Language of document :

Order of the General Court of 13 September 2017 — Germany v Commission

(Case T-116/10) 1

(Action for annulment — ERDF — Reduction of financial assistance — North Rhine-Westphalia Programme — Failure to comply with the time-limit for adopting a decision — Infringement of essential procedural requirements — Action manifestly well founded)

Language of the case: German

Parties

Applicant: Federal Republic of Germany (represented initially by J. Möller, subsequently by J. Möller and T. Henze, acting as Agents, and U. Karpenstein, lawyer)

Defendant: European Commission (represented by: B.-R. Killmann, B. Conte and A. Steiblytė, acting as Agents)

Re:

Application based on Article 263 TFEU seeking the annulment of Commission Decision C(2009) 10675 of 23 December 2009 reducing the assistance granted to the Objective 2 North Rhine-Westphalia Programme (1997-1999) in the Federal Republic of Germany from the European Regional Development Fund (ERDF) under Commission Decision C(97)1120 of 7 May 1997.

Operative part of the order

1.    Commission Decision C(2009) 10675 of 23 December 2009 reducing the assistance granted to the Objective 2 North Rhine-Westphalia Programme (1997-1999) in the Federal Republic of Germany from the European Regional Development Fund (ERDF) under Commission Decision C(97)1120 of 7 May 1997 is annulled.

2.    The European Commission is ordered to pay the costs.

____________

1     OJ C 134, 22.5.2010.