Language of document :

Order of the President of the General Court of 12 July 2011 - Emme v Commission

(Case T-422/10 R)

(Interim measures - Competition - Commission decision imposing a fine - Bank guarantee - Application to suspend the operation of a measure - Financial loss - No exceptional circumstances - No urgency)

Language of the case: Italian

Parties

Applicant: Emme Holding SpA (Pescara, Italy) (represented by: G. Visconti, E. Vassallo di Castiglione, M. Siragusa, M. Beretta and P. Ferrari, lawyers)

Defendant: European Commission (represented by: B. Gencarelli, V. Bottka and P. Manzini, Agents)

Re:

Application to suspend the operation of Article 2 of Commission Decision C (2010) 4387 final of 30 June 2010 relating to a proceeding under Article 101 TFEU and Article 53 of the EEA Agreement (Case COMP/38.344 - Prestressing steel) and to dispense the applicant from the obligation to provide a bank guarantee so as to avoid immediate recovery of the fine imposed under Article 2 of that decision.

Operative part of the order

1.    The application for interim measures is dismissed.

2.    Costs are reserved.