Language of document :

Order of the President of the General Court of 8 December 2014 — STC v Commission

(Case T-355/14 R)

(Interim measures — Public services contracts — Tendering procedure — Construction and maintenance of a tri-generation plant — Rejection of tender submitted by a tenderer — Application for interim measures — Prima facie case not made out)

Language of the case: Italian

Parties

Applicant: STC SpA (Forlì, Italy) (represented by: A. Marelli and G. Delucca, lawyers)

Defendant: European Commission (represented by: L. Cappelletti, L. Di Paolo and F. Moro, acting as Agents)

Re:

In essence (i) an application to suspend the operation of the Commission’s decision of 3 April 2014 in which the Commission rejected the tender submitted by STC in tendering procedure JRC IPR 2013 C04 0031 OC for the construction and maintenance of a tri-generation plant with a gas turbine on the Ispra (Italy) site of its Joint Research Centre (JRC) (OJ 2013/S 137-237146), the decision in which the Commission awarded the contract to CPL Concordia and consequently all other subsequent decisions; and (ii) an application to suspend the operation of the Commission’s decision to refuse the request for access to the documents and an interim measure to allow the full exercise of the right of access to the tender documents.

Operative part of the order

1.    The application for interim measures is dismissed.

2.    Costs are reserved.