Order of the President of the General Court of 10 June 2014 – Schmiedag v Commission

(Case T-183/14 R)

(Interim measures – State aid – National promotion of electricity production from a renewable source – Commission decision to open formal investigation procedure in respect of State aid – Application for suspension of operation of a measure – Urgency – Fumus boni juris)

Language of the case: German

Parties

Applicant: Schmiedag GmbH (Hagen, Germany) (represented by: H. Höfler, C. Kahle and V. Winkler, lawyers)

Defendant: European Commission (represented by: T. Maxian Rusche and R. Sauer, Agents)

Re:

Application for suspension of the legal effects of the decision by which the Commission opened a formal investigation procedure in respect of State aid concerning the German law on renewable energy.

Operative part of the order

    The application for interim measures is dismissed.

    The judgment of 7 April 2014 in Case T-179/14 R Schmiedag v Commission is set aside.

3.    Costs are reserved.