existence of a material error in the Commission’s costs and revenue analysis.

243    The Commission’s argument that a finding of a practice resulting in the margin squeeze may be made, notwithstanding the existence of a positive margin, is at odds with the case-law, as the legal test, in order to establish that a pricing practice resulting in a margin squeeze is abusive for the purposes of Article 102 TFEU, is whether the undertaking itself or an undertaking as efficient as it would have been in a position to offer its services to subscribers otherwise than at a loss. A positive margin does not necessarily lead to an abuse. The necessary precondition for a finding of a practice resulting in an abusive margin squeeze is the existence of a negative margin at an equally efficient competitor, which was not demonstrated in the present case for 2005.

244    Moreover, the Commission’s contention that the multi-period (multi-annual) approach was proposed by the applicant is incorrect, since, in reality, it suggested the updating method referred to in paragraph 194 above.

245    In the first place, the Commission notes that it is apparent from recitals 997 and 998 of the contested decision that the ‘period-by-period’ (year-by-year) approach allowed it to be demonstrated that an equally efficient competitor using, on the wholesale market, access to the applicant’s local loop faced negative margins and could not replicate profitably the applicant’s retail broadband portfolio. That conclusion is not undermined by the fact that the margin was positive for the last four months of 2005. It is only after reaching that conclusion that the Commission strengthened its analysis with the ‘multi-period’ approach. As regards the arguments relating to the validity of that multi-period (multi-annual) approach, the Commission refers back to the arguments it submitted in the context of the second part of the second plea in law.

246    In the second place, the Commission maintains that it follows from the judgment of 17 February 2011, TeliaSonera Sverige (C‑52/09, EU:C:2011:83, paragraphs 74 and 75), that an abusive squeeze may exist even where margins remain positive, where the dominant undertaking’s practices are likely to make it at least more difficult for the operators concerned to trade on the market by reason, for example, of artificially reduced profitability, where such practices are not economically justified. Consequently, the fact that the margin was positive for the last four months of 2005 does not automatically mean that the applicant’s conduct did not amount to abuse during that period. On the contrary, the Commission argues that such conduct constitutes abuse if the applicant’s pricing policy was likely to have an exclusionary effect for competitors that are at least as efficient as the applicant by making access to the market concerned more difficult or even impossible for them. In addition, when determining the lawfulness of the pricing policy applied by a dominant undertaking, reference should be made to that undertaking’s strategy which, in the case at hand, indicates that the applicant knew that it was setting higher prices than its average revenue for wholesale access at local loop level and that it could carry out a margin squeeze.

247    In the third place, as regards the criticisms of the multi-period (multi-annual) approach, the Commission repeats its arguments that the infringement period was already determined using the ‘period-by-period’ approach. On the basis of that approach, the Commission concluded that that infringement period commenced on 12 August 2005. The period adopted for the multi-period approach was determined by the infringement period which had already been established in the context of the ‘period-by-period’ approach. Moreover, the Commission submits that while it was aware of the shortcomings of the ‘multi-period’ (multi-annual) approach, that approach was proposed by the applicant in paragraphs 1388 and 1389 of its response to the statement of objections.

248    Finally, the applicant’s contention that the multi-period (multi-annual) approach could be based on the duration of a customer’s subscription or a contract is not supported by the case-law since, in the Telefónica case, as in the present case, the multi-period (multi-annual) analysis covered approximately five years, corresponding both to the length of the infringement and the lifetime of the relevant assets.

249    The intervener points out that the Commission’s approach, in calculating the margin squeeze, was prudent and to the applicant’s advantage since, with a view to avoiding purely hypothetical assumptions of those costs, collocation fees, which constituted, for alternative operators, an unknown amount and, for the applicant, a significant part of the costs connected with the local loop, were not included in the LRAIC.

250    By the second part of its third plea in law, the applicant accuses the Commission, in essence, of having applied the multi-period (multi-annual) approach solely in order to extend the infringement period to the last four months of 2005 during which, according the period-by-period (year-by-year) approach, there was a positive margin. The Commission thus wrongly concluded that there was a margin squeeze during 2005 and infringed the principle of legal certainty.

251    In that regard, it should be pointed out that the Commission concluded, relying on the ‘period-by-period’ (year-by-year) approach, that the applicant had engaged in margin squeeze practices from 12 August 2005. It is apparent from recital 997 of the contested decision that, on the basis of an analysis relating to every year during the period under consideration, an equally efficient competitor using wholesale access to the applicant’s local loop was faced with negative margins and could not replicate profitably the retail broadband portfolio of the applicant. In recital 998 of the contested decision, the Commission pointed out that the fact that there is a positive margin for four months in 2005 does not disprove that conclusion, given that an entry over four months could not be considered as entry on a lasting basis. According to the Commission, operators consider their ability to earn a reasonable return over a longer period, which extends over several years (recital 998 of the contested decision). On that basis, the Commission concluded, in recital 1012 of that decision, that, in the period between 12 August 2005 and 31 December 2010, a competitor as efficient as the applicant could not have replicated profitably that operator’s retail portfolio.

252    However, as was noted in paragraph 228 above, in order to assess the lawfulness of the pricing policy applied by a dominant undertaking, it is necessary, in principle, to refer to pricing criteria based on the costs incurred by the dominant undertaking itself and on its strategy.

253    In particular, as regards a pricing practice resulting in a margin squeeze, the use of such analytical criteria can establish whether that undertaking would have been sufficiently efficient to offer its retail services to end-users otherwise than at a loss if it had first been obliged to pay its own wholesale prices for the intermediary services (see paragraph 229 above and the case-law cited).

254    First, the validity of such an approach is all the more justified by the fact that it also conforms to the general principle of legal certainty, since taking into account the costs and prices of the dominant undertaking enables that undertaking, in the light of its special responsibility under Article 102 TFEU, to assess the lawfulness of its own conduct. While a dominant undertaking knows what its own costs and charges are, it does not, as a general rule, know what its competitors’ costs and charges are. Secondly, an exclusionary abuse also affects potential competitors of the dominant undertaking, which might be deterred from entering the market by the prospect of a lack of profitability (see paragraph 230 above and the case-law cited).

255    It follows therefrom that, in order to establish the constituent elements of the practice of a margin squeeze, the Commission, in recital 828 of the contested decision, correctly had recourse to the equally efficient competitor criterion, by demonstrating that the dominant undertaking’s downstream operations could not trade profitably on the basis of the wholesale price applied in respect of its downstream competitors and on the retail price applied by the downstream arm of that undertaking.

256    As is apparent from tables 32 to 35 of the contested decision, the analysis carried out by the Commission resulted, in all the scenarios envisaged and as the latter itself acknowledged in recital 998 of that decision, in a positive margin for the period between 12 August and 31 December 2005.

257    In such circumstances, the Court has already held that, to the extent that a dominant undertaking sets its prices at a level covering the great bulk of the costs attributable to the supply of the goods or services in question, it is, as a general rule, possible for a competitor as efficient as that undertaking to compete with those prices without suffering losses that are unsustainable in the long term (judgment of 27 March 2012, Post Danmark, C‑209/10, EU:C:2012:172, paragraph 38).

258    It results therefrom that, during the period between 12 August and 31 December 2005, a competitor as efficient as the applicant had, in principle, the possibility to compete with the latter on the retail market for broadband services in so far as unbundled access to the local loop was granted to it, and without suffering losses that were unsustainable in the long term.

259    The Court has indeed held that, if a margin is positive, it is not ruled out that the Commission can, in the context of the examination of the exclusionary effect of a pricing practice, demonstrate that the application of that practice was, by reason, for example, of reduced profitability, likely to have the consequence that it would be at least more difficult for the operators concerned to trade on the market concerned (see, to that effect, judgment of 17 February 2011, TeliaSonera Sverige, C‑52/09, EU:C:2011:83, paragraph 74). That case-law can be read in conjunction with Article 2 of Regulation No 1/2003, according to which, in any proceedings for the application of Article 102 TFEU, the burden of proving an infringement of that article rests on the party or the authority alleging the infringement, namely, in the present case, the Commission.

260    However, in the present case, it must be noted that the Commission did not demonstrate in the contested decision that the applicant’s pricing practice, during the period between 12 August and 31 December 2005, resulted in such exclusionary effects. However, such a demonstration was required particularly given the presence of positive margins.

261    The mere claim, in recital 998 of the contested decision, that the operators consider their ability to earn a reasonable return over a longer period, which lasted several years, cannot constitute such proof. Such a fact, assuming it is established, is based on a prospective examination of profitability, which is necessarily hypothetical. Furthermore, in the present case, those positive margins appeared at the very beginning of the period under consideration, at a time when no negative margin could yet have been found. In those circumstances, it must be concluded that the reason set out in recital 998 of the contested decision does not satisfy the requirement arising from the principle of legal certainty noted in paragraph 230 above, according to which a dominant undertaking must be in a position to assess the conformity of its conduct with Article 102 TFEU.

262    For that same reason, the finding of the negative margins, by means of the application of the multi-period approach, cannot undermine that assessment, since, in the present case, that approach resulted in such a finding only by means of a weighting of the positive margins for 2005 with the negative margins found respectively for the years 2006 to 2010 (recital 1013 of the contested decision) and 2006 to 2008 (recital 1014 of the contested decision).

263    Moreover, in recital 1026 of the contested decision, on the basis of the documents established by applicant’s regulatory department in April 2005 and relating to a strategy of submission of the reference offer concerning unbundled access to the local loop and ULL prices, the Commission considered that the latter knew, from 1 August 2005, that the prices for wholesale access at local loop level were squeezing the margins of alternative operators.

264    Nevertheless, it should be noted that, in the light of positive margins between 12 August and 31 December 2005, the Commission was subject to a specific obligation with regard to the proof of exclusionary effects of the practice of a margin squeeze alleged against the applicant during that period (see the case-law referred to in paragraph 259 above).

265    Therefore, the Commission’s allegation and the documents invoked in support thereof are not sufficient to demonstrate the exclusionary effect of the practice of a margin squeeze alleged against the applicant and, for example, a reduction of profitability, likely to make it at least more difficult for the operators concerned to exercise their activities on the market at issue.

266    Moreover, sections 9 and 10 of the contested decision, which deal with the anticompetitive effects of the applicant’s conduct, do not contain any examination of the effects of the practice of a margin squeeze alleged during the period between 12 August and 31 December 2005.

267    Therefore, in the light of settled case-law according to which any doubt in the mind of the Court must operate to the advantage of the undertaking to which the decision finding an infringement was addressed (judgments of 8 July 2004, JFE Engineering and Others v Commission, T‑67/00, T‑68/00, T‑71/00 and T‑78/00, EU:T:2004:221, paragraph 177, and of 12 July 2011, Hitachi and Others v Commission, T‑112/07, EU:T:2011:342, paragraph 58), it must be concluded that the Commission has not provided proof that the practice leading to a margin squeeze by the applicant had begun before 1 January 2006. Since the contested decision is, consequently, vitiated by an error of assessment on that point, it is not necessary to examine whether that approach also infringed Article 23 of Regulation No 1/2003, as the applicant claims.

268    In the light of the above, the second part of the third plea in law invoked by the applicant must be partially upheld and Article 1(2)(d) of the contested decision must be annulled in so far as it declares that, over the course of the period between 12 August and 31 December 2005, the applicant imposed unfair tariffs which do not allow an equally efficient competitor relying on wholesale access to its unbundled local loops to replicate the retail broadband services offered by the applicant without incurring a loss.

4.      The fourth plea in law, alleging manifest errors of assessment and of law, when the Commission concluded that the applicant and Deutsche Telekom were part of a single undertaking and that they were both liable for the infringement at issue

269    By its fourth plea in law, the applicant alleges that the Commission committed manifest errors of assessment and of law by finding that it and Deutsche Telekom were part of a single undertaking and were both liable for the alleged infringement committed by the applicant.

270    That plea in law is divided into four parts. The first alleges a failure to demonstrate that Deutsche Telekom exercised decisive influence over the applicant’s commercial policy. The second alleges errors of law and a manifest error of assessment as regards the lack of proof of the exercise of decisive influence as well as an infringement of the obligation to state reasons. The third alleges an infringement of the principle of presumption of innocence and the principles governing the burden of proof. The fourth alleges errors of law and a manifest error of assessment as regards the lack of proof of the exercise of decisive influence as well as an infringement of the obligation to state reasons.

(a)    Admissibility of the fourth plea in law

271    The Commission argues that this plea is inadmissible because the resolution of the question whether Deutsche Telekom and the applicant constitute one and the same undertaking will not alter the fine imposed on the applicant and therefore cannot have any positive outcome for it. In the context of calculating fines, the deterrent multiplier and the aggravating circumstance of recidivism were applied only to Deutsche Telekom, not to the applicant. According to settled case-law, the applicant’s interest in the annulment of the contested measure presupposes that such annulment must be capable, by its result, of procuring an advantage for the party bringing it. Therefore, by the cases giving rise to judgments of 17 May 2011, Arkema France v Commission (T‑343/08, EU:T:2011:218, paragraphs 39 and 49), and of 16 November 2011, Fardem Packaging v Commission (T‑51/06, not published, EU:T:2011:666, paragraphs 31 and 32), the Court rejected as inadmissible the plea raised by a subsidiary contesting the attribution of liability to its own parent company, on the ground that that plea would have no impact on the applicant’s fine. Conversely, the Court also held that a parent company which had been held jointly and severally liable could not contest ‘directly’ the fine imposed on its subsidiary.

272    The applicant claims that the plea is admissible, since, if the Court had to impose on it a new fine, the 10% total turnover ceiling in accordance with Article 23(2) of Regulation No 1/2003, would be calculated on the basis of its own turnover and not that of Deutsche Telekom. It would also be in the applicant’s interest if the Court, as the Commission has already done, were to hand down a fine of less than 10% of the applicant’s turnover, without any increase in respect of deterrence or recidivism.

