Language of document : ECLI:EU:T:2017:465





Order of the President of the General Court of 4 July 2017 —
Institute for Direct Democracy in Europe v Parliament

(Case T118/17 R)

(Interim proceedings — Institutional law — European Parliament — Decision awarding a grant to a political foundation — Suspension of prefinancing — Obligation to provide a bank guarantee — Application for interim measures — No urgency)

1.      Application for interim measures — Suspension of operation of a measure — Interim measures — Conditions for granting — Prima facie case — Urgency — Serious and irreparable damage — Cumulative nature — Order of examination and method of verification — Discretion of the court hearing the application for interim relief — Balancing of all the interests involved

(Arts 256(1) TFEU, 278 TFEU and 279 TFEU; Rules of Procedure of the General Court, Art. 156)

(see paras 17, 19, 20)

2.      Application for interim measures — Suspension of operation of a measure — Interim measures — Conditions for granting — Urgency — Serious and irreparable damage — Burden of proof — Financial loss — Obligation to provide concrete and precise indications, supported by detailed documentary evidence — Situation which could jeopardise the existence of the applicant company or irremediably alter its position in the market

(Arts 256(1) TFEU, 278 TFEU and 279 TFEU; Rules of Procedure of the General Court, Art. 156(4) and (5))

(see paras 31, 44, 47, 49)

3.      Application for interim measures — Suspension of operation of a measure — Suspension of operation of the obligation to provide a bank guarantee in the context of the financing of a political foundation — Conditions for granting — Exceptional circumstances — Impossible to obtain a bank guarantee — Extent of the burden of proof

(Art. 278 TFEU; Rules of Procedure of the General Court, Art. 156(4))

(see paras 33-38)

4.      Application for interim measures — Formal requirements — Submission of applications — Brief summary of the pleas in law on which the application is based — Pleas in law not set out in the application and pleadings — General reference to other documents — Inadmissibility

(Arts 278 TFEU and 279 TFEU; Rules of Procedure of the General Court, Art. 156(4) and (5))

(see paras 43, 45)

Re:

APPLICATION pursuant to Articles 278 and 279 TFEU for the grant of interim measures, seeking, first, the suspension of operation of Parliament Decision FINS-2017-28 of 15 December 2016 concerning the funding allocated to the applicant in so far as it suspends payment of prefinancing, second, exemption from the requirement to provide a bank guarantee as a condition for prefinancing and, third, an order that the Parliament pay to the applicant the prefinancing amount.

Operative part

1.

The application for interim measures is dismissed.

2.

Costs are reserved.