Order of the President of the General Court of 27 February 2012 —
Dagher v Council
(Case T-‑218/11 R)
Interim measures — Common foreign and security policy — Restrictive measures adopted having regard to the situation in Côte d’Ivoire — Withdrawal from the list of persons concerned — Application for interim measures — No need to adjudicate
Application for interim measures — Suspension of operation of a measure — Request which has become devoid of purpose — No need to adjudicate (Art. 278 TFEU) (see paras 7, 8, 10)
Re:
| Firstly, application for an order that the Council and the Italian Republic issue a visa to the applicant; secondly, application for suspension of operation of Council Implementing Regulation (EU) No 85/2011 of 31 January 2011, implementing Council Regulation (EC) No 560/2005 of 12 April 2005 imposing certain specific restrictive measures directed against certain persons and entities in view of the situation in Côte d’Ivoire (OJ 2005 L 28, p. 32) and Council Decision 2010/656/CFSP of 29 October 2010 renewing the restrictive measures against Côte d’Ivoire (OJ 2010 L 28, p. 60); and, thirdly, a claim for damages in compensation for the loss allegedly suffered by the applicant. |
Operative part
1. | | There is no longer any need to adjudicate on the application for interim measures. |