273    Moreover, in the context of claims for compensation, potential plaintiffs could sue the applicant in Germany, where Deutsche Telekom is established, by relying on the conclusion that the applicant is part of the Deutsche Telekom group. However, in such a case, the applicant would have to defend itself in a foreign language before a foreign court and most likely under a foreign law. In that regard, it is settled case-law that the impact of ‘follow-on’ damages claims brought before national courts is an important aspect of the effectiveness of EU competition law, as is the need for proceedings to be conducted to take account of the defendant’s own language. Therefore, according to the applicant, when considering the question of the admissibility of the fourth plea in law, it is necessary to take account of the risk of prejudice to the applicant in ‘follow-on proceedings’.

274    In the first place, the Commission responds that the fine which it imposed on the applicant is significantly less than 10% of its turnover, which was EUR 828 million in 2013 (recital 1540 of the contested decision). In that regard, the Court would need to more than double the amount of the fine imposed on the applicant before reaching the threshold set in Article 23 of Regulation No 1/2003. Not only would such an increase be unprecedented, but no request for an increase has been made.

275    In the second place, with respect to the possibility of damages actions being brought against the applicant in countries other than Slovakia if the applicant were treated as forming a single undertaking with Deutsche Telekom, the Commission states that such a consideration, even if it were correct, would be irrelevant for the purpose of determining whether the applicant’s fourth plea is admissible. It is apparent from the case-law cited in paragraph 271 above that, in the case of the admissibility of an action brought by a subsidiary against the portion of the fine imposed on its parent company, it is necessary to determine whether any positive consequence would ensue from annulment of the Commission decision as regards the amount of the fine imposed by the contested decision. The potential impact of the contested decision on potential future actions brought by private parties is irrelevant for the purpose of determining the amount of the applicant’s fine.

276    In that regard, it should be noted that the Courts of the European Union are entitled to assess, according to the circumstances of each case, whether the proper administration of justice justifies the dismissal of an action on the substance without a prior ruling on its admissibility (see, by analogy, judgments of 26 February 2002, Council v Boehringer, C‑23/00 P, EU:C:2002:118, paragraphs 51 and 52, and of 25 April 2013, Inuit Tapiriit Kanatami and Others v Commission, T‑526/10, EU:T:2013:215, paragraph 20).

277    In the circumstances of the present case and in the interests of procedural economy, it is necessary to examine first the fourth plea in law, without first ruling on its admissibility, since that plea is, in any event and for the reasons set out below, unfounded.

(b)    Substance

(1)    First part alleging failure to demonstrate that Deutsche Telekom actually exercised decisive influence over the applicant’s commercial policy or, at the very least, an inadequate statement of reasons

278    By the first part, the applicant claims that the Commission did not prove the actual exercise of decisive influence and inferred the parent company’s liability from Deutsche Telekom’s alleged ability to exercise such influence. The applicant submits that the Commission committed manifest errors of law and of assessment of the facts and infringed, in particular, the principle of the presumption of innocence.

279    In support of that first part, the applicant raises four complaints. Firstly, the Commission does not distinguish between the ability to exercise decisive influence and the actual exercise of such influence, and relies on the mere possibility of exercising decisive influence. Secondly, the applicant criticises the fact that the Commission established decisive influence by staff overlaps, finding that the management of Deutsche Telekom could ‘possibly … influence [its] conduct in the market’ (recital 1264 of the contested decision). Thirdly, the applicant accuses the Commission of having inferred the existence of an economic unit from the fact that the staff seconded by Deutsche Telekom to the applicant maintained direct contacts with the parent company and regularly reported to it. Fourthly, decisive influence is not established by the applicant’s system of upstream reporting in the context of the meetings of the Deutsche Telekom group concerning central and eastern Europe.

(i)    Outline of the principles

280    It should be pointed out that, according to settled case-law, liability for the conduct of a subsidiary can be imputed to its parent company in particular where, although it has separate legal personality, that subsidiary does not decide independently on its own conduct on the market, but carries out, in all material respects, the instructions given to it by the parent company, having regard in particular to the economic, organisational and legal links between those two legal entities (see judgments of 10 September 2009, Akzo Nobel and Others v Commission, C‑97/08 P, EU:C:2009:536, paragraphs 58 and 72 and the case-law cited, and of 18 January 2017, Toshiba v Commission, C‑623/15 P, not published, EU:C:2017:21, paragraph 45 and the case-law cited).

281    In such a situation, because the parent company and its subsidiary form a single economic unit and therefore form a single undertaking for the purposes of Article 101 TFEU, the Commission may address a decision imposing fines to the parent company, without having to establish the personal involvement of the latter in the infringement (judgments of 10 September 2009, Akzo Nobel and Others v Commission, C‑97/08 P, EU:C:2009:536, paragraph 59, and of 9 September 2015, Toshiba v Commission, T‑104/13, EU:T:2015:610, paragraph 94).

282    In examining whether the parent company is able to exercise decisive influence over the market conduct of its subsidiary, account must be taken of all the relevant factors relating to the economic, organisational and legal links which tie the subsidiary to its parent company and, therefore, account must be taken of the economic reality (see judgments of 24 June 2015, Fresh Del Monte Produce v Commission and Commission v Fresh Del Monte Produce, C‑293/13 P and C‑294/13 P, EU:C:2015:416, paragraph 76 and the case-law cited, and of 18 January 2017, Toshiba v Commission, C‑623/15 P, not published, EU:C:2017:21, paragraph 46 and the case-law cited). Those links may vary from case to case and cannot therefore be set out in an exhaustive list (see, to that effect, judgments of 10 September 2009, Akzo Nobel and Others v Commission, C‑97/08 P, EU:C:2009:536, paragraph 74; of 1 July 2010, Knauf Gips v Commission, C‑407/08 P, EU:C:2010:389, paragraph 100; and of 16 June 2016, Evonik Degussa and AlzChem v Commission, C‑155/14 P, EU:C:2016:446, paragraph 33).

283    However, it should be noted that, in order to be able to impute the conduct of a subsidiary to the parent company, the Commission cannot merely find that the parent company is in a position to exercise decisive influence over the conduct of its subsidiary, but must also establish whether that influence was actually exercised (see judgments of 12 October 2011, Alliance One International v Commission, T‑41/05, EU:T:2011:586, paragraph 94 and the case-law cited, and of 9 September 2015, Toshiba v Commission, T‑104/13, EU:T:2015:610, paragraph 95 and the case-law cited).

284    The exercise of decisive influence by a parent company over its subsidiary’s conduct may be inferred from a body of consistent evidence, even if some of that evidence, taken in isolation, is insufficient to establish the existence of such influence (judgments of 1 July 2010, Knauf Gips v Commission, C‑407/08 P, EU:C:2010:389, paragraph 65; of 24 June 2015, Fresh Del Monte Produce v Commission and Commission v Fresh Del Monte Produce, C‑293/13 P and C‑294/13 P, EU:C:2015:416, paragraph 77; and of 18 January 2017, Toshiba v Commission, C‑623/15 P, not published, EU:C:2017:21, paragraph 47).

285    Moreover, organisational links are among the factors capable of proving the existence of an economic unit between the parent company and its subsidiary (see paragraphs 280 and 282 above). The fact that the parent company is represented in the management bodies of its subsidiary is thus relevant evidence that it exercises actual control over the subsidiary’s commercial policy (see judgments of 27 September 2012, Total v Commission, T‑344/06, not published, EU:T:2012:479, paragraph 73 and the case-law cited; of 13 December 2013, HSE v Commission, T‑399/09, not published, EU:T:2013:647, paragraph 38 and the case-law cited; and of 15 July 2015, Socitrel and Companhia Previdente v Commission, T‑413/10 and T‑414/10, EU:T:2015:500, paragraph 213 and the case-law cited).

286    Moreover, the actual exercise of management power by the parent company over its subsidiary may be proved, in particular, by the presence, in leading positions of the subsidiary, of individuals who occupy managerial posts within the parent company. Such an accumulation of posts necessarily places the parent company in a position to have a decisive influence over its subsidiary’s market conduct since it enables members of the parent company’s board to ensure, while carrying out their managerial functions within the subsidiary, that the subsidiary’s course of conduct on the market is consistent with the line laid down at management level by the parent company. That objective can be attained even though member(s) of the parent company who take on managerial functions within the subsidiary do not have authority as agents of the parent company. Furthermore, the involvement of the parent company in the management of the subsidiary may follow from the business relationship which it has with that subsidiary. Accordingly, where a parent company is also the supplier or customer of its subsidiary, it has a very specific interest in managing the production or distribution activities of the subsidiary, in order to take full advantage of the added value created by the vertical integration thus achieved (see judgment of 9 September 2015, Toshiba v Commission, T‑104/13, EU:T:2015:610, paragraph 100 and the case-law cited).

287    Likewise, in the case-law, the analysis of the existence of a single economic entity among a number of companies forming part of a group has involved consideration of the question whether the parent company had influenced the pricing policy of its subsidiary, production and distribution activities, sales objectives, gross margins, sales costs, cash-flow, stocks and marketing (see judgments of 12 December 2012, 1. Garantovaná v Commission, T‑392/09, not published, EU:T:2012:674, paragraph 31 and the case-law cited, and of 9 September 2015, LG Electronics v Commission, T‑91/13, not published, EU:T:2015:609, paragraph 38).

288    Finally, it should be noted that the scope of judicial review provided for in Article 263 TFEU extends to all the elements of Commission decisions relating to proceedings applying Articles 101 and 102 TFEU which are subject to in-depth review by the Court, in law and in fact, in the light of the pleas raised by the applicants and taking into account all the elements submitted by the latter, whether those elements pre-date or post-date the contested decision, whether they were submitted previously in the context of the administrative procedure or, for the first time, in the context of the proceedings before the Court, in so far as those elements are relevant to the review of the legality of that decision (judgment of 21 January 2016, Galp Energía España and Others v Commission, C‑603/13 P, EU:C:2016:38, paragraph 72).

289    It is in the light of those principles that it is necessary to assess the merits of the four complaints put forward by the applicant in support of the first part of the fourth plea in law.

(ii) The applicant’s assertion that the Commission did not distinguish between the ability to exercise decisive influence and the actual exercise of such influence

290    By its first complaint, the applicant claims that the Commission does not distinguish between the ability to exercise decisive influence and the actual exercise of such influence, by relying on the mere possibility of exercising decisive influence.

291    The applicant also argues that the Commission failed to fulfil its obligation to provide sufficient reasons for the contested decision.

292    As regards the argument that the Commission did not prove that Deutsche Telekom actually exercised decisive influence over the applicant, the applicant claims in particular that the Commission maintained, first, that Deutsche Telekom ‘possibly’ influenced conduct on the market and that it ‘could’ always intervene through its Board of Directors (recital 1264 of the contested decision) and, secondly, that Deutsche Telekom’s ‘ability’ to coordinate and influence it was reinforced (recital 1336 of the contested decision).

293    In that regard, it should be noted that an allegation relating to the possibility of the exercise by Deutsche Telekom of decisive influence over the applicant, made in an isolated passage of the contested decision, cannot call into question the fact that the Commission carried out a detailed analysis in order to prove the actual exercise of such influence.

294    It must be noted that the Commission proceeded by way of several stages in order to reach the conclusion that the applicant and Deutsche Telekom were part of the same economic unit during the period under consideration.

295    Therefore, as a first phase, in recitals 1201 to 1255 of the contested decision, the Commission enumerated a series of objective circumstances establishing according to it that Deutsche Telekom had, during that period, the ability to exercise decisive influence over the applicant’s conduct on the market. The Commission essentially inferred that ability, firstly, from the fact that the majority ownership by Deutsche Telekom of the applicant’s capital allowed it to impose its views whenever the latter’s general assembly acted by simple majority (recitals 1224 to 1228 of the contested decision), secondly, from the fact that the shareholders’ agreement, as amended in 2003 by the agreement on further cooperation of the applicant’s shareholders, provided for the nomination by Deutsche Telekom of four of the seven members of the applicant’s Board of Directors, including its president, and for the adoption by that board of commercial decisions by simple majority (recitals 1229 and 1230), thirdly, from the influence indirectly exercised by Deutsche Telekom over the applicant’s Executive Management Board by means of members nominated by it to that subsidiary’s Board of Directors (recitals 1233 to 1241 of the contested decision) and, fourthly, from declarations made by Deutsche Telekom that, in essence, it acquired control over EuroTel following the purchase by the applicant, on 31 December 2004, of 49% of that operator’s share capital which was not already owned by the applicant at that time (recitals 1247 to 1255 of the contested decision).

296    In a second phase, in recitals 1256 to 1387 of the contested decision, the Commission examined several circumstances which, according to it, allow it to be established that Deutsche Telekom exercised decisive influence over the applicant’s conduct on the market.

297    At the outset, it should be noted that, in recitals 1295 and 1296 of the contested decision, the Commission considered, in essence, that the possibility for Deutsche Telekom to intervene with the applicant, if necessary by the replacement of members of that subsidiary’s management or by evoking that possibility, sufficed to demonstrate the exercise by Deutsche Telekom of decisive influence over the applicant, by means of its representation on the Board of Directors.

298    Admittedly, that finding, considered in isolation, is not compatible with the principles referred to in paragraph 283 above. However, that error does not suffice to render unlawful the examination following which the Commission concluded that Deutsche Telekom had to be held responsible for the single and continuous infringement which is the subject of the contested decision, since it formed a single undertaking with the applicant. That conclusion is not based on the sole finding relating to the possibility for Deutsche Telekom to intervene with the applicant referred to in paragraph 297 above, but, in accordance with the principles noted in paragraph 284 above, on a body of evidence resulting from an analysis of the economic, organisational and legal links which tied those two entities during the period under consideration.

