Language of document :

Judgment of the Court of First Instance (First Chamber) of 27 September 2006 - Ferriere Nord v Commission

(Case T-153/04) 1

(Competition - Fine - Breach of Article 81 EC - Powers of the Commission in respect of the enforcement of sanctions - Limitation period - Articles 4 and 6 of Regulation (EEC) No 2988/74 - Admissibility)

Language of the case: Italian

Parties

Applicant: Ferriere Nord SpA (Osoppo, Italy) (represented by: W. Viscardini and G. Donà, lawyers)

Defendant: Commission of the European Communities (represented by: A. Nijenhuis and A. Whelan, acting as Agents, and by A. Colabianchi, lawyer)

Re:

Annulment of the Commission decisions notified by letter of 5 February 2004 and by facsimile of 13 April 2004 concerning the outstanding balance of the fine imposed on the applicant by Commission Decision 89/515/EEC of 2 August 1989 relating to a proceeding under Article 85 of the EEC Treaty (IV/31.553 - Welded steel mesh) (OJ 1989 L 260, p. 1)

Operative part of the judgment

The Court:

1.    Annuls the Commission decisions notified by letter of 5 February 2004 and by facsimile of 13 April 2004 concerning the outstanding balance of the fine imposed on the applicant by Commission Decision 89/515/EEC of 2 August 1989 relating to a proceeding under Article 85 of the EEC Treaty (IV/31.553 - Welded steel mesh);

2.    Orders the Commission, in addition to bearing its own costs, to pay those of the applicant.

____________

1 - OJ C 168, 26.6.2004.