Language of document :

Order of the President of the General Court of 4 March 2024 – Penta system v Commission

(Case T-43/24 R)

(Interim relief – Public supply contracts – Tendering procedure – Rejection of a tenderer’s bid and award of the contract to another tenderer – Application for suspension of operation of a measure – Failure to comply with procedural requirements – Inadmissibility)

Language of the case: English

Parties

Applicant: Penta system Srl (Modugno, Italy) (represented by: K. Duchoňová, lawyer)

Defendant: European Commission

Re:

By its application based on Articles 278 and 279 TFEU, the applicant seeks the suspension of operation of, first, the decision of the European Commission of 27 November 2003, by which it rejected the bid it submitted in the context of the tender procedure JRC/IPR/2022/RP/1912, entitled ‘Radioactive Waste Management Facilities Operations Maintenance (RAMA) Services’, and, secondly, the decision of the Commission by which it awarded the contract to another tenderer.

Operative part of the order

1.    The application for interim measures is dismissed.

2.    The costs are reserved.