299    In that regard, it should be noted that the Commission infers the actual exercise of decisive influence, firstly, from overlaps of staff between those two companies (recitals 1263 to 1287 of the contested decision), secondly, from concrete illustrations of cases in which decisions of the applicant’s Board of Directors were compatible with instructions provided by Deutsche Telekom to the members of that board appointed by Deutsche Telekom (recitals 1288 to 1294 of the contested decision), thirdly, from the regular transmission to Deutsche Telekom of information concerning the applicant’s intended commercial policy in the context of meetings of the Deutsche Telekom group, first of all in the cooperation structure of Deutsche Telekom subsidiaries in the central and eastern European countries (CEEC) and, subsequently, in the cooperation structure for south-eastern Europe (recitals 1298 to 1337 of the contested decision), fourthly, from the examination by Deutsche Telekom, in the context of regular international management meetings, of proposals concerning the applicant’s commercial policy before those proposals are examined by the applicant’s Board of Directors or Executive Management Board (recitals 1338 to 1359 of the contested decision) and, fifthly, from the decisive influence exercised by Deutsche Telekom over the applicant during the latter’s choice of the vendor of an IPTV platform (recitals 1360 to 1375 of the contested decision). The Commission further complemented that analysis, in recitals 1459 to 1468 of the contested decision, with several elements which according to it constituted additional evidence of the decisive influence exercised by Deutsche Telekom over the applicant’s conduct on the market.

300    In a third phase, the Commission set out, in recitals 1388 to 1458 of the contested decision, the reasons why it considered in essence that various cases presented by Deutsche Telekom as proof of the absence of such decisive influence do not in reality demonstrate the applicant’s independence on the market.

301    It follows from the above that, despite the error pointed out in paragraphs 297 and 298 above, in the present case the Commission did not presume the exercise by Deutsche Telekom of decisive influence over the applicant’s conduct on the market. On the contrary, although the Commission relied in the first part of its analysis on Deutsche Telekom’s ability to exercise such influence over the applicant (see paragraph 295 above), it also verified, following a detailed analysis, whether that influence had actually been exercised. Therefore, in accordance with the principles referred to in paragraphs 282 to 288 above, the Commission concluded that the applicant and Deutsche Telekom formed a single undertaking following the examination of a body of relevant evidence relating to the economic, organisational and legal links tying those two companies.

302    The passages in recitals 1264 and 1336 of the contested decision to which the applicant makes reference do not call that assessment into question. In the first place, as regards recital 1264 of the contested decision, to which the applicant makes reference, it should be noted that it is included in the part of that decision in which the Commission examined several circumstances allowing in its opinion it to be established that Deutsche Telekom exercised a decisive influence over the applicant’s conduct. In particular, it inferred the existence of that actual influence from overlaps of staff between those two companies (recitals 1263 to 1287 of the contested decision). In the second place, as regards the passage cited by the applicant according to which the ‘ability’ of Deutsche Telekom to coordinate and influence it was reinforced (recital 1336 of the contested decision), that passage is included in the analysis carried out in recitals 1298 to 1337 of the contested decision, in which the Commission considered, in essence, that the obligation imposed on the applicant to report to Deutsche Telekom as well as the regular reporting of the applicant’s information to Deutsche Telekom by means of meetings of the Deutsche Telekom group for central and eastern Europe also constituted indications of the exercise by Deutsche Telekom of decisive influence over the applicant’s commercial policy. As a result, those passages are included in the parts in which the Commission examined all the indications with a view to establishing the exercise by Deutsche Telekom of decisive influence over the applicant, so that those passages read in isolation do not allow it to be established that there was a lack of evidence of such influence.

303    Finally, in so far as that complaint alleges a failure to state reasons, it must be noted that the reasons why the Commission considered that there was a body of evidence allowing the exercise of decisive influence by Deutsche Telekom over the applicant to be established are set out in a clear and sufficiently detailed manner in recitals 1201 to 1483 of the contested decision. It follows that the applicant’s allegation that the contested decision is vitiated by a lack of reasoning in that regard must be rejected.

304    The first complaint of the first part must therefore be rejected.

(iii) The management staff overlaps between Deutsche Telekom and the applicant

305    By its second complaint, the applicant criticises the fact that the Commission proved decisive influence by staff overlaps, finding that the management of Deutsche Telekom could ‘possibly ... influence [its] conduct in the market’ (recital 1264 of the contested decision).

306    In that regard, first, the Commission’s description and assessment of Mr R. R.’s position and function is incorrect. According to the applicant, in his position at Deutsche Telekom, Mr R. R. was responsible for consolidating the applicant’s financial results into those of its parent company. The applicant claims that he was thus in charge of accounting matters and had no influence over the conduct of its subsidiary. Second, the Commission’s assessment of the senior management in general is erroneous. Accordingly, the contested decision does not distinguish between the executive and non-executive members of the Board of Directors, since the overlaps were limited to the non-executive board members appointed by Deutsche Telekom.

307    In so far as the applicant’s allegation seeks to contest the way in which the Commission described and evaluated the activities referred to in recitals 1263 and 1264 of the contested decision, it should be noted that the applicant did not substantiate that allegation with contrary evidence.

308    Moreover, it has been held that the position of member of the board of directors of a company entails, by its very nature, legal responsibility for the activities of the company as a whole, including its conduct on the market (judgment of 30 April 2014, FLSmidth v Commission, C‑238/12 P, EU:C:2014:284, paragraph 30). As a result, it cannot be considered, as the applicant claims, that Mr R. R.’s role within the applicant is limited to assuming legal obligations relating to the consolidation of the accounts of that subsidiary at the level of the Deutsche Telekom group. It results from recital 1265 of the contested decision, without being called into question by the applicant, that, during the period under consideration, Mr R. R. also audited the applicant’s accounts with a view to their consolidation at the level of the Deutsche Telekom group.

309    Although such factors, relating to control and finance, admittedly do not suffice to establish the existence of economic unity between the applicant and Deutsche Telekom, they do nevertheless relate to the decentralised management typical of large companies and, therefore, indeed constitute indications that the applicant did not decide independently upon its own conduct on the market (see, to that effect, judgment of 11 July 2014, RWE and RWE Dea v Commission, T‑543/08, EU:T:2014:627, paragraph 51).

310    The applicant also puts forward the argument that overlaps of staff cannot per se constitute the actual exercise of decisive influence. Although such overlaps may give a parent company the ability to exercise decisive influence, they cannot be relied on as proof of the exercise of such influence. Moreover, the personnel overlaps were restricted to non-executive directors of the Board of Directors appointed by Deutsche Telekom, although those non-executive directors did not participate in the applicant’s day-to-day management.

311    In that regard, it is necessary to note the finding made in paragraph 308 above that the position of member of the Board of Directors of a company entails, by its very nature, legal responsibility for the activities of the company as a whole, including its conduct on the market. Therefore, the overlaps of staff between the applicant and Deutsche Telekom, regarding the functions of members of the Board of Directors, could be considered to be one factor among others supporting the existence of a single economic unit between those two entities.

312    Furthermore, it is admittedly true, as the Commission noted in essence in recitals 10 and 1219 of the contested decision, that the applicant’s day-to-day management was the responsibility of its Executive Management Board, since that latter had delegated to it certain of the powers of the Board of Directors.

313    However, as the Commission correctly pointed out in recital 1273 of the contested decision, it has been held that a decisive influence by a parent company over a subsidiary was not necessarily connected with the day-to-day management of that subsidiary (judgment of 26 September 2013, The Dow Chemical Company v Commission, C‑179/12 P, not published, EU:C:2013:605, paragraph 42; see also, to that effect, judgments of 29 June 2012, E.ON Ruhrgas and E.ON v Commission, T‑360/09, EU:T:2012:332, paragraph 280, and of 13 December 2012, Versalis and Eni v Commission, T‑103/08, not published, EU:T:2012:686, paragraph 68). The exercise by a parent company of decisive influence over the commercial policy of a subsidiary does not require proof of an interference in that subsidiary’s day-to-day management, nor of influence over its commercial policy in the strict sense, such as its distribution or pricing strategy, but rather influence over the general strategy which defines the orientation of the undertaking (see, to that effect, judgment of 9 September 2015, Toshiba v Commission, T‑104/13, EU:T:2015:610, paragraph 121).

314    In the present case, it should be noted, as was pointed out during the hearing, that Deutsche Telekom had a majority of members on the Executive Management Board. In addition, it should be recalled that the delegation of the applicant’s day-to-day management to the Executive Management Board did not result in its Board of Directors losing its essential tasks to define and implement that company’s commercial policy. The applicant thus does not contest the finding, made in recital 1269 of the contested decision, that the approval of its corporate and operating plan and of its budget remained the responsibility of the Board of Directors. The Commission did not commit an error when it found that indications of such supervision could be inferred, in particular, from the obligation imposed on the Executive Management Board, in essence, to report regularly to the Board of Directors about its activities and the state of that company and its subsidiaries, as well as of the Board of Director’s power to approve the business plan prepared by the Executive Management Board (recital 1271 of the contested decision).

315    It follows that, in the light of the principles referred to in paragraphs 285 and 286 above, the Commission was correct, in recitals 1263 to 1274 of the contested decision, to conclude that the presence on the applicant’s Board of Directors of Deutsche Telekom managers constituted an indication that the latter had exercised decisive influence over that subsidiary regarding its position on the market.

316    The second complaint of the first part must therefore be rejected.

(iv) The provision by Deutsche Telekom of staff to the applicant

317    By its third complaint, the applicant accuses the Commission of having inferred the existence of an economic unit from the fact that the staff seconded by Deutsche Telekom to it maintained direct contact with the parent company and regularly reported to the latter.

318    In that regard, it must be noted that, first, the applicant does not provide any evidence in support of its allegation and that, secondly, it merely criticises the Commission without even specifying the relevant part of the contested decision.

319    Moreover, the applicant considers that the Commission failed to prove that Deutsche Telekom actually exercised decisive influence over it. In that regard, proof that seconded staff ‘had beforehand or afterwards important functions in other subsidiaries of [Deutsche Telekom] or international functions within the [Deutsche Telekom] group’ does not demonstrate that those persons ‘are more attached to [that] group than to [the applicant]’ (recital 1280 of the contested decision).

320    However, it is apparent from recital 1275 of the contested decision, which is not contested by the applicant, that in 2003 the applicant and Deutsche Telekom concluded an agreement under which Deutsche Telekom undertook to provide employees to the applicant for execution of professional and management services, that subsidiary for its part undertaking to pay a fee to Deutsche Telekom. Moreover, the applicant does not contest the finding made in recital 1276 of the contested decision, according to which, in essence, four of the senior managers made available by Deutsche Telekom during the period under consideration occupied positions in it involving a high level of responsibility. In that context, in recital 1280 of the contested decision, the Commission considered that the senior managers of Deutsche Telekom seconded to the applicant remained employees of Deutsche Telekom during their posting, and thus depended on that company for the continuation of their carriers within the Deutsche Telekom group.

321    It should be pointed out that such an undertaking to provide staff of the parent company to a subsidiary comes within the organisational links which are relevant for the purposes of determining whether they constitute a single undertaking, within the meaning of the case-law cited in paragraphs 280 and 282 above, since that provision of staff is capable of providing an indication of the parent company’s active involvement in the management of its subsidiary.

322    Therefore, the Commission was entitled to conclude that such a provision of staff to the applicant could constitute an indication of decisive influence exercised over that subsidiary during the period under consideration.

323    The third complaint of the first part must therefore be rejected.

(v)    The reports presented at the regular meetings of the Deutsche Telekom group concerning central and eastern Europe

324    By its fourth complaint, the applicant claims that the parent company’s decisive influence is not established by its system of upstream reporting in the context of the meetings of the Deutsche Telekom group concerning central and eastern Europe.

325    By that complaint, the applicant contests, in essence, the analysis in recitals 1298 to 1337 of the contested decision, in which the Commission considered, in essence, that the obligation imposed on the applicant to report to Deutsche Telekom as well as the regular provision of information by the applicant to Deutsche Telekom by means of meetings of the Deutsche Telekom group concerning central and eastern Europe were also indications of the exercise by Deutsche Telekom of decisive influence over the applicant’s commercial policy.

326    In the first place, the applicant claims that all the evidence submitted by the Commission in that context nevertheless concerns solely the exchange of information, and not the exercise of decisive influence.

327    In that regard, it should at the outset be pointed out that the Commission, in the contested decision, did not infer from the regular provision of information to Deutsche Telekom, concerning the applicant’s commercial policy, that those entities formed a single economic unit. The Commission merely noted that fact as one indication amongst others of the exercise by Deutsche Telekom of decisive influence over that subsidiary.

328    It must be noted that such an approach is, in principle, compatible with the case-law noted in paragraphs 280 and 282 above. The regular reporting, by a subsidiary to its parent company, of detailed information relating to its commercial policy is liable to establish awareness on the part of the parent company of its subsidiary’s conduct on the market and, consequently, to put the parent company in a position to intervene in a more informed and therefore efficient way in the commercial policy of that subsidiary (see, to that effect, judgments of 13 December 2013, HSE v Commission, T‑399/09, not published, EU:T:2013:647, paragraph 93; see also, by analogy, judgment of 6 March 2012, FLSmidth v Commission, T‑65/06, not published, EU:T:2012:103, paragraph 31). Therefore, such a fact comes indeed within the scope of the organisational links between Deutsche Telekom and the applicant during the period under consideration, and is thus capable of contributing, along with other indicators, to establishing that those companies formed a single economic unit during that period.

329    In the second place, as regards the applicant’s argument that the new organisational structure provided for by the strategic cooperation framework agreement which it concluded with Deutsche Telekom, to which reference is made in recital 1304 of the contested decision, was never implemented and it was only intended to be used as a basis for the exchange of know-how and information in order to support the applicant, first of all, it is necessary to note that, as the applicant confirmed during the hearing, that agreement came into force at the time of its signature, that is to say in March 2006.

330    Next, as is noted in recital 1307 of the contested decision, it resulted from a presentation relating to the governance structure of Deutsche Telekom’s subsidiaries in the CEEC, prepared for a meeting of the operational directors of those subsidiaries which took place on 7 March 2006, that the strategic cooperation framework agreements concluded with those subsidiaries formed the basis for operational cooperation within the Deutsche Telekom group.

331    Finally, it is apparent from the preamble to the strategic cooperation framework agreement annexed to the defence and from recitals 1305 and 1306 of the contested decision that that agreement sought to allow the applicant to benefit from Deutsche Telekom’s expertise in fixed-line telecommunications, to provide the applicant with Deutsche Telekom’s support in the management of fixed lines and online telecommunications as well as to allow the applicant to exploit synergies and thus create benefits for its shareholders. More particularly, first, Article 3 of that framework agreement stipulated that Deutsche Telekom ‘w[ould] advise on suitable … managers at director level (selection, remuneration, remuneration policy, development and performance management) [and that] the targets for the company and [for] the management board members [had] to be reconciled with [Deutsche Telekom] and approved by [the applicant’s] Board of Directors’. Secondly, that article provided that Deutsche Telekom ‘w[ould] advise on suitable members for the management of fixed line based business (selection, remuneration, remuneration policy, development and performance appraisal)’. It follows that that framework agreement provided for a closer connection than a mere exchange of know-how.

332    As is apparent from the case-law referred to in paragraph 328 above, the regular reporting by a subsidiary, to its parent company, of detailed information relating to its commercial policy is likely to establish the parent company’s awareness of its subsidiary’s conduct on the market and, consequently, to place the parent company in a position to intervene in a more informed and thus effective way in the commercial policy of that subsidiary.

333    Consequently, the Commission was entitled to consider that the agreement on strategic cooperation was a relevant element to be taken into account in order to establish the existence of decisive influence.

334    In the third place, the applicant considers that ‘[a]lso with respect to the new organisational structure for [Deutsche Telekom]’s SEE affiliates, the contested decision’s observations only concern the exchange of information’. Although the applicant does not identify the paragraphs of the contested decision to which it is referring in its arguments, it appears that its argument concerns recitals 1318 to 1337 of the contested decision. It should be noted that the applicant does not adduce any evidence in support of its arguments, so that that argument must be rejected.

335    The fourth complaint, alleging a lack of evidence regarding the reports presented at the regular meetings of the Deutsche Telekom group concerning central and eastern Europe, must therefore be rejected.

336    It results from all the foregoing that the first part of the fourth plea in law, alleging a failure to demonstrate the actual exercise of decisive influence by Deutsche Telekom over the applicant’s commercial policy, must be dismissed as unfounded.

(2)    Second part alleging errors of law and a manifest error of assessment as regards the lack of proof of the exercise of decisive influence as well as an infringement of the obligation to state reasons

337    By the second part, the applicant claims that the Commission conducted a one-sided and biased assessment of the Board of Directors’ briefing documents and the minutes of the international management meetings. The applicant contests, in essence, the evidence put forward by the Commission to prove the exercise of decisive influence over it.

338    That part is divided into four complaints.

339    First, the Commission failed to prove that Deutsche Telekom had decisive influence over the decisions of the applicant’s Board of Directors. Secondly, the Commission did not demonstrate the exercise of decisive influence by Deutsche Telekom through the international management meetings. Thirdly, the Commission committed an error by finding that Deutsche Telekom exercised decisive influence ‘by issuing precise instructions to [the applicant] about the choice made by [the applicant] of a vendor for its future IPTV [Internet Protocol Television] platform’ (recital 1365 of the contested decision). Fourthly, the mere fact that Deutsche Telekom was the notifying party in merger case M.3561 (Deutsche Telekom v EuroTel) does not prove that it exercised decisive influence over the applicant.

(i)    The examination of decision-making processes within the applicant’s Board of Directors

340    By its first complaint, the applicant claims that the Commission wrongly considered that Deutsche Telekom briefed non-executive members of the Board of Directors, which went beyond mere preparation of its representatives for the meetings of that board. In doing so, the Commission failed to explain how those briefings differed from ‘normal’ briefings, so that it infringed its obligation to state reasons.

341    In that regard, in recitals 1290 to 1292 of the contested decision, the Commission examined the briefings drafted for the board meetings between 15 June 2005 and 23 September 2010 in the light of the minutes from those meetings. More particularly, the Commission considered, in recital 1291 of that decision, that, although it is usual corporate practice for a shareholder to prepare its representatives for board meetings, that practice sometimes went beyond such preparation.

342    Moreover, it is necessary to reject as ineffective the applicant’s argument that the preparation of non-executive members of its Board of Directors ahead of the latter’s meetings, by means of preparatory notes, is compatible with common practice and thus does not indicate the exercise of decisive influence over that subsidiary. The mere fact that it can be common practice for a parent company to send such preparatory notes to its representatives within a subsidiary, which, furthermore, the Commission concluded in recital 1291 of the contested decision, does not render those notes irrelevant for the purposes of establishing whether those companies form the same undertaking, since the examination of the contents of those notes is part of the assessment of the economic, organisational and legal links between those companies.

343    In so far as that argument alleges a failure to state reasons, it suffices to note that, in recital 1292 of the contested decision, the Commission referred to three meetings of the Board of Directors during the infringement period where Deutsche Telekom’s preparatory notes were followed by the applicant’s Board of Directors. It was in particular noted that the minutes of those meetings followed the recommendations contained in those preparatory notes. Therefore, it must be concluded that the Commission explained why it considered that those notes constituted an indication of decisive influence by Deutsche Telekom over the decisions of the applicant’s Board of Directors. As a result, the applicant is wrong to accuse the Commission of having failed to state the reasons on which the contested decision is based on that point.

344    The applicant also cannot be followed when it complains that the Commission considered that Deutsche Telekom made ‘comments’ about the applicant’s commercial policy by means of its representatives within that subsidiary’s Board of Directors. Assuming that the preparatory notes examined by the Commission in recital 1292 of the contested decision were not binding on the executive members of the applicant’s Board of Directors who were appointed by Deutsche Telekom, that in no way rules out that such preparatory notes could, in the light of a specific examination of their impact on the decisions of that board, constitute an indication of decisive influence exercised by Deutsche Telekom over the applicant’s conduct on the market.

345    Finally, the applicant relies on Slovak company law pursuant to which members of the Board of Directors cannot give preference to the interests of only some of the shareholders over the interests of the company. That law also provides for the personal liability of the members of the Board of Directors, in order to ensure their independence.

346    In that regard, the applicant appears to complain that the Commission committed an error, in recitals 1281 and 1282 of the contested decision, by considering that the Slovak company law provisions providing for an obligation of loyalty on the part of the administrators towards the shareholders, did not prevent a parent company holding a majority interest in the share capital of a subsidiary established in Slovakia from exercising decisive influence over the latter’s conduct on the market.

347    It must be noted that nothing in the applicant’s arguments is capable of calling into question that finding made by the Commission in recital 1282 of the contested decision. In any event, the Commission was correct to conclude that such an obligation of loyalty does not aim to prevent a parent company from exercising decisive influence over its subsidiary. The pursuit of the interests of a subsidiary does not exclude the simultaneous pursuit of the interests of its parent company.

348    It follows that the first complaint of the second part must be rejected.

(ii) The examination of the international management meetings

349    By its second complaint, the applicant considers, in essence, that the Commission failed to show that decisive influence was exercised by means of international management meetings.

350    It should be noted, at the outset, that the applicant does not dispute that those international management meetings took place in the form and with the frequency described in the contested decision. In that regard, it follows from recitals 1310 and 1342 of the contested decision, which are not contested by the applicant, that international management meetings indeed took place between Deutsche Telekom and the CEEC subsidiaries, including the applicant, during the period between, at least, 4 May 2006 and 2 April 2009. In addition, the minutes of the meeting of the Chief Operating Officers of 7 March 2006, which are not contested by the applicant and which are referred to in recital 1303 of the contested decision, provide a serious indication of the actual establishment of a governance structure within the Deutsche Telekom group in relation to the CEEC subsidiaries.

351    Therefore, in the light of the regular organisation of those international management meetings, the Commission did not commit an error when it concluded that the international management meetings had indeed provided a context for the implementation of the principles of cooperation set out in the strategic cooperation framework agreement.

352    Moreover, the applicant does not dispute that the international management meetings were used to exchange financial information.

353    In that regard, as is apparent from the case-law referred to in paragraph 287 above, the analysis of the existence of a single economic entity among a number of companies forming part of a group involves, in particular, the examination of whether the parent company has influenced the pricing policy of its subsidiary, production and distribution activities, sales objectives, gross margins, sales costs, cash-flow, stocks and marketing.

354    The applicant considers that the Commission misunderstood the aim of the international management meetings, namely to establish a more structured mechanism for the exchange of information, know-how and practices. In addition, the Commission’s claim that Deutsche Telekom organised those meetings so as ‘to allow for a comprehensive review of [the applicant]’s business and projects in the absence of representatives from the minority shareholder in [it], the Slovak Republic’ (recital 1341 of the contested decision) has not been proved.

355    In the present case, it must be noted that the reasoning in connection with the examination of the minutes of the international management meetings (recitals 1354 to 1359 of the contested decision) sets out the reasons why the Commission concluded, in recital 1352 of that decision, that those meetings not only had provided Deutsche Telekom with a regular source of detailed information about the applicant’s activities, but had also allowed Deutsche Telekom to intervene in the development of that subsidiary’s position on the market. Moreover, the Commission specifically replied, in recitals 1349 to 1351 of the contested decision, to the argument presented by the applicant in its response to the statement of objections, according to which the international management meetings had merely sought to exchange information and could therefore not contribute to showing that those entities constituted a single economic unit. Furthermore, the applicant does not put forward any arguments allowing the merits of the Commission’s findings in that regard to be called into question.

356    In addition, as regards the applicant’s argument that the Commission misconceived the nature of ‘actions’ in so far as the applicant never felt bound, it should be noted that the applicant does not put forward any convincing arguments calling into question the Commission’s finding that, in essence, the ‘action items’ referred to in the minutes of the meeting of 4 May 2006, described in recital 1344 of the contested decision, indicate Deutsche Telekom’s real and in-depth involvement in the applicant’s commercial policy, in particular by means of a requirement that the latter submit detailed information about that policy and its development.

357    Finally, as regards the applicant’s arguments alleging an absence of measures to be taken during the international management meetings and the absence of proof in that regard, it should, first of all, be noted that it has already been held that the absence of direct instructions given by a parent company to its subsidiary in no way means that those two legal entities belong to separate undertakings, since a single commercial policy within a group may also be inferred from the totality of the economic and legal links between the parent company and its subsidiary, in particular as regards human resources (see, to that effect, judgment of 9 September 2015, Toshiba v Commission, T‑104/13, EU:T:2015:610, paragraph121 and the case-law cited).

358    In the present case, it must be pointed out that the extracts from the minutes of those meetings provided by the Commission, in recital 1354 of the contested decision, indeed illustrate the close organisational links which existed between those entities and, at the very least, Deutsche Telekom’s high degree of involvement in defining the applicant’s commercial policy, beyond a simple exchange of information and good practices. Therefore, the Commission was entitled to consider that the minutes of the international management meetings set out in that recital provided indications of the exercise by Deutsche Telekom of decisive influence over the applicant’s conduct on the market.

359    The second complaint of the second part must therefore be rejected.

(iii) The examination of the choice made by the applicant of a vendor of internet television services (IPTV)

360    By its third complaint, the applicant contests the Commission’s finding, in recital 1365 of the contested decision, that Deutsche Telekom had ‘exercised a decisive influence by issuing precise instructions to [it] about the choice … of a vendor for its future IPTV platform’. In that regard, the applicant independently drew up the tender for the appointment of a supplier for its IPTV platform, it analysed all available alternatives and selected the tender of the candidate who was eventually successful because it was the most interesting. According to the applicant, Deutsche Telekom only assisted it with technical issues, by providing know-how and information on best practices, and did not issue instructions.

361    In that regard, it should be noted that, in recital 1365 of the contested decision, firstly, the Commission stated that Deutsche Telekom had influenced the choice of the vendor of internet television (IPTV) services at a very early stage of the decision-making process, in particular due to information received directly from two senior executives of the applicant who were seconded by Deutsche Telekom (Mr H. M. and Mr J. Z.). Secondly, the Commission noted, in that recital, that that choice concerned an important investment, specifically the purchase of hardware, software and system integration services for which the applicant was unable to freely choose the vendor it preferred. Thirdly, the Commission noted, in that recital, that that investment was a key element in the applicant’s broader ‘triple play’ project, which was of strategic importance for the latter. However, the applicant does not adduce any evidence in order to call into question the above findings showing the way in which Deutsche Telekom exercised its influence over that commercial decision of the applicant.

362    Therefore, the Commission was entitled to find, in recitals 1365 to 1375 of the contested decision, that the procedure which led to the applicant’s choice of vendor of IPTV services indeed constituted an additional indication of the exercise by Deutsche Telekom of decisive influence over the applicant’s position on the market.

363    The third complaint of the second part must therefore be rejected.

(iv) The examination of the EuroTel transaction

364    By its fourth complaint, the applicant considers that the mere fact that Deutsche Telekom was the notifying party in merger case M.3561– Deutsche Telekom v EuroTel does not prove that Deutsche Telekom exercised decisive influence over it. The concept of ‘decisive influence’, which entails an ex post analysis, differs from that of control under the ‘Merger Regulation’, which is based on an ex ante analysis.

365    In that regard, it should above all be pointed out that the fact that the applicant acquired the entire share capital of EuroTel in 2004, following notification of that merger operation by Deutsche Telekom, cannot in itself be considered to be decisive for the purposes of establishing whether the applicant and Deutsche Telekom formed a single undertaking during the period under consideration.

366    It is apparent from Article 4(2) of Council Regulation (EC) No 139/2004 of 20 January 2004 on the control of concentrations between undertakings (‘the EC Merger Regulation’) (OJ 2004 L 24, p. 1) and from Articles 2 and 3 of Commission Regulation (EC) No 802/2004 of 7 April 2004 implementing Regulation No 139/2004 (OJ 2004 L 133, p. 1), that notification is an administrative act consisting in the filing of a specific form by the person acquiring control of the whole or parts of one or more undertakings. In the present case, it is indeed Deutsche Telekom which, by its participation in its subsidiary, acquired the control of EuroTel in 2004.

367    Therefore, it cannot be inferred from that purely administrative act that Deutsche Telekom actually exercised decisive influence over the applicant.

368    By contrast, that finding does not render irrelevant the Commission’s assessment, correctly made in recital 1460 of the contested decision, according to which the fact that Deutsche Telekom notified the merger at issue ‘is an additional example of the exercise of decisive influence’ by that company over the applicant, although the proposed transaction concerned solely the acquisition, by the applicant, of sole control over EuroTel.

369    The fourth complaint of the second part of the fourth plea in law must therefore be rejected.

(3)    Third part alleging errors of law and manifest errors of assessment as regards the applicant’s independent conduct

370    By the third part, the applicant claims that, by rejecting the examples provided by Deutsche Telekom and by itself to show that it decided on its commercial and regulatory strategies independently and by finding that those examples did not rebut ‘the existence and exercise of the decisive influence by [Deutsche Telekom]’ (recital 1458 of the contested decision), the Commission committed errors of law and manifest errors in the assessment of the facts and, therefore, infringed the principle of the presumption of innocence and the principles governing the burden of proof.

371    In that regard, the applicant relies on the assertion in recital 1389 of the contested decision that ‘it is not shown by [Deutsche Telekom] that the allegedly independent business decisions of [the applicant] [had] referred to by [Deutsche Telekom] were against [Deutsche Telekom]’s interests’, demonstrates that the Commission assumed that it was for Deutsche Telekom and/or the applicant to prove that Deutsche Telekom had not exercised decisive influence over the latter. Where the parent company holds less than 100% of its subsidiary’s shares, there is no presumption of decisive influence, with the result that the onus is on the Commission to prove that the parent company was able to exercise decisive influence, that it actually used that ability and that the influence was significant. In addition, contrary to what the Commission seems to assume, it is not necessary to show that the interests of the parent company and those of its subsidiary were clearly at odds. Thus, the examples provided by Deutsche Telekom and the applicant are intended to demonstrate that, where those interests are not aligned, the subsidiary acts independently if the parent company does not issue instructions. Finally, the Commission was wrong to reject those examples on the ground that the latter’s decisions were motivated by local market conditions (recitals 1423 and 1431 of the contested decision). The only relevant factor is whether the applicant acted independently and a diligent analysis of the market conditions is, on any view, the basis for all commercially sound decisions.

(i)    Preliminary observations

372    First of all, it is necessary to reject the applicant’s argument that the part of the contested decision examined in the context of the third part of the present plea in law disregards the fact that no presumption of decisive influence applies in the present case, and that the Commission, consequently, infringed the principles governing the burden of proof. Relying on recital 1389 of the contested decision, the applicant claims that the Commission reversed its burden of proof.

373    It follows from recital 1388 of the contested decision that, during the administrative procedure, Deutsche Telekom presented a series of examples in order to show that it did not issue instructions to the applicant during the period under consideration, and that it did not exercise any decisive influence over the latter. First, and without prejudice to the other complaints invoked under the present part, the Commission assessed each of those examples, in recitals 1393 to 1458 of the contested decision, in a way compatible with its obligation to conduct a diligent and impartial examination of all the economic, organisational and legal links between those two legal entities. Secondly, and more generally, it should be noted that the Commission’s conclusion that the applicant and Deutsche Telekom formed a single undertaking during the period under consideration is not based on a presumption, but on an examination of all of those links (paragraphs 301 and 302 above).

374    It is necessary to examine in turn the eight examples of its independent conduct on the market alleged by the applicant, so as to establish whether, as the latter claims, the Commission should have inferred from those examples that Deutsche Telekom and the applicant did not form a single undertaking during the period under consideration.

(ii) The applicant’s position with regard to the ‘4-in-1’ project

375    By its first complaint, the applicant accuses the Commission of not having explained why its decision not to participate in the ‘4-in-l’ wholesale project is not proof of its independence. The fact that the applicant had to convince Deutsche Telekom of its reasons for that decision are irrelevant. According to the applicant, it is apparent from recitals 1393 to 1396 of the contested decision that there was a difference of interests between the applicant and Deutsche Telekom, as the latter tried unsuccessfully to convince the former to join the project.

376    In that regard, it should be noted that, according to recital 1393 of the contested decision, Deutsche Telekom aimed, by that project, to integrate the ‘international voice’ business of all its subsidiaries in southern and eastern Europe into one network and into one wholesale sales structure. However, as is stated in recital 1394 of the contested decision, the applicant decided not to participate in that project.

377    The applicant does not contest the finding in recital 1395 of the contested decision, according to which it had justified to Deutsche Telekom its intention not to participate in the ‘4-in-l’ project as a result of its specificities within the Deutsche Telekom group, in particular the fact that its international activities, based on the next generation network (‘NGN’), were thriving and that that project would result for it in revenue and profitability losses, in particular in Ukraine. It admittedly follows from that recital that, first, the applicant maintained that position although it was approached by Deutsche Telekom on two occasions and that, secondly, the Slovak State itself (Ministry of Economy and the National Property Fund of the Slovak Republic) had expressed its concern that the ‘4-in-1’ project would decrease the applicant’s revenue.

378    However, it should be pointed out that the applicant does not put forward any evidence calling into question the Commission’s finding, in recitals 1395 and 1396 of the contested decision, that that opposition and the fact that Deutsche Telekom did not insist that the applicant participate in that project did not establish the latter’s independence on the market. Therefore, the Commission could legitimately reach that conclusion. The fact that the applicant had to ‘convince’ Deutsche Telekom of the merits of its position in that project also shows, as the Commission pointed out, that the applicant’s commercial conduct was not independent.

379    The first complaint of the third part of the present plea in law must therefore be rejected.

(iii) Introduction by the applicant of the ‘naked DSL’ in 2005

380    By its second complaint, the applicant claims that it independently decided in 2005 to launch the DSL without fixed telephone line (‘the naked DSL’), although it follows from recital 1405 of the contested decision that Deutsche Telekom was sceptical about that launch, since it considered that that product presented a significant commercial risk.

381    In that regard, firstly, the applicant does not call into question the finding, made by the Commission in recitals 1401 and 1402 of the contested decision, according to which two of the senior executives of Deutsche Telekom as well as departments other than Deutsche Telekom’s regulatory affairs department had been informed several months in advance by the applicant of the latter’s project to introduce the naked DSL, but had not voiced any objections in that regard.

382    Furthermore, the applicant does not adduce any evidence capable of calling into question the finding, made in recitals 1402 to 1404 of the contested decision, according to which that project was subject to a request for information from the applicant made by Deutsche Telekom’s regulatory affairs department, after the latter was informed about that project. According to recital 1404 of the contested decision, that request for information led Mr C. S., an employee of the applicant, not only to respond to Deutsche Telekom, but also to immediately send an email to Mr H. M., an employee of Deutsche Telekom seconded to that subsidiary, in which he informed the latter that Deutsche Telekom ‘[was] suddenly “realizing”’ what the applicant was doing ‘in wholesale’ and stated, in essence, that that could cause problems.

383    The evidence examined in paragraphs 381 and 382 above suffice to establish that, as the Commission in essence stated in recital 1406 of the contested decision, the applicant feared Deutsche Telekom’s reaction to its project to introduce the naked DSL, which does not seem to be compatible with complete commercial independence on the part of that subsidiary on the market.

384    Secondly, it is admittedly true that the applicant was able to introduce a naked DSL offer despite Deutsche Telekom’s reservations in that regard. However, first, it should be noted that the existence of a certain independence on the part of the subsidiary, in particular in the management of its commercial strategy stricto sensu, is not incompatible with that subsidiary forming part of the same economic unit as its parent company (judgment of 13 December 2013, HSE v Commission, T‑399/09, not published, EU:T:2013:647, paragraph 80). Secondly, it is necessary to note the finding, made by the Commission in recital 1408 of the contested decision and which is not contested in the context of the present action, according to which Deutsche Telekom’s position on that issue was not as inflexible as the Commission alleged during the administrative procedure. It follows from that recital that Deutsche Telekom’s regulatory affairs department had indicated, in an email sent to the applicant on 23 November 2005, that ‘naked DSL [was] regarded as a strong threat’, but that Deutsche Telekom understood that ‘there may be reasons in Slovakia which may justify a deviating approach’.

385    In those circumstances, the Commission did not commit an error when it concluded in essence, in recital 1411 of the contested decision, that the applicant’s decision to offer naked DSL was not capable of establishing that that subsidiary determined its conduct on the market independently and of calling into question the set of indications, identified by the Commission in the contested decision, that those two entities formed a single economic unit.

386    The second complaint of the third part of the present plea in law must therefore be rejected.

(iv) The applicant’s intention to develop a next generation network

387    By its third complaint, the applicant claims that its decision to introduce NGN, which was taken in 2003 independently and against the wishes of Deutsche Telekom, is another example of its independent conduct. That decision was part of the applicant’s eNGine programme, which it designed itself. The applicant was well aware of Deutsche Telekom’s scepticism when it took that decision. The applicant states that all of the minutes of the international management meetings to which the Commission refers as evidence of Deutsche Telekom’s involvement in the introduction of that technology date from the period between 2006 and 2009 and are thus subsequent to the decision taken in 2003. The contested decision does not therefore contain any arguments to support the Commission’s position.

388    In that regard, it admittedly follows from the elements cited in recital 1418 of the contested decision that Deutsche Telekom was initially opposed to the introduction by the applicant of an NGN network.

389    However, the Commission did not commit an error when it concluded, in recital 1422 of the contested decision, on the basis of extracts set out in recitals 1420 and 1421 of the contested decision, that the introduction of NGN by the applicant was not an indication that that subsidiary independently determined its position on the market.

390    The third complaint of the third part of the present plea in law must therefore be rejected.

(v)    The applicant’s decision to offer satellite television (DVB-S)

391    By its fourth complaint, the applicant claims that its decision to introduce DVB-S illustrates that it developed strategies and products independently. Contrary to the Commission’s contention that that project was a ‘further example of [Deutsche Telekom]’s close and early involvement in [the applicant]’s projects’ (recital 1426 of the contested decision), DVB-S was introduced on the applicant’s initiative alone.

392    In that regard, it must be noted that the findings made in recital 1424 of the contested decision relating to the minutes of the international management meetings from 2008 and 2009, the contents of which are not called into question by the applicant, establish the close involvement of Deutsche Telekom in the introduction by the applicant of satellite television. Firstly, on the basis of extracts reproduced in recital 1424 of the contested decision, the Commission did not commit an error when it considered, in that recital, that close cooperation was envisaged within the Deutsche Telekom group on that matter. Secondly, it is apparent from other extracts referred to in that recital that Deutsche Telekom expressed its intention to be kept informed about that project and indicated that it was necessary to involve its ‘International Controlling T-Home’ department in that project. Thirdly, it is apparent from the minutes of the international management meeting of 29 January 2009, referred to in that recital, that the business cases for the DVB-S were presented to the Deutsche Telekom management even before they were subject to the approval of that subsidiary’s Executive Management Board.

393    Even assuming that those meetings establish solely that Deutsche Telekom wished to be informed so as to assess the possible impact on the results of the Deutsche Telekom group and to establish appropriate preparatory notes for its representatives on the applicant’s Board of Directors, that does not suffice to establish, in the light in particular of the case-law referred to in paragraph 384 above, that the introduction by the applicant of satellite television constituted an indication of its independence on the market. On the contrary, in accordance with what was set out in paragraph 309 above, such involvement by Deutsche Telekom in the planning and financing of such a project is part of the decentralised management typical of large undertakings and thus constitutes itself, as the Commission correctly noted in recital 1426 of the contested decision, an indication that Deutsche Telekom and the applicant indeed formed a single undertaking during the period under consideration.

394    The fourth complaint of the third part of the present plea in law must therefore be rejected.

(vi) Development by the applicant of its own branding strategy

395    By its fifth complaint, the applicant claims that it decided independently on its branding, the features of its products and its marketing campaigns. In that regard, while all of Deutsche Telekom’s affiliates had the opportunity to use the parent company’s brands for their own products, the applicant was nevertheless able to decide independently which brands it wished to use.

396    In that regard, concerning the errors allegedly committed by the Commission in the analysis of the applicant’s branding strategy, examined in recitals 1427 to 1437 of the contested decision, it should be noted that the fact that two companies present themselves towards the outside world as forming part of the same group constitutes relevant evidence which, without being sufficient in itself, may be taken into consideration along with other evidence in order to justify the conclusion that they form part of the same economic unit (see, to that effect, judgment of 13 December 2013, HSE v Commission, T‑399/09, not published, EU:T:2013:647, paragraph 36). Contrary to what is, in essence, claimed by the applicant, the existence of such a unit in relation to third parties reflects in principle the nature of the economic, organisational and legal connections between those companies.

397    Moreover, it should be noted that the applicant does not adduce any evidence capable of calling into question the findings made in recitals 1434 and 1435 of the contested decision, according to which it follows from the minutes of the international management meetings referred to in those recitals that the applicant, in every case, justified its choice to Deutsche Telekom, without the parent company objecting. As was noted in paragraph 384 above, a certain degree of independence on the part of a subsidiary in the management of its commercial policy stricto sensu, is not incompatible with that subsidiary forming part of the same economic unit as its parent company.

398    Finally, as regards the examples in its reply to the statement of objections to which the applicant referred in its response, it must be noted that the applicant in no way substantiates the grounds on which those examples allow it to be established that the Commission committed an error.

399    The fifth complaint of the third part of the present plea in law must therefore be rejected.

(vii) The applicant’s role with regard to a project in the Gulf States

400    By its sixth complaint, the applicant claims that the Commission should have taken account of the fact that it had agreed to provide consulting services to a telecommunications operator of the Gulf countries despite objections expressed in that regard by Deutsche Telekom.

401    It should be noted that, according to recital 1438 of the contested decision, the applicant decided in 2005 to share its experience acquired in the area of NGN based on a consultancy agreement with a group of financial investors intending to establish a new telecommunications company in the Gulf States. It is also apparent from that recital that that agreement was concluded in September 2005, without the intervention of the applicant’s Board of Directors, and that it provided for support to the initial development and operation of NGN with a number of points of presence in Kuwait, Bahrain, Qatar, Oman, Saudi Arabia and the United Arab Emirates as well as the development of an international operation for the newly established telecommunications undertaking.

402    The applicant claims that the decision to conclude that agreement was taken in spite of the opposition expressed by Deutsche Telekom and that that decision thus constituted an additional indication that the applicant and Deutsche Telekom did not form a single economic unit during the period under consideration.

403    In that regard, it must be borne in mind that the Commission showed, with the help of extracts relating to the international management meetings included in recital 1441 of the contested decision, that the continuation of that project was indeed approved by Deutsche Telekom during the international management meeting of 2 March 2007. The applicant does not adduce any evidence to call that finding into question.

404    The sixth complaint of the third part of the present plea in law must therefore be rejected.

(viii) The applicant’s decision to implement the POP Ukraine project

405    By its seventh complaint, the applicant alleges that the Commission disregarded the evidence of the independent decision, in 2005, relating to the creation of a ‘point of presence’ (POP) in Ukraine. In that regard, the applicant considers that the statement of Mr H. M., which the Commission disregarded because it was a written statement prepared for the purpose of this case (recital 1445 of the contested decision), cannot be called in question.

406    In that regard, without it being necessary to rule on the probative value of that statement, it should be noted that the applicant’s decision to establish an office in Ukraine was not an indication that the applicant independently determined its position on the market. Assuming that statement to be valid for the purposes of the present case, although the elements set out in recitals 1443 and 1444 of the contested decision tend, admittedly, to confirm that the applicant enjoyed a certain independence when defining its commercial policy, they also indicate the close involvement of Deutsche Telekom in the POP Ukraine project. It follows that the Commission was able, without committing an error, to conclude that the applicant’s decision to establish an office in Ukraine was not an indication that the applicant determined its position on the market independently of Deutsche Telekom.

407    Therefore, it is necessary to reject the seventh complaint of the third part of the present plea in law.

(ix) The applicant’s decision to outsource the management of the fleet of vehicles and to purchase IP (Internet Protocol) transit services

408    By its eighth complaint, the applicant claims that the decision not to outsource the fleet management project and to purchase IP (Internet Protocol) transit services was taken independently. The Commission was wrong to find that those decisions are of ‘limited value’. The Commission stated that those decisions did not constitute ‘ordinary business decisions’ because they form part of ‘the limited number of decisions … for which a qualified majority is necessary in the [Board of Directors]’. The applicant asserts that it nevertheless decided in both cases not to cooperate with other Deutsche Telekom affiliates without ever reaching the stage where the project would have required board approval.

409    In that regard, in the first place, it should be pointed out that, according to recital 1446 of the contested decision, the applicant anticipated at a given time entrusting to a third party the management of its fleet of vehicles and launched for that purpose a call for tenders. It is moreover not disputed that DeTeFleetServices GmbH, another subsidiary of Deutsche Telekom, submitted a tender with a view to obtaining that contract. As is apparent from recital 1447 of the contested decision, that management project for the fleet was approved by the applicant’s Board of Directors, which was decisively influenced by Deutsche Telekom.

410    In the second place, as regards the decision relating to the purchase of IP transit services, according to recital 1451 of the contested decision, Deutsche Telekom declared that operators such as the applicant purchased IP transit services from incumbent operators of a core network abroad so as to ensure internet connectivity beyond national borders. However, as is apparent from recital 1452 of the contested decision, Deutsche Telekom declared that the applicant did not receive IP transit services from its ICSS branch, either completely or on a major scale. Deutsche Telekom also maintained, in essence, that that decision conflicted with its intention that the transit services in all the IP networks within the Deutsche Telekom group be placed under the aegis of the ICSS so as to achieve economies of scale.

411    Contrary to what is claimed by the applicant, those elements do not amount to an indication that the applicant independently determined its conduct on the market. Firstly, it should be borne in mind that the exercise by a parent company of decisive influence over the commercial policy of a subsidiary does not require proof of an interference in the day-to-day management of that subsidiary’s operation, nor of influence over its commercial policy stricto sensu (see paragraph 313 above and the case-law cited). Since the applicant’s decisions referred to in paragraphs 408 and 410 above relate to the day-to-day management of that subsidiary, they are not capable of calling into question the set of indications identified by the Commission in the contested decision, establishing that the undertaking’s general strategy and orientation were defined by Deutsche Telekom.

412    Secondly, and in any event, those decisions in no way establish that the applicant acted in a manner incompatible with the orientation defined by Deutsche Telekom.

413    As regards the applicant’s decision to retain the management of its vehicle fleet in-house and, therefore, not to outsource it to DeTeFleetServices, it suffices to note that that decision illustrates a situation in which the applicant sought an optimal commercial solution by making use of the room for manoeuvre left to it by Deutsche Telekom. The fact that that decision deprived another subsidiary of Deutsche Telekom, namely DeTeFleetServices, of an interesting transaction does not however mean that that decision was adopted in spite of Deutsche Telekom’s opposition.

414    As regards the applicant’s failure to make use of the IP transit services offered by the ICSS branch of Deutsche Telekom, the refusal to put aside its own commercial interests in favour of synergies at the level of the group does not suffice to show the absence of decisive influence over the applicant’s conduct.

415    The eighth complaint of the third part of the present plea in law must therefore be rejected.

416    In the light of the foregoing, it must be concluded that the Commission did not commit an error when it considered that the various conduct and decisions of the applicant examined in paragraphs 375 to 415 above did not provide indications that that subsidiary determined its conduct on the market independently and was, consequently, not capable of calling into question the set of indications moreover identified in the contested decision to the effect that the parent company and the subsidiary formed a single economic unit during the period under consideration. The third part of the plea in law must therefore be rejected as unfounded.

(4)    Fourth part based on the necessity of proving that the exercise of decisive influence was significant and alleging infringement of the obligation to state reasons

417    In the first place, the applicant considers that, even if Deutsche Telekom exercised decisive influence over it, the Commission has to prove, in particular, the significance of such exercise with respect to the independence of the applicant on the market. It is apparent from the case-law of the Court that the conduct of a subsidiary may be imputed to the parent company particularly where, although having a separate legal personality, that subsidiary does not decide independently on its own conduct on the market, but carries out, in all material respects, the instructions given to it by the parent company. This means that the parent company has a power of direction over its subsidiary to the point of depriving it of any real independence in determining its own course of action on the market. In the present case, the contested decision did not examine that point and failed to show that the applicant carried out, in all material respects, the instructions given to it by Deutsche Telekom.

418    In the second place, in so far as the contested decision did not state that the applicant carried out, in all material respects, the instructions given to it by Deutsche Telekom, the Commission failed to fulfil its obligation to state reasons.

419    The fourth part of the fourth plea in law cannot succeed.

420    First, it does not follow from the case-law set out in paragraphs 282 to 288 above that the Commission must prove, in addition to the ability of the parent company to exercise decisive influence over a subsidiary and the actual exercise thereof, that the decisive influence was significant.

421    Secondly, as was noted in paragraph 384 above, the existence of a certain amount of autonomy on the part of the subsidiary, in particular in the management of its commercial policy stricto sensu, is not incompatible with that subsidiary forming part of the same economic unit as its parent company.

422    In the present case, in the light of the arguments in paragraphs 290 to 415 above, it must be concluded that the examination of the economic, organisational and legal links between the applicant and Deutsche Telekom permitted it to be established that the applicant’s general strategy on the market was defined by Deutsche Telekom. Therefore, the Commission correctly concluded that those two companies formed a single economic unit during the period under consideration, even if that unit was marked by decentralisation of the day-to-day management of the applicant’s activities.

423    Moreover, in the light of the clear and detailed explanations provided in that regard in recitals 1186 to 1483 of the contested decision, it must be concluded that that decision contains a detailed statement of reasons such as to comply with the requirement referred to in paragraph 163 above.

424    Therefore, the complaint alleging a failure to state reasons must be rejected.

425    Consequently, the two complaints presented in support of the fourth part of the fourth plea in law must be rejected as unfounded.

426    It follows that it is necessary to reject the fourth plea in law as unfounded, without the need to examine its admissibility.

5.      The fifth plea in law, raised in the alternative, alleging errors in the determination of the amount of the fine

427    By its fifth plea in law, raised in the alternative, the applicant claims that the Commission committed errors in the calculation of the amount of the fine imposed on it. That plea is divided into two parts. The first part alleges a manifest error of assessment where the Commission took account of the applicant’s turnover for the 2010 financial year for the purpose of calculating the amount of the fine. The second part alleges a manifest error of assessment relating to the date on which the infringement period commenced.

(a)    First part alleging a manifest error of assessment as a result of the applicant’s turnover for the 2010 financial year being taken into account for the purpose of calculating the amount of the fine

428    The applicant considers that the Commission committed a manifest error of assessment in finding, in accordance with point 13 of the 2006 Guidelines, that the basic amount of the fine had to be calculated on the basis of the turnover for the last full year of the infringement, namely, in particular, the applicant’s turnover on the unbundled local loop market and fixed broadband market in 2010.

429    In so doing, the Commission diverged from its own decision-making practice, namely Decision C(2011) 4378 final, of 22 June 2011, relating to a proceeding under Article 102 TFEU (Case COMP/39.525 — Polish telecommunications) (‘the Polish Telecommunications decision’). In recital 896 of that decision, the Commission found that it was appropriate to take the average annual sales due, first, to the significant growth in sales during the period in question in the relevant market, particularly wholesale sales and, secondly, to the fact that the market was still developing and hence growing beyond normal market growth rates at the time of the infringement. That consideration should be applied to the present case since the Commission admitted in the contested decision that the applicant’s turnover had grown by 133% between 2005 and 2010. Therefore, relying on that decision, the applicant argues that the basic amount of the fine should have been calculated on the basis of the average of the five years of infringement found by the Commission.

430    By relying on the last financial year, the Commission applied stricter standards to the applicant than in the Polish Telecommunications decision. The applicant also states that although the Commission enjoys a margin of discretion in setting the amount of fines, it cannot act in an arbitrary and inconsistent manner.

431    The Commission, supported by the intervener, contests those arguments.

432    It is necessary, first of all, to note that Article 23(3) of Regulation No 1/2003 provides that, in fixing the amount of the fine, regard must be had both to the gravity and to the duration of the infringement.

433    Moreover, it should be noted that, according to point 13 of the 2006 Guidelines, ‘in determining the basic amount of the fine to be imposed, the Commission will take the value of the undertaking’s sales of goods or services to which the infringement directly or indirectly relates in the relevant geographic area within the EEA’ and that for that purpose, it ‘will normally take the sales made by the undertaking during the last full business year of its participation in the infringement …’.

434    It is apparent, moreover, from the case-law that the proportion of the turnover accounted for by the goods or services in respect of which the infringement was committed gives a proper indication of the scale of the infringement on the relevant market, since the turnover in those goods or services constitutes an objective criterion giving a proper measure of the harm which that practice does to normal competition (see, to that effect, judgment of 28 June 2016, Portugal Telecom v Commission, T‑208/13, EU:T:2016:368, paragraph 236 and the case-law cited).

435    Point 13 of the 2006 Guidelines thus aims, as regards an infringement of Article 102 TFEU, to adopt as the starting point for the calculation of the amount of the fine imposed on the undertaking at issue an amount which reflects the economic significance of the infringement (see, to that effect, judgments of 11 July 2013, Team Relocations and Others v Commission, C‑444/11 P, not published, EU:C:2013:464, paragraph 76; of 12 November 2014, Guardian Industries and Guardian Europe v Commission, C‑580/12 P, EU:C:2014:2363, paragraph 57; and of 23 April 2015, LG Display and LG Display Taiwan v Commission, C‑227/14 P, EU:C:2015:258, paragraph 53).

436    However, it should also be noted that the self-limitation of the Commission’s discretion arising from the adoption of the 2006 Guidelines is not incompatible with that institution maintaining a substantial margin of discretion. Those guidelines display flexibility in a number of ways, enabling the Commission to exercise its discretion in accordance with the provisions of Regulation No 1/2003, as interpreted by the EU Courts (see, to that effect, judgment of 11 July 2013, Team Relocations and Others v Commission, C‑444/11 P, not published, EU:C:2013:464, paragraph 96 and the case-law cited), and with other rules and principles of Union law. In particular, point 13 of the 2006 Guidelines itself states that the Commission must ‘normally’ use the sales made by the undertaking during the last full business year of its participation in the infringement for the calculation of the amount of the basic fine (see, to that effect, judgment of 9 September 2015, Samsung SDI and Others v Commission, T‑84/13, not published, EU:T:2015:611).

437    In the present case, it is apparent from recitals 1490 to 1495 of the contested decision that, in order to determine the basic amount of the fine imposed jointly and severally on the applicant and on Deutsche Telekom, the Commission took account of the sales made by the applicant during the last full business year of its participation in the infringement, namely the turnover achieved by that operator on the market for access to unbundled local loops for fixed retail broadband in 2010. The Commission thus applied point 13 of the 2006 Guidelines.

438    The applicant cannot be followed when it claims that the Commission committed a manifest error of assessment by not deviating from that rule in the present case, despite the sharp increase in its turnover during the period under consideration.

439    First, although the applicant claims that, between 2005 and 2010, its turnover increased by 133%, from EUR 31 184 949 to EUR 72 868 176, it nevertheless does not put forward any evidence capable of establishing that that latter turnover, achieved over the last full calendar year of the infringement, did not constitute, at the time when the Commission adopted the contested decision, an indication of its true size, of its economic power on the market and of the scope of the infringement at issue.

440    Secondly, the applicant cannot be followed when it complains that the Commission ignored its Polish Telecommunications decision and, as a result, disregarded its previous practice and imposed a criterion different from that provided for in point 13 of the 2006 Guidelines.

441    It is apparent from settled case-law that the Commission’s practice in previous decisions does not itself serve as a legal framework for the fines imposed in competition matters and that decisions in other cases can give only an indication for the purpose of determining whether there might be discrimination since the facts of those cases, such as markets, products, the undertakings and periods concerned, are not likely to be the same (see judgments of 24 September 2009, Erste Group Bank and Others v Commission, C‑125/07 P, C‑133/07 P and C‑137/07 P, EU:C:2009:576, paragraph 233 and the case-law cited; of 16 June 2011, Heineken Nederland and Heineken v Commission, T‑240/07, EU:T:2011:284, paragraph 347; and of 27 February 2014, InnoLux v Commission, T‑91/11, EU:T:2014:92, paragraph 144).

442    Therefore, previous decisions by the Commission imposing fines can be relevant from the point of view of observance of the principle of equal treatment only where it is demonstrated that the facts of the cases in those other decisions, such as markets, products, the countries, the undertakings and periods concerned, are comparable to those of the present case (see judgments of 13 September 2010, Trioplast Industrier v Commission, T‑40/06, EU:T:2010:388, paragraph 145 and the case-law cited; of 29 June 2012, E.ON Ruhrgas and E.ON v Commission, T‑360/09, EU:T:2012:332, paragraph 262 and the case-law cited; and of 9 September 2015, Philips v Commission, T‑92/13, not published, EU:T:2015:605, paragraph 204 and the case-law cited).

443    In the present case, the applicant has not put forward any evidence capable of establishing that the facts of the case which gave rise to the Polish Telecommunications decision were comparable to those of the present case. The Commission stated in its pleadings that, in that case, it had taken into account the average of the turnover of 2005 to 2009 on the ground that the relevant turnover of the period concerned had grown exponentially, namely an increase of 2 800% for the period from 2006 to 2007, an increase of 370% for the period from 2007 to 2008 and an increase of 160% for the period from 2008 to 2009. It follows from that turnover, the correctness of which is not called into question by the applicant, that, first, the rate of growth of the turnover was much higher in the case giving rise to the Polish Telecommunications decision than that of the applicant’s turnover in the present case and, secondly, that that turnover evolved in a less stable way than the turnover observed in the present case.

444    It follows from the above that, by taking into account in the present case the turnover achieved by the applicant during the year ending 31 December 2010, namely the last full business year of participation in the infringement, and by thus complying with its own rule set out in point 13 of the 2006 Guidelines, the Commission did not exceed the limits of its discretion concerning the determination of the amount of fines.

445    The first part of the fifth plea in law must therefore be rejected as unfounded.

(b)    Second part, alleging a manifest error of assessment relating to the date on which the infringement period commenced

446    By its second part, the applicant claims that the contested decision is vitiated by a manifest error of assessment in so far as it finds the existence of an infringement commencing on 12 August 2005, the date on which the reference offer was published. As a framework contract, that offer was meant to evolve, particularly in the course of negotiations with third parties or following advice provided by national regulatory authorities.

447    More particularly, the applicant notes, first, that that offer was the first the applicant had ever drawn up, which made clarifications and amendments through negotiations all the more necessary.

448    Secondly, the Commission’s position according to which that infringement starts with the publication of the reference unbundling offer is not consistent with its decision-making practice. By way of example, in its Decision C(2004) 1958 final, of 2 June 2004 (Case COMP/38.096 — Clearstream) (‘the Cleastream decision’), the Commission concluded that Clearstream had abused its dominant position by constructively refusing to supply Euroclear with primary clearing and settlement services for registered shares. The Commission, nevertheless, acknowledged that it was necessary to give the parties some time to enable them to negotiate the terms and conditions of the contracts (recital 341 of the Clearstream decision). Likewise, in its Polish Telecommunications decision, the Commission did not take the date of publication of the reference offer as the starting date of the infringement, but the day of the beginning of its first negotiations with the other operators.

449    The applicant states that a refusal to supply infringement can only exist after access negotiations have failed due to the unreasonableness of the conditions set by the network holder. Furthermore, according to the applicant, the onus was on the Commission to prove at what point in time the negotiations failed due to the applicant’s unreasonable demands. Moreover, account needs to be taken of the fact that access negotiations are by definition long and cumbersome given the complexity of the matter.

450    In the alternative, the applicant considers that the alleged refusal to grant access starts either at the end of a reasonable period that granting access would normally require involving preparations from both sides (recital 341 of the Clearstream decision) or on the start date of the initial access negotiations with alternative operators (recital 909 of the Polish Telecommunications decision).

451    The Commission, supported by the intervener, disputes those arguments.

452    In that regard, it is not disputed that, by his decision of 14 June 2005, the Chairman of TUSR required the applicant to provide unbundled access to its local loop under fair and reasonable conditions, and that it is with a view to fulfilling that obligation that the applicant published, on 12 August 2005, a reference unbundling offer (see paragraphs 9 and 10 above).

453    Moreover, the applicant does not dispute the description of the contents of its reference offer made in section 7.6 of the contested decision (‘ST’s unfair terms and conditions’), according to which the Commission concluded, in recital 820 of that decision, that the terms and conditions of that offer had been set so as to render unbundled access to the local loop unacceptable for the alternative operators.

454    It is apparent from that part of the contested decision that the abusive practices which are there classified as ‘refusal to supply’ by the Commission resulted, essentially, from the reference offer itself.

455    Therefore, as regards, firstly, the lack of disclosure to alternative operators of information relating to the applicant’s network, which is necessary for the unbundling of the local loop, it follows first of all from recital 439 of the contested decision that the Commission considered that the reference offer did not contain the basic information regarding the locations of physical access sites and the availability of local loops in specific parts of the access network. Furthermore, in recitals 443 to 528 of the contested decision, the Commission admittedly examined the information relating to the network provided by the applicant at the request of an alternative operator with a view to unbundling. However, it follows also from that part of the contested decision that the arrangements for access to such information which were considered by the Commission to be unfair and, therefore, dissuasive for alternative operators resulted from the reference offer itself. The Commission in particular criticised the fact, in the first place, that the reference offer had not determined the exact scope of the information relating to the network that the applicant would place at the disposal of alternative operators, by specifying the categories of information concerned (recital 507 of the contested decision), in the second place, that that offer provided access to information from the non-public information systems only after the conclusion of the framework agreement on access to the local loop (recital 510 of the contested decision) and, in the third place, that that offer made such access to information relating to the applicant’s network subject to the payment by the alternative operator of large fees (recitals 519 and 527 of the contested decision).

456    As regards, secondly, the reduction of the scope of its regulatory obligation concerning unbundled access to the local loop, first of all, it follows from recitals 535 and 536 of the contested decision that the restriction of that obligation to active lines only (see paragraph 32 above), alleged of the applicant by the Commission, resulted from paragraph 5.2 of the introductory part of its reference offer. Next, it follows in particular from recitals 570, 572, 577, 578 and 584 of the contested decision that it is in the light of stipulations contained in Annex 3 to that reference offer that the Commission inferred that the applicant had unjustifiably excluded conflicting services from its obligation relating to unbundled access to the local loop (see paragraph 33 above). Finally, it follows from recital 606 of the contested decision that the 25% cable use limitation rule imposed by the applicant for unbundled access to the local loop and regarded by the Commission as unjustified (see paragraph 34 above), resulted from Annex 8 to the reference offer.

457    As regards, thirdly, the setting by the applicant of unfair conditions relating to unbundling regarding collocation, qualification, forecasting, repairs, service and maintenance and bank guarantee, they all resulted, as is shown in section 7.6.4 of the contested decision, from the reference offer published by that operator on 12 August 2005. Also, the terms which are considered by the Commission to be unfair were included respectively in Annexes 4, 5, 14 and 15 to that offer as regards collocation (recitals 653, 655 and 683 of the contested decision), in Annexes 12 and 14 as regards the alternative operators’ forecasting obligation (recitals 719 and 726 to 728 of the contested decision), in Annex 5 as regards the qualification procedure of the local loops (recitals 740, 743, 767, 768 and 774 of the contested decision), in Annex 11 as regards the terms and conditions relating to repairs, service and maintenance (recitals 780, 781, 787, 790 and 796 of the contested decision), and in Annexes 5 and 17 as regards the bank guarantee required from the alternative operator which is a candidate for unbundled access (recitals 800, 802 to 807, 815 and 816 of the contested decision).

458    It follows that, even assuming that some of those terms of access were liable to be relaxed in the context of bilateral negotiations between the applicant and operators seeking access, which the applicant merely affirms without corroborating evidence, the Commission correctly concluded that the reference offer published on 12 August 2005 was capable of dissuading as from that date applications for access made by alternative operators, due to the unfair terms and conditions which it contained.

459    In those circumstances, the Commission did not commit an error in finding that, as a result of the terms of access in its reference offer published on 12 August 2005, the applicant had compromised the entry of alternative operators onto the mass (or general public) retail market for broadband services at a fixed location in Slovakia, in spite of the obligation imposed on it in that regard under TUSR’s decision, and that that conduct was therefore capable of having such negative effects on competition from that date (see, inter alia, recitals 1048, 1050, 1109, 1184 and 1520 of the contested decision).

460    That conclusion is not undermined by the applicant’s claim that the Commission infringed its own decision-making practice, namely the approach adopted in the Clearstream decision and in the Polish Telecommunications decision. It suffices to note that those decisions were made in a context which is different from that of the present case and that they are therefore not capable of establishing that in the contested decision the Commission diverged from its previous decision-making practice.

461    Therefore, in the first place, as regards the Clearstream decision, it suffices to note that that decision, unlike the contested decision in the present case, was taken in a context characterised by the absence of any regulatory obligation for the undertaking which owns the infrastructure at issue to grant other undertakings access to that infrastructure, and by the absence of an obligation imposed on that undertaking to publish a reference offer setting out the terms and conditions of such access.

462    Moreover, the period of four months, which the General Court considered to correspond to the reasonable time limit for the provision of the primary clearing and settlement services by Clearstream, had been established by comparing the examples in which Clearstream granted access to its Cascade RS system. Therefore, it should be noted that, in that case, there were several examples in which Clearstream had granted access, which allowed the Commission, and later the Court, to reach the conclusion that the period of four months was reasonable to grant such access (judgment of 9 September 2009, Clearstream v Commission, T‑301/04, EU:T:2009:317, paragraph 151). However, in the present case, since the applicant gave access to its local loops only to one other operator on 18 December 2009, there was no example which could serve as a reference, so that the Commission could not fix such a ‘reasonable period’. It follows that the circumstances of the present case are not comparable with those of the case giving rise to the judgment of 9 September 2009, Clearstream v Commission (T‑301/04, EU:T:2009:317).

463    In the second place, as regards the Polish Telecommunications decision, the Commission found that the incumbent operator at issue had abused its dominant position on the Polish wholesale market for broadband access and unbundled access to the local loop, by refusing to give access to its network and to supply wholesale products from those markets in order to protect its position on the retail market. Moreover, the context of the Polish Telecommunications case was characterised by a regulatory obligation to grant access similar to that imposed on the applicant in the present case, and by the obligation imposed on the Polish Telecommunications operator at issue to publish a reference offer for unbundled access to its local loop. Nevertheless, it is apparent from a detailed analysis of the Polish Telecommunications decision that the approach taken in that decision is not inconsistent with that taken in the contested decision. In the Polish Telecommunications decision, the Commission noted that the dominant operator’s anticompetitive strategy essentially materialised only in the course of negotiations with alternative operators which were candidates for the grant of unbundled access to the local loop and wholesale access to the dominant operator’s broadband services. Therefore, the unreasonable access conditions resulted from proposals for access contracts made by the dominant operator at issue in the context of negotiations with alternative operators. Furthermore, the delay in the process of negotiating access agreements could not, by hypothesis, have been identified upon the publication of the dominant operator’s first reference offer. In addition, the limitation of access to its network carried out by the dominant operator took place at a later stage than the conclusion of the wholesale access agreements with the alternative operators. Moreover, the limitation of effective access to subscriber lines took place after the alternative operator concerned obtained access to a collocation space or the authorisation to install a correspondence cable. Finally, the problems of access to reliable and accurate general information which is necessary for alternative operators to take decisions relating to access were manifest at every step of the procedure for access to the dominant operator’s network. The conduct of the dominant operator in the Polish Telecommunications case was therefore different from the practices which were classified as ‘refusal to supply’ by the Commission in the contested decision, practices which, as is apparent from the analysis in paragraphs 455 to 459 above, resulted essentially from the reference offer for unbundled access to the local loop of the applicant itself. In contrast to the Polish Telecommunications decision in which the starting point of the infringement of Article 102 TFEU was fixed at the date on which the first access negotiations between the dominant operator at issue and an alternative operator had begun, several months after the publication of the first reference offer (recital 909 and the footnote to page 1259 of the contested decision), those differences justify the Commission identifying, in the present case, 12 August 2005, that is to say the date of publication of the reference offer, as the date of commencement of the implied refusal of access to the local loop.

464    For the same reason, it is necessary to reject the applicant’s argument that the refusal to supply infringement can be established only after the access negotiations have failed due to the unreasonableness of the conditions set by the network holder. In addition, it is not certain that the negotiations could have led to the unfair terms and conditions in the reference offer being removed.

465    Concerning the applicant’s allegation that the Commission must bear the burden of proof in relation to the point in time the negotiations failed due to the applicant’s unreasonable demands, first, for the same reasons as those indicated in paragraphs 461 to 464 above, that date cannot be relevant in order to determine the start of the infringement. Secondly, as the intervener contended, the exact date of the failure of the negotiations cannot be objectively determined, so that the Commission is not required to provide such proof.

466    As regards the arguments presented in the alternative, in so far as the applicant considers that the alleged refusal to grant access should start at the end of a reasonable period that granting access would normally require involving preparations from both sides (recital 341 of the Clearstream decision), it should be noted that such a reasonable period does not exist in the present case for the reasons set out in paragraphs 460 to 462 above. Therefore, that argument must be rejected. In so far as the applicant intends the infringement to start on the date of the initial access negotiations with alternative operators (recital 909 of the Polish Telecommunications decision), as was considered, in essence, in paragraphs 463 and 464 above, the negotiations were not relevant for the purposes of determining the start of the infringement in this case. Consequently, that argument must also be rejected.

467    The second part, alleging an error committed by the Commission when it found that the implied refusal of access to the local loop began on 12 August 2005, must therefore be rejected as unfounded.

468    It should be added that the applicant does not dispute the classification of a single and continuous infringement adopted by the Commission with respect to all of the practices mentioned in Article 1(2) of the contested decision, namely (a) withholding from alternative operators network information necessary for the unbundling of local loops; (b) reducing the scope of its obligations regarding unbundled local loops; (c) setting unfair terms and conditions in its reference unbundling offer regarding collocation, qualification, forecasting, repairs and bank guarantees; (d) applying unfair tariffs which do not allow an equally efficient competitor relying on wholesale access to the unbundled local loops of the applicant to replicate the retail broadband services offered by the applicant without incurring a loss.

469    In those circumstances, and in so far as the second part of the present plea in law, alleging an error committed by the Commission when it found that the implied refusal of access to the local loop began on 12 August 2005, was rejected (see paragraph 467 above), the Commission was justified in finding that the single and continuous infringement which is the object of the contested decision had started on 12 August 2005.

470    Therefore, it is necessary to reject the fifth plea in law in its entirety.

471    It follows from all the foregoing that Article 1(2)(d) of the contested decision must be annulled in so far as it declares that, during the period between 12 August and 31 December 2005, the applicant applied unfair tariffs which do not allow an equally efficient competitor relying on wholesale access to its unbundled local loops to replicate the retail broadband services offered by it without incurring a loss (see paragraph 268 above). As a result, Article 2 of that decision must also be annulled in so far as it concerns the applicant. The remainder of the claim for annulment of the contested decision must be dismissed.

IV.    The conclusions, put forward in the alternative, seeking variation of the amount of the fine

472    The applicant also requests the Court, in the alternative, to reduce the amount of the fines which were imposed on it by the contested decision.

473    It should be noted, in that regard, that, according to settled case-law, the review of legality provided for in Article 263 TFEU entails the EU judicature conducting a review, in respect of both the law and the facts, of the contested decision in the light of the arguments relied on by an applicant, which means that it has the power to assess the evidence, annul the decision and to alter the amount of the fines (see, to that effect, judgments of 3 September 2009, Prym and Prym Consumer v Commission, C‑534/07 P, EU:C:2009:505, paragraph 86 and the case-law cited; of 26 January 2017, Duravit and Others v Commission, C‑609/13 P, EU:C:2017:46, paragraph 30 and the case-law cited; and of 27 March 2014, Saint-Gobain Glass France and Others v Commission, T‑56/09 and T‑73/09, EU:T:2014:160, paragraph 461 and the case-law cited).

474    The review of legality is supplemented by the unlimited jurisdiction which Article 31 of Regulation No 1/2003, in conjunction with Article 261 TFEU, confers on the EU judicature. That jurisdiction empowers the Courts, beyond carrying out a mere review of legality with regard to the penalty, to substitute their own appraisal for the Commission’s and, consequently, to cancel, reduce or increase the fine or penalty payment imposed (judgments of 8 December 2011, Chalkor v Commission, C‑386/10 P, EU:C:2011:815, paragraph 63, and of 8 December 2011, KME Germany and Others v Commission, C‑389/10 P, EU:C:2011:816, paragraph 130; see, also, judgment of 26 January 2017, Duravit and Others v Commission, C‑609/13 P, EU:C:2017:46, paragraph 31 and the case-law cited).

475    It should be noted that the exercise of unlimited jurisdiction does not amount to a review of the Court’s own motion, and that proceedings before the Courts of the European Union are inter partes. Therefore, with the exception of pleas involving matters of public policy which the Courts are required to raise of their own motion, it is for the applicant, in principle, to raise pleas in law against the decision under appeal and to adduce evidence in support of those pleas (see, to that effect, judgment of 10 July 2014, Telefónica and Telefónica de España v Commission, C‑295/12 P, EU:C:2014:2062, paragraph 213 and the case-law cited).

476    It is in the light of those principles that it is necessary to determine whether the amount of the fines imposed by the Commission in the contested decision must be modified.

477    As is apparent from paragraphs 267, 268 and 471 above, the Commission has not provided evidence that that practice leading to a margin squeeze committed by the applicant could have started before 1 January 2006 and, consequently, Article 1(2)(d) of the contested decision must be annulled to the extent that it concerns the applicant and that it includes a margin squeeze which was committed between 12 August and 31 December 2005 in the single and continuous infringement.

478    As regards the impact of that error on the basic amount of the fine for which the applicant is jointly and severally liable, the Court considers, in the exercise of its unlimited jurisdiction, that it is necessary to reduce the proportion of the applicant’s relevant sales applied by the Commission and to establish that proportion at 9.8% instead of 10%. Since the applicant achieved over the course of the last full year of the infringement a relevant turnover of EUR 72 868 176, the amount which must be used to calculate the basic amount of the fine for which the applicant is jointly and severally liable is EUR 7 141 081.20. The basic amount of that fine corresponds to the multiplication of that amount by a coefficient of 5.33, reflecting the duration of the infringement, and must therefore be set at EUR 38 061 963. The applicant’s application for the amount of the fine to be reduced is dismissed as to the remainder.

479    As regards the Commission’s application, brought in the alternative during the hearing, for the amount of the fine imposed jointly and severally on the applicant and on Deutsche Telekom to be increased, the Court considers, without it even being necessary to rule on the admissibility of such an application, that, in the light of the circumstances of the case, it is not necessary to modify the amount fixed in paragraph 478 above.

 V.      Costs

480    Under Article 134(1) of the Rules of Procedure, the unsuccessful party is to be ordered to pay the costs if they have been applied for in the successful party’s pleadings. Furthermore, under Article 134(3) of the Rules of Procedure, the parties are to bear their own costs where each party succeeds on some and fails on other heads. However, if it appears justified in the circumstances of the case, the Court may order that one party, in addition to bearing its own costs, pay a proportion of the costs of the other party. In the present case, the Commission and the intervener have failed on some heads. Nevertheless, the applicant has not applied for the intervener to be ordered to pay the costs, but only for the Commission to be so ordered.

481    In those circumstances, the applicant must be ordered to bear four fifths of its own costs, as well as four fifths of the costs of the Commission and the intervener, in accordance with the form of order sought by them. The Commission is to bear one fifth of its own costs and of those of the applicant. The intervener is to bear one fifth of its own costs.

On those grounds,

THE GENERAL COURT (Ninth Chamber, Extended Composition)

hereby:

1.      Annuls Article 1(2)(d) of Commission Decision C(2014) 7465 final of 15 October 2014 relating to proceedings under Article 102 TFEU and Article 54 of the EEA Agreement (Case AT.39523 — Slovak Telekom) in so far as it declares that, over the course of the period between 12 August and 31 December 2005, Slovak Telekom, a.s., imposed unfair tariffs which do not allow an equally efficient operator relying on wholesale access to its unbundled local loops to replicate the retail broadband services offered by it without incurring a loss;

2.      Annuls Article 2 of Decision C(2014) 7465 final in so far as it fixes the amount of the fine imposed jointly and severally on Slovak Telekom at EUR 38 838 000;

3.      Fixes the amount of the fine imposed jointly and severally on Slovak Telekom at EUR 38 061 963;

4.      Dismisses the action as to the remainder;

5.      Orders Slovak Telekom to bear four fifths of its own costs, four fifths of the costs of the European Commission and four-fifths of the costs of Slovanet, a.s.;

6.      Orders the Commission to bear one fifth of its own costs and one fifth of the costs incurred by Slovak Telekom;

7.      Orders Slovanet to bear one fifth of its own costs.


Van der Woude

Gervasoni

Madise

da Silva Passos

 

      Kowalik-Bańczyk

Delivered in open court in Luxembourg on 13 December 2018.


E. Coulon

 

      S. Gervasoni

Registrar

 

President


Table of contents


I. Background to the dispute

A. Technological, factual and regulatory context of the contested decision

B. Procedure before the Commission

C. Contested decision

1. Definition of the relevant markets and dominant position of the applicant on those markets

2. The applicant’s conduct

(a) Refusal to provide unbundled access to the applicant’s local loops

(b) Margin squeeze of alternative operators in the provision of unbundled access to the applicant’s local loops

3. Analysis of the anticompetitive effects of the applicant’s conduct

4. Addressees of the contested decision and fines

5. Operative part of the contested decision

II. Procedure and forms of order sought

III. Law

A. Admissibility

1. The preliminary observations formulated in the introductory part of the application and relating to the effects of the practices at issue

2. Admissibility of Annex A.9 to the application

B. Substance

1. First plea in law: manifest errors of law and assessment in the application of Article 102 TFEU as regards the applicant’s abusive conduct

(a) The first and fifth complaints

(b) The third complaint

(c) The second complaint

(d) The fourth complaint

2. Second plea in law: infringement of the applicant’s rights of defence as regards the assessment of the practice resulting in the margin squeeze

(a) The first part, alleging procedural errors committed by the Commission concerning the calculation of the long run Average incremental costs (LRAIC)

(b) The second part, alleging the inability to take a position, during the administrative procedure, about the multi-period approach to the calculation of the costs borne by the applicant in order to assess the existence of a practice resulting in the margin squeeze

3. The third plea in law, alleging errors committed in the finding of the margin squeeze

(a) First part alleging that no account was taken of the optimisation adjustments in the calculation of the applicant’s LRAIC

(b) The second part, alleging an error in the margin squeeze calculation due to the consolidation of revenue and costs for the entire period under consideration, as well as infringement of the principle of legal certainty

4. The fourth plea in law, alleging manifest errors of assessment and of law, when the Commission concluded that the applicant and Deutsche Telekom were part of a single undertaking and that they were both liable for the infringement at issue

(a) Admissibility of the fourth plea in law

(b) Substance

(1) First part alleging failure to demonstrate that Deutsche Telekom actually exercised decisive influence over the applicant’s commercial policy or, at the very least, an inadequate statement of reasons

(i) Outline of the principles

(ii) The applicant’s assertion that the Commission did not distinguish between the ability to exercise decisive influence and the actual exercise of such influence

(iii) The management staff overlaps between Deutsche Telekom and the applicant

(iv) The provision by Deutsche Telekom of staff to the applicant

(v) The reports presented at the regular meetings of the Deutsche Telekom group concerning central and eastern Europe

(2) Second part alleging errors of law and a manifest error of assessment as regards the lack of proof of the exercise of decisive influence as well as an infringement of the obligation to state reasons

(i) The examination of decision-making processes within the applicant’s Board of Directors

(ii) The examination of the international management meetings

(iii) The examination of the choice made by the applicant of a vendor of internet television services (IPTV)

(iv) The examination of the EuroTel transaction

(3) Third part alleging errors of law and manifest errors of assessment as regards the applicant’s independent conduct

(i) Preliminary observations

(ii) The applicant’s position with regard to the ‘4-in-1’ project

(iii) Introduction by the applicant of the ‘naked DSL’ in 2005

(iv) The applicant’s intention to develop a next generation network

(v) The applicant’s decision to offer satellite television (DVB-S)

(vi) Development by the applicant of its own branding strategy

(vii) The applicant’s role with regard to a project in the Gulf States

(viii) The applicant’s decision to implement the POP Ukraine project

(ix) The applicant’s decision to outsource the management of the fleet of vehicles and to purchase IP (Internet Protocol) transit services

(4) Fourth part based on the necessity of proving that the exercise of decisive influence was significant and alleging infringement of the obligation to state reasons

5. The fifth plea in law, raised in the alternative, alleging errors in the determination of the amount of the fine

(a) First part alleging a manifest error of assessment as a result of the applicant’s turnover for the 2010 financial year being taken into account for the purpose of calculating the amount of the fine

(b) Second part, alleging a manifest error of assessment relating to the date on which the infringement period commenced

IV. The conclusions, put forward in the alternative, seeking variation of the amount of the fine

V. Costs


*      Language of the case: English.


1      This judgment is published in extract